PropertiesRe: Building A Bungalow In Lagos by trust101: 2:55pm On Sep 08, 2012
grin grin

PropertiesRe: Building A Bungalow In Lagos by trust101: 2:20pm On Sep 08, 2012
maybe more later!!

PropertiesRe: Building A Bungalow In Lagos by trust101: 2:17pm On Sep 08, 2012
happy weekend

PropertiesRe: Building A Bungalow In Lagos by trust101: 6:23pm On Sep 07, 2012
grin

PropertiesRe: Building A Bungalow In Lagos by trust101: 6:20pm On Sep 07, 2012
spyder880: Good, developements. Those Greek pillars always look nice.
Thank you Oga sir grin

PropertiesRe: Building A Bungalow In Lagos by trust101: 5:42pm On Sep 07, 2012
More

PropertiesRe: Building A Bungalow In Lagos by trust101:
No work on site yesterday.2X4x12 X50 @450= #22500 + transportation #5,000 = #27,500
4" nail 1 bag @ #5000.

PropertiesRe: Building A Bungalow In Lagos by trust101: 4:41pm On Sep 04, 2012
grin grin grin grin

PropertiesRe: Building A Bungalow In Lagos by trust101: 6:30pm On Sep 03, 2012
grin

PropertiesRe: Building A Bungalow In Lagos by trust101: 3:57pm On Sep 03, 2012
pictures.

PropertiesRe: Building A Bungalow In Lagos by trust101: 3:50pm On Sep 03, 2012
today's pictures.

PropertiesRe: Building A Bungalow In Lagos by trust101: 10:38pm On Sep 01, 2012
No work was done today and the person to take the pictures of what was done yesterday isn't around.
Monday we shall all have some pictures to enjoy grin

PropertiesRe: Building A Bungalow In Lagos by trust101: 12:30am On Sep 01, 2012
spyder880: Thank you bros, you are really doing something great here. Loving it so much.
You are welcome and thank you too for your contributions.
PropertiesRe: Building A Bungalow In Lagos by trust101: 2:16pm On Aug 31, 2012
spyder880: Depends on you, if you have the time and knowledge then you can buy and give to the builder. The stress is on the knowledge. But this sometimes saves the builder the hassles of explaining why some faults happened with the construction, he cannot be blamed for faulty materials if the owner is the one that bought. Depending on a lot of other factors sha.
Thanks.That is why you are the best.
PropertiesRe: Building A Bungalow In Lagos by trust101: 12:33pm On Aug 31, 2012
blank: I have a question.

Is it better to buy your own materials and give the builder or should you leave it for them to do so?

Learning.
MY THINKING IS IF YOU WANT THE BEST BETTER BUY IT YOURSELF AND I DON'T WORRY IF SOME GETS MISSING.(YOU HAVE TO KEEP YOUR EYES ON IT).
THANKS.
PropertiesRe: Building A Bungalow In Lagos by trust101: 12:26pm On Aug 31, 2012
blink182: Wonderful
THANKS AND I HOPE YOU ARE ENJOYING AND LEARNING FORM THE BEST grin grin (spyder) grin
PropertiesRe: Building A Bungalow In Lagos by trust101: 12:24pm On Aug 31, 2012
spyder880: I guess these wood are 12ft in lenght? Because some saw mills cut 2x4 in 18ft sizes which will change the overall estimated quantity. Well done.
YES IS 12FT.
THE PRICE IS THE BEST I COULD FIND AROUND.
THANKS FOR YOUR KIND WORDS.
MY PHOTO GUY ISN'T AROUND TODAY BUT WORK IS GOING ON SITE.
THANKS.
PropertiesRe: Building A Bungalow In Lagos by trust101: 11:42pm On Aug 30, 2012
more tomorrow or next

PropertiesRe: Building A Bungalow In Lagos by trust101: 11:37pm On Aug 30, 2012
more!!

PropertiesRe: Building A Bungalow In Lagos by trust101: 11:33pm On Aug 30, 2012
more!

PropertiesRe: Building A Bungalow In Lagos by trust101: 11:25pm On Aug 30, 2012
roof work

PropertiesRe: Building A Bungalow In Lagos by trust101: 8:32pm On Aug 29, 2012
more pictures tomorrow!!

PropertiesRe: Building A Bungalow In Lagos by trust101: 8:28pm On Aug 29, 2012
some Carpentry work

PropertiesRe: Building A Bungalow In Lagos by trust101: 2:10am On Aug 28, 2012
more pictures later in the week.

PropertiesRe: Building A Bungalow In Lagos by trust101: 2:07am On Aug 28, 2012
after painting

PropertiesRe: Building A Bungalow In Lagos by trust101: 2:00am On Aug 28, 2012
more

PropertiesRe: Building A Bungalow In Lagos by trust101: 1:38am On Aug 28, 2012
woods!!!

PropertiesRe: Building A Bungalow In Lagos by trust101:
Wood for the roofing akun,
2x4X12 #450 x 340 = #153,000
2x6X12 #750 x 80 = #60,000
3x4X12 #700 x 20 = #14,000
2x2X12 #250 x 400 = #100,000
4"Nails #450X2 = #9000 + 1 bag #5000 =#14000
3" 1/2 #2250
Some chemicals to paint the wood before using =#24,100 + kerosene @#135 per liter x 65 liters = #8775
Transportation #30,000
Total #406,125

PropertiesRe: Automatic Gate, Usin Remote Control by trust101: 2:08am On Aug 20, 2012
jobontech: MAIN FUTURES
24 MOUNTH GARANTY.
BATTRY BACKUP.
RAPID OPPRATING SPEED.
INTELIGENT SPEED CONTROL.
SMOOTH ACCELERATION,AND DECCELERATION.
GATE SPEED 22-26M/MIN.
DAILY OPPRATION - MAX750.
ACCESRIES AND PART ALSO AVAILABLE.

ANY OTHER THING YOU NEED TO KNOW CONTACT JOBONTECH,
Email: bonnyonyema@yahoo.com. jobontech@yahoo.com.
Phone: +234 8023640637. +234 8098540824. +017378380.
hello there,i will like to know why you think everybody should be calling you to know
your price and what if i call you and your price isn't good for me? i think
many people have the same view so do yourself a favor and paste your price.
thanks
PropertiesRe: Building A Bungalow In Lagos by trust101: 3:23pm On Aug 15, 2012
blank: How much will a reasonable size gate cost?
check this out

https://www.nairaland.com/716689/fence-gates-pictures-prices
PropertiesRe: Building A Bungalow In Lagos by trust101: 2:59pm On Aug 15, 2012
spyder880: Awesome! Bros, welcome to the builder's club because you over qualify sef :Dlovely breakdown of figures.
grin grin
PropertiesRe: Building A Bungalow In Lagos by trust101:
trust101: The cost breakdown should be ready by next week grin
Prayer :#10,000

Cleaning of land : #20,000

Food for prayer #8,000

Architectural drawing @ #35,000

Omo onile (Area boys): #40,000

Omo onile family #200,000

Pegging :#5,250

water #1200x 15 = #18,000

water #1500x 1 = #1500

Digging of foundation cant remember: #40,000 or less.

Supervision of foundation digging/Architect drawing re-measuring of building @#16,000

Granite 30 tons: #130,000

Granite 34 tons: #132,000 + #3000 Omo onile =#135,000

Sharp Sand 155 tons:#316,000

Cement 120 bags: #216,000

packing of cement with transportation :#15,000

cement 50 bags @ #2070x50= #103,500

Bricklayer work from foundation/german floor/blocks setting/lintel/level =#470,000.

Carpenter workmanship from foundation/german floor/lintel/level= #50,000

Iron rod 12mm 18.4lengths,rings and binding wire for pillar and casket for foundation : #36,800

Broken blocks for filling of hole before german floor with labor:#6000

Welder workmanship form foundation/lintel to 25 pillars and 23 caskets for the pillars:#25,000

Iron rod 12mm 32.5lengths for 25 pillars #1600x 32.5 = #52,000

lintel iron rod 12mm,9"rings,wire #147,000

filling sand 10 tons @ #8500 x 26 =#221,000 + soak-away sand + 10 tons on my land.

packing of filling sand #1500 x 26 = #39000

Digging of soak-away #45,000

packing of soak-away filling sand #10,000

foundation 9" blocks #150 x 1500 = #225,000

Plank 1X12 @ #740 x 50 =#37,000 + transportation #3,000 = #40,000

Plank 1X12 @ #800 x 50 =#40,000 + transportation #5,000 = #45,000

Rama of filling sand before german floor #10,000.

Building blocks to lintel 9"#150 x 2700 = #405,000

Block setting to level 9" @ #170 x 1400 = #238,000

Water @ #1500x 8 = #12,000

Big soak-away 9" blocks @ #170x 300 = #51,000

Small soak-away 6" block @130x 70= #9100

Cement with transportation @ #2070x 8= #16,560

Plaster sand 10 tons @ #16,000

Bricklayer/Carpenter/welder #24,000/#7,000/#6,000 = #32000

Pillars designed 5 workmanship @ #40,000 (i bought cement)

Cement for pillars design @ #2070x 20 =#41,400

Wood 2x3x12 @ #350x 30 = #10,500

Tip for the bricklayer boys #15,000

Tip for carpenter boys #6,000

Electrical pipe 45,000

Electrician workmanship for laying the pipes #25,000

Transportation to the site @#50,000

Total cost:#3,743,610




Roof gutter cost breakdown,


Carpenter #70,000

Wood 2x3x12 @ #290 x 80 = #23,200

Nails #10,000

Granite 15tons @ #60,000

Plank 1x12x12 @ 740 x 80 = #59,200

Plank 1x12x12 @ 740 x 20 = #14,800

Cutting to sizes:2,4,6inch #9000 + the design @60x150 #9000 = #18,000.

Cutting 5 to sizes 1 and 2inch to 35 pieces @#50 = #1750

plywood 12 @ #1,700 = #20,400

Transportation #17,000

Welder #65,000

Iron rod 12mm 3.5feet x 532 = 46.55lengths@ #1750 per length = #81,462

Iron rod 12mm for beam 36lengths@ #1750 per length = #63,000

Iron rod 10mm 33lengths@ #1350 = #44,550

Drainage Pipe @#5000

Trans portion to site:#20,000

Cement @2000 X 54 = #108,000

Water @1500 X 5 = #7,500

Food for laborer @ #10,000

Casting of roof gutter laborer #60,000

Plastering the inside of the roof gutter cement 15 bags @#2,000 = #30,000

Bricklayer plastering inside of roof gutter @35,000

Water @1500 X 2 = #3,000

Plaster sand 10 tons @#16,000

sharp sand 10 tons @#25,000

Transportation to site:#7,000



Total amount spent on roof gutter is = #874,862

Total amount spent on building is = #3,743,610

Total amount spent is = #4,618,472