Formwork to second floor slab block 3
|
Concreting has been done for block 2 first floor slab, also. Next stage is setting out at 1st floor level, casting of kickers and standing of first floor column reinforcements and then formwork.
|
Casting of 1st floor columns block 3 In pictures...
|
Casting of kickers for 1st floor columns block 3 Reinforcement to 1st floor columns block 3 Formwork to 1st floor columns block3 In pictures...
|
Block 2 first floor Formwork to beams and slab @ 100% Bending and tying of beam reinforcements @ 100% Also reinforcements for ribs at 100% Mesh overlay ......done MEP .......done
|
We recently embarked on demolition exercise to pave way for commencement of construction activities on block 1, the hitherto existing structure has been brought down and rubbles evacuated.
|
Pilling operation block 4 in picture Modified: Pictures also shows pile integrity test and preparation pilling of pilling rig for action in block 4
|
Next update on block 3, casting of 1st floor slab and beams
|
Next update for this block is formwork to 1st floor slab and beams
|
I have decided to update blocks 1 & 2 together and also blocks 3 & 4 under the existing two threads ealier created. I see this as a better approach so we can easily pick up where we left off. For clarity each picture will have an embedded text stating which block it is. This thread therefore will cover blocks 3 & 4 |
As a matter of fact I have equally considered it time consuming to create separate threads for all these blocks, I will now henceforth update this project under this thread. Any better opinion is however welcomed. |
Good evening ladies and Gentlemen. Apologies for my inability to update this thread for the past 5 months or so, a lot has happened since then and we have been able to forecast as well as surmount the challenges as is expected of a professional. The uncontrolled rise in cost of construction materials was highly unprecedented and has forced the developer to do some review, fluctuation wise and all which requires time, necessary deliberations and approvals from stakeholders. This hurdle has been surmounted and projects is progressing timeously. General Progress Report Block 3 Last update on block 3 was MEP for first floor, currently we are at the third floor for this block Block 2 Last update was on ground floor slab, currently we are set to cast the second floor of this block and of course proceed with the 3rd suspended floor. Block 1 Demolition of existing structure done Bulk excvation done preparatory for pile point setting out. Pile points setting out done Pilling to commence immediately Block 4 Last update was on the pilling operation, we have since completed the pilling and the neccessary load tests, pile caps and ground beams have been cast. Ground floor slab also done. This means we have completed foundation stage for this block. Currently, cutting, bending and tying of ground floor column reinforcements for this block is at 100%. We have been cleared by LABSCA to proceed with formworks and casting of the columns. This means that we have maintained traction on all the block despite the challenges. Pictures will follow Thanks for your time GOZOK.. Modified... |
We are prime consultants and have undertaken notable and challenging jobs. If you have plans to put up a structure or structures , don't hesitate to contact Gozok. Our team are ever ready to deliver your drawings to any location within the country. Except Sambisa ![]() |
Good day everyone Our doors are unique with edge protection material, get weary of changing your doors 4 to 5 years! |
If you love unique and durable doors,...don't hesitate to reach out. |
Get in touch for ypur working drawings with respective seals. Delivery is nation wide. |
Good evening great people. We have an update on block 3 We have commenced: 1) Mechanical and electrical conduits 2) Marking of Ducts on as designed 3) fiing of water hose ducts for fire fighting.... Pictures
|
Good evening everyone. We have achieved a milestone on block 2 1) Shuttering of column formwork...done 2) casting of columns and striking of formwork...done 3) Laying of reinforcements for Lift Shaft...done
|
Our doors are magical... |
Good evening everyone, contact us if you are in the conception and design stage of your project. We will furnish you with complete working drawing vis a vis: Architectural working drawings Structural drawing Electrical and mechanical All with Coren Seal ready for Approval in your respective state building control agency. Soft copies of all drawings to be sent in pdf format to your mailbox. Delivery nation wide... |
michlins:Happy to hear that sir... stay tuned. |
Good evening Distinguished Ladies and gentlemen. Trust your weekend went as planned? We have an update on this block. We are finally out of the foundation, see pictures below.
|
First floor slab reinforcements arrangements. The detail incorporates both rib and solid slab.
|
Compaction and damproofing at plinth level..
|
Our doors are uniquely crafted with edge protection material to reduce wear and tear due to prolonged use. |
DM for your complete working drawings with respective seals... |
We bring innovation to construction. |
Full working drawings with seal at your finger tips, to be delivered to you anywhere in the country. Soft copy in pdf format also to be delivered to your mail. Get in touch. |
Race against time... Filling to make up level as well as striking of formwork are going on simultaneously here! Most of our activities on this project are on CRITICAL PART and requires zero float! Watering and compaction to follow... In picture...
|
Main beams for block 3 dropped to level... Laying of reinforcements for ribbs ongoing... Plus laying of reinforcements for areas with solid slab equally ongoing. Considering the dynamics of this project, the sructural design incorporated both ribbed and solid slabs for all floors according to code provisions and requirements. Attention to details is the hall mark of any successful project. Pctures...
|
Our doors are selling fast... |
Get in touch for your complete working drawings with Coren seal... |
1 2 3 4 5 6 7 8 ... 38 39 40 41 42 43 44 45 46 (of 110 pages)
, don't hesitate to contact Gozok. Our team are ever ready to deliver your drawings to any location within the country. Except Sambisa 