| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:12am On Feb 15, 2021 |
JerrCa:Thank you Sir. |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:24am On Feb 15, 2021 |
We will start lifting blocks onto this decking as from this morning, while sourcing for more blocks, more pictures from this site later. |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 11:14pm On Feb 15, 2021 |
Lifting blocks to the top of this decking.........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 11:17pm On Feb 15, 2021 |
We plan to clear a portion of the compound and start a security man house in this compound by tomorrow......... |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 7:07am On Feb 17, 2021 |
The back of this house.......
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 9:19am On Feb 18, 2021 |
We have started forming the walls of this house........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 9:21am On Feb 18, 2021 |
More.....
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 9:25am On Feb 18, 2021 |
Buying more vibrated blocks this morning.......
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by Attah00002(m): 1:22pm On Feb 18, 2021 |
Morning sir.thanks so much for the great work and your intensive contribution to property section sir. Your pikin are following sir. I have one question I want to ask sir. I have been following your thread for some time now sir. In the pic below,you use 3 block after the lintel(beam) before the decking(first floor slab) but some other thread you use 2 block after the lintel before the decking. WHY? Thank you sir.
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by Attah00002(m): 1:33pm On Feb 18, 2021 |
Attah00002:I mean this thread https://www.nairaland.com/1907636/port-harcourt-luxury-flats/7
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 9:02am On Feb 19, 2021 |
Attah00002:Clients preference. In most of the drawings I have built, the specifications always reads 2 blocks before the decking beam, but a lot of home owners are now loving an additional 300 mm on the top of their building plans and we have to give them what they want, as long as it's structurally safe to do so. But remember, the clients will always pay for the difference in the additional line of blocks with workmanship. Note also that this have a few more implications in the finish, cost of finish materials and workmanship will rise up slightly. |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 7:34pm On Feb 20, 2021 |
We have continued to raise the block walls of this house.........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 7:48pm On Feb 20, 2021 |
Lobby..........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 7:49pm On Feb 20, 2021 |
Walking upstairs.........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 7:54pm On Feb 20, 2021 |
More from upstairs........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 8:01pm On Feb 20, 2021*. Modified: 8:21pm On Feb 20, 2021 |
Balconies........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 10:08pm On Feb 20, 2021 |
We have started digging the foundation for a security post.......
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by sonnie10: 8:44pm On Feb 21, 2021 |
spyder880:Did you use 16mm or 12mm for the decking? Do you remember how many pieces? |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:20am On Feb 22, 2021 |
sonnie10:This is a very big decking and and as such, needed adequate reinforcement. We used; 16mm rods 130 12mm rods 350 10mm rods 30 8mm rods 50 Rolls of binding wire 2 1/2 We also spent up to 70k on transportation and loading charges. |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by sonnie10: 6:06am On Feb 22, 2021*. Modified: 12:35pm On Feb 22, 2021 |
spyder880:Thank you a lot |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 8:32am On Feb 22, 2021 |
We return to this site today to continue our works with the upper floor....... We will also move fast on the security man house |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by folmus: 4:51pm On Feb 22, 2021 |
spyder880:Looking forward to seeing more pics |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 6:01pm On Feb 22, 2021 |
folmus:Certainly, there will be many more pictures from this and other sites tomorrow. |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:19pm On Feb 23, 2021 |
Let's start the concrete blinding for this security man house.......... we plan to start the foundation blocks by tomorrow morning.
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:22pm On Feb 23, 2021 |
Then we started raising the fence of this compound..........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by mixratio(m): 6:38pm On Feb 23, 2021 |
Chief Spyder, well-done sir. I always enjoy your threads. very educative and straightforward. I have a question though, on your suspended slab/decking, why did you use to spread that nylon? Asides from preventing leakage of concrete, does it have any other advantages? thanks |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 7:07pm On Feb 23, 2021 |
mixratio:Apart from holding the concrete from slipping through the cracks, the nylon performs a few other functions. First is that it helps to prevent early water loss in the concrete slab cast, prolonging moisture retention, thereby helping the curing process of the slab. Another advantage is that it preserves my wood. When I use nylon to separate the wood and the raw cast, it tends to prolong the durability of the wood, making it possible for me to reuse the wood. |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by mixratio(m): 4:48pm On Feb 24, 2021 |
spyder880:Thanks for your prompt response. Making the formwork reusable was an eye opener for me |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by RobbStark(m): 12:21pm On Feb 25, 2021 |
spyder880:This stair needs to have a good anchorage at the landing deck. Great job |
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:14am On Feb 27, 2021 |
Let's continue with the fence foundation and foundation blinding..........
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:18am On Feb 27, 2021 |
Starting work on the security man house
|
| Re: The Making Of The "Contemporary 6 Bedroom Duplex " In Anambra by spyder880(op): 5:23am On Feb 27, 2021 |
Back of the house, and some pictures from the top, we have completed the iron reinforcement works for the upper floors.
|