Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 4:02pm On Apr 01, 2025 |
Good day ladies and Gentlemen, hope you are enjoying the holiday? |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 4:00pm On Apr 01, 2025 |
Good day everyone, hope you are making the most of the holiday? |
Properties › Re: Need HDF Doors?: Check Out Our Custom HDF Doors With Edge Protection Material. by Procontractor(op): 4:08pm On Mar 30, 2025 |
Quality before aesthetics, fitted with edge protection material. Warranty is minimum of 30 years! |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 4:04pm On Mar 30, 2025 |
Happy Eid-el-fitr to all Muslim faithfuls!
Our site wil be closed on Monday and Tuesday to allow all muslim faithfuls in my team to break their fast.
Gozok... |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 4:03pm On Mar 30, 2025 |
Happy Eid-el-fitr to all Muslim faithfuls!
Our site wil be closed on Monday and Tuesday to allow all muslim faithfuls in my team to break their fast.
Gozok... |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 4:13pm On Mar 29, 2025 |
Recovery of re-usable formwork is paramount on this project considering the economic situation.
Here on block 3 we have depropped second floor slab ready for use on the third floor...
|
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 4:10pm On Mar 29, 2025*. Modified: 5:38pm On Mar 29, 2025 |
We have reached a milestone on this block 2
Casting of second floore slab at 100%
Preparation of third floor column reinforcements at 100%
Setting out and kickers to follow...
|
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 8:37am On Mar 27, 2025 |
Update coming soon |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 8:37am On Mar 27, 2025 |
Good day everyone
Update coming soon... |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 11:14pm On Mar 25, 2025*. Modified: 5:19am On Mar 26, 2025 |
Update on block 1
We have commenced pilling operation on this block
In pictures...
|
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 11:12pm On Mar 25, 2025 |
Good evening Ladies and Gentlemen
Here is update for block 4
Shuttering of GF columns formwork ...done
Casting of GF columns ......done
|
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 2:38am On Mar 25, 2025 |
Stay tuned for more updates on block 4 today |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 2:37am On Mar 25, 2025 |
Stay tuned for updates on commencement of pilling in block 1 today |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 9:45pm On Mar 24, 2025*. Modified: 2:36am On Mar 25, 2025 |
In pictures...
|
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 9:41pm On Mar 24, 2025 |
We have updates on block 1
Pilling rig is ready for machine
Materials arrived today for commencement of pilling tomorrow... |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 9:37pm On Mar 24, 2025 |
More updates on block 4 in pictures....
|
Properties › Re: Need HDF Doors?: Check Out Our Custom HDF Doors With Edge Protection Material. by Procontractor(op): 6:24pm On Mar 23, 2025 |
Have you seen our custom made edge protected doors? You will love it! |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 6:20pm On Mar 23, 2025 |
More updates coming soon... |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 6:20pm On Mar 23, 2025 |
We have achieved a major mile stone on block 4
Pilling operation at 100%
Pile cropping to required level at 100%
Excavation to required level at 100%
Cutting bending and tying of pile cap reinforcements at 100%
Foundation beams at 100%
Starters at 100%
Formwork to foundation at 100 %
Mechanical and electrical sleeves, ducts at 100%
Concreting of pile caps and GB...done
Filling to make up level...done
DPM at plinth level....done
Mesh topping at plinth level...done
Concreting of Gf slab....done
Kickers, GF columns reinforcements...done
Formwork to GF columns...done
Reinforcement to shear wall...done
Concreting to GF columns and shear wall....done
In pictures
|
Properties › Re: Need HDF Doors?: Check Out Our Custom HDF Doors With Edge Protection Material. by Procontractor(op): 8:17pm On Mar 22, 2025 |
Custom doors you can trust... |
Properties › Re: Need HDF Doors?: Check Out Our Custom HDF Doors With Edge Protection Material. by Procontractor(op): 2:00pm On Mar 22, 2025 |
Our doors are unbeatable |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 1:56pm On Mar 22, 2025 |
Pile point setting out block 1
|
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 1:54pm On Mar 22, 2025 |
Striking of second floor columns formwork, block 3...
|
Properties › Re: Need HDF Doors?: Check Out Our Custom HDF Doors With Edge Protection Material. by Procontractor(op): 11:38pm On Mar 21, 2025 |
Order our custom HDF doors and save yourself the stress of replacing doors after few years. |
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 11:32pm On Mar 21, 2025*. Modified: 1:49pm On Mar 22, 2025 |
Formwork and casting of block 3 second floor columns...
|
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 11:30pm On Mar 21, 2025 |
More updates coming tomorrow, stay tuned and God bless. |
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 10:15pm On Mar 20, 2025*. Modified: 11:25pm On Mar 21, 2025 |
More updates on block 2:
Reinforcement works to second floor slab, beams and ribs @ 100%
Polystyrene arrangement @ 100%
MEP @ 100%
Approval from relevant authorities obtained
Levelling for casting done, floor ready to cast penultimate next week
Pictures...
|
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 9:59pm On Mar 20, 2025*. Modified: 4:03am On Mar 22, 2025 |
More updates on block 3:
Formwork to second floor slab @ 100%
Reinforcement to beams, ribs and slabs @ 100%
Polystyrene arrangement @ 100%
MEP @ 100%
Stage certifications by LABSCA done.
Concrete works for block 2 first floor slab done
Kickers for second floor column done
Reinforcement works for second floor column @ 100%
Let's look at pictorial representation
Modified: 1st picture clearly shows general progress in block 3 not 2 as the picture embedded text depicts. Block 2 is on the far left in the picture.
|
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 11:03am On Mar 20, 2025*. Modified: 5:22pm On Mar 30, 2025 |
Still on block 3 second floor slab and beams formwork...
|
Properties › Re: Construction Diary Of Our 4 Blocks 6 Storey Residential Buildings Block 2 & 1 by Procontractor(op): 11:01am On Mar 20, 2025 |
On to the next mile stone for block 2:
Our next deliverables are;
1) Casting of 1st floor columns and striking of formwork
2) Formwork to second floor slab and beams
3) Reinforcements to 2nd floor beams and slabs
4) MEP
5) concreting
So far we have achieved items (1) to (5)
Labsca sign off and consultants indemity document obtained. Concreting to take place next week God willing
|
Properties › Re: Construction Diary of Our 4 Blocks Of 6 Storey Residential Buildings Block 3 & 4 by Procontractor(op): 9:16pm On Mar 19, 2025*. Modified: 11:02am On Mar 20, 2025 |
More on block 3 second floor slab formwork ...
|