Construction Of A 3-Bedroom Bungalow In PortHarcourt by YouGood(m): 8:03pm On Feb 17, 2020 |
We will be constructing a 3-bedroom bungalow in Port Harcourt, and the Engineer will be posting updates here including the materials, quantities and costs. 1 Like |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:53am On Feb 18, 2020 |
11/03/2020. Today's progress, casting of foundation. 13/03/2020. Today's progress, casting of foundation completed. Material used ,32 bags of cement, labour cost(per bag #1,500* 30bags,with 2no bricklayer used ,@ fixed cost to achieve casting of the foundation. 1no. Shape sand #30,000naira, 1no 3/8 #22,000naira. 3no truck of laterite,30pieces of 1/12 @#1,800, 2/2 @#350naira 10pieces ,half bag of 4' inche nails @#2,500 naira , water 10 drums of @#1000naira per drum, 12lengths of y12 @#2,500naira per 1, 3'inche nails(half bag)@ #2,500naira.
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 2:45pm On Feb 21, 2020 |
9/03/2020. Today's progress, carpenter getting prepared for boarding of foundation (dpc.) 30 pieces of 1/12 wood @#1,800 naira , 2/2 wood @#350 naira per one and half bag of 3'inches nails @ #2,500 naira. 1 Like
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Godisgreatest1: 2:57pm On Feb 21, 2020 |
Charles4wokoma:What size of blocks for foundation?. 1 Like 1 Share |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by val15: 5:39pm On Feb 21, 2020 |
Following |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by ovoP(m): 9:40pm On Feb 21, 2020 |
How much would such a project cost? 1 Like |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 10:15pm On Feb 24, 2020 |
9/03/2020. Today's progress. Boarding of foundation (dpc.) 1no.capenter , 30 pieces of 1/12@#1,800naira, 10pieces of 2/2@ #350naira each, 3'inches nails @#2,500naira and 12 lengths of y12@#2,500 per one. See receipt of payment below
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 4:47pm On Feb 25, 2020 |
9/03/2020. Today's progress, boarding of foundation (dpc.) 1 carpenter used, 30 pieces of 1/12 wood@#1,800 naira each, 10pieces of 2/2 wood@ #350naira each,3'inches nail @#2,500 for half bag and 12lengths of y12 iron @#2,500 naira each.
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 9:01am On Feb 26, 2020 |
Break down: clearing of site(total area cleared 300m, cost 5000naira) -- uprooting of 3no palm tree(@5000 per 1) total cost 15,000naira. ---Digging of foundation (per meter 300naira* 115 total area cleared. ----forming of block work(dpc) 6000.00naira per day ,for 3days with 2no bricklayer and 1no labor. ----material : 9' inch block 500 pieces,180.00naira per 1no.*500 ---sharp sand: 30,000naira ----3/8 aggregate: 22,000naira. ---- laterite: 2no trucks @18,000naira *2 ----water: 1000naira per day. ---- Drum : 500naira per day. ---- iron : y12 ( 12 lengths @ 2,500 naira *12 1 Like
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Godisgreatest1: 12:32pm On Feb 26, 2020 |
Charles4wokoma:Please make the correction, 1 meter is #300 naira, not 300,000. Thank you. 1 Like |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 8:08pm On Feb 29, 2020 |
10/03/2020. Today's progress, carpenter's form work completed. Compaction of filled materials in progress,see pictures below.
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Hargbo(m): 9:08pm On Feb 29, 2020 |
lemme grab a seat, ama follow this thread to the end |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 12:51pm On Mar 01, 2020 |
Breakdown: Additional 300,9'inch block(300*180) _ 2no. Bricklayer and 1no.labour.for 2days*6000naira. _ water for 2days @ 1000naira per day --- New tank 9000naira and transportation to site 2000naira. Total: 79,000naira - previous balance of 117,000naira. Balance:39,000naira. At this stage ,the available balance can't push the work to the next level, funds is needed. 1 Like |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by YouGood(m): 10:20pm On Mar 01, 2020 |
Funds released to Engineer previously: N400,000 (out of which N39,000 is unutilized) Funds released now: N300,000. So funds with Engineer is currently N339,000 Total funds released so far: N700,000 3 Likes |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Hargbo(m): 5:47am On Mar 02, 2020 |
Charles4wokoma:the bricklayers laid 300 block for 6000naira abi how did you calculate there workmanship |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by joycluv: 7:38am On Mar 02, 2020 |
Op congratulations on this your project. But I think it would be more civilized for you to show the design and the size of this very build to enable us understand and appreciate the thread better. 3 Likes |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:36pm On Mar 02, 2020 |
Hargbo:. Good evening Mr.Hargbo! Consider starting time of work, block quantity * rate per block , equal to their workmanship. I hope I answered ur question. 1 Like |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:53pm On Mar 02, 2020 |
Godisgreatest1:. Size of block is 9' inch block |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by collins88(m): 8:03pm On Mar 02, 2020 |
Great Job 2 Likes |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Hargbo(m): 1:50pm On Mar 03, 2020 |
Charles4wokoma:Yes Boss.. any latest update |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:25pm On Mar 03, 2020 |
9/03/2020. Today's progress: boarding of foundation (dpc). Labour 1 carpenter, 30pieces of 1/12@#1,800naira, 10pieces of 2/2@,#350naira each, 3' inches nails half bag @#2,500naira .10/03/2020, today's progress, casting of foundation in progress,with 2no.bricklayers and 2no labour.
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:32pm On Mar 03, 2020 |
Material on site and their cost : 1no truck sharp sand (#30,000 naira),1no truck of 3/8,(#22,000naira) 2no truck of laterite(#36,000 naira) See pictures of material below. Note, we received laterite late this evening, pictures could not be taken because of poor visibility . 10/03/2020. Today's progress, compaction in progress,see pictures below.
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 11:03pm On Mar 03, 2020 |
Godisgreatest1:. Noted ! |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by jarrot(m): 11:31pm On Mar 03, 2020 |
Would like to know the estimate from foundation to finishing. Thanks |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 10:49pm On Mar 04, 2020 |
jarrot:. |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 12:26pm On Mar 05, 2020 |
13/03/2020. Foundation completed. Breakdown of material cost and labour . Fund released to me #300,000naira, previous balance #39,000naira unutilized. ___1no. Sharp sand(#30,000naira) __1no. 3/8 aggregate (#22,000nair) __3no. Laterite (#18,000naira*3) ___1/12wood(#1,800naira*30) ___2/2 wood (#350*10) ___3'inches nails (half bag #2,500) __4' inches nails(half bag #2,500)naira ___water ,per drum#1000naira(10*1000) ___ 12 lengths of y12@#2,500 per one *12 Labour cost ___, carpenter (#15,000naira) ___iron bender(#7,500naira) ____bricklayer(fixed sum to achieve foundation#50,000naira) ____labour (#1,500*30bags) At this point available fund can't commence super structure. 1 Like
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:36am On Mar 14, 2020 |
Required material cost and labour for super structure (building). ___ 2,985 pieces of 6inches blocks@#165naira. ___ 15 bags of cement@2,500naira. ___25 pieces of y12@#2,500naira(for lintel and head course). ___17pieces of 1/12wood for lintel form work @#1,800naira. ___water @ #1000naira per drum*10drums. Labour cost. __ per block #80*2,985 ___carpenter #25,000naira ___iron bender #7,500naira. Total cost: #870,100naira. 1 Like |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by cooljuman: 8:41am On Mar 14, 2020 |
Please, I'll need you to give me some information, I'm also building in portharcourt and in need of clay sand to fill my foundation to dpc level. You can contact me on 0 8 zero 3 four 7 7 nine three 7 zero. Thanks |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:22pm On Mar 19, 2020 |
Today's progress: with the fund provided (#200,000 naira),10bags of cement@2,550naira, 1000pieces of 6inches block@#165.00naira per 1. Note after purchase of the listed materials, balance available (#10,000naira)can not kick start the work(building super structure),e.g the quantity of sharp sand is insufficient, additional 1 truck is required,water and labour wage , can't be purchased and paid from the balance after purchase. See receipt of purchase of materials below,also see pictures of quantity of sharp sand available .
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 5:08am On Mar 21, 2020 |
1000 pieces of 6' inches block @#165naira, delivered to site . See pictures of blocks below.
|
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Babs612000(m): 5:41am On Mar 21, 2020 |
Charles4wokoma:Hello you wrote 15 bags of cement for 2985 blocks is that possible to set the blocks. |
Re: Construction Of A 3-Bedroom Bungalow In PortHarcourt by Charles4wokoma: 7:52pm On Mar 21, 2020 |
Today's progress: Building super structure commences,with 4 bricklayer and 3 labour,@#80naira per block. Total number of blocks laid today 720 out of 1000 pieces . Total number of cement used 8bags out of 10bags . Water used ,3 drums @1000naira per drum. I truck of sand delivered to site today @#38,000naira. fund provided for the commencing of the building super structure (#280,000naira ). Additional 1000pieces of 6inches block was purchased @ #165naira(#130,000naira)out of the #230,000naira provided today. See pictures of work progress,and materials available on ground.
|
Own A 2bedroom Bungalow With A Deposit N250k / Using Builders Square To Check The Correctness Of Your Foundation. / Construction Of Metal Works On A Two Storey Building In Enugu. COMPLETED
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 96 |