CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Welcome to this thread.
I am a Structural Engineer registered with COREN. I have First and Second degrees in Civil/Structural Engineering and more than 15 years experience building hundreds of structures in Nigeria.

DESCRIPTION
The building located in Lekki to be built in a swamp full of natural ground water. The building has a ground floor, a Gallery and a 2nd floor. All can sit between 3,000 and 5000 persons depending on the sit arrangement. I have called it a 3000 Seater but we designed for worst case scenario to carry more than 5000. Infact even if 10,000 persons have space to squeeze themselves into the building, the Structural strength can carry them all plus some more.

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Sand filling of the site is first step after the land acquisition.

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Before the construction is commenced, we did several Structural analysis of the frame structure using different design softwares. So as to determine the various loads and moments and share forces acting at the members.

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Further Structural analysis and design

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by Fheelzz(m): 7:43am On Dec 16, 2020
Space booked grin
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Fence

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
We carried out Soil test and investigation to be very sure of the capacity of weight the soil can bear and also to understand the soil strata underneath the site.
2 Standard Penetration Test (Borehole)
8 Dutch Cone Penetrometre Tests (DCPTs)
The site is 2 full plots

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 7:00am On Dec 17, 2020
Soil test

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 10:04am On Dec 17, 2020
Compaction of the soil to achieve near-zero voids of the soil.

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Excavation of trenches.
And BLINDING

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
I did very wide footings to spread the incoming loads of the building. Pressure equals Force (F) divided by the Area (A).
P=F/A. So when you want to reduce the Pressure coming to the soil, you increase the Surface area. This is simple Engineering based on simple physics. Engineering is based on sound science

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 9:55am On Dec 18, 2020
From the soil test results, I could either use short piles or 'long' beams. The cost for short piles are cheaper than the cost of deep beams. But clients always have dislike for piles. Most probably because piles have been made to appear costly. It's like giving a dog a bad name to hang it.
This is why me and a group of Geotechnical Engineers and Geologists had to form a Pile Construction company that builds piles that are less expensive than deep rafts.

So on this site, we opted to use DEEP RAFT with wide footings.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by deking(m): 10:28am On Dec 18, 2020
Keep it coming. Learnt something already.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:44pm On Dec 19, 2020
deking:
Keep it coming. Learnt something already.
Thanks alot
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 1:32am On Dec 20, 2020
Raft

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Raft formwork

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 5:53pm On Dec 20, 2020
Raft completed

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Sandfill of the foundation

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Compaction of the sand to level

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 11:24am On Dec 21, 2020
Roller compactor is very good in Compacting the sand to achieve near zero void.
When the sand is fully compacted, the ground flood slab will not require so much reinforcement again like a suspended floor slab will require.
But if it is not well compacted, then the ground floor slab will just be the one carrying itself. So it's better to design and construct it as a suspended slab. Or else you het failed slab with cracked tiles

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Blinding for the Ground Floor Slab.

NOTE:
We covered the compacted sand with thick nylon to avoid flow of ground water to the building. Reason why some houses have walls and tiles that suffer moist effects

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 2:14pm On Dec 21, 2020
Rebar works for slab

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 2:14pm On Dec 21, 2020
Reinforcement

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 3:21pm On Dec 21, 2020
Casting of ground floor slab

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 3:24pm On Dec 21, 2020
Casting

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 6:44pm On Dec 21, 2020
No time to check time.
Blockwork done and dusted

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 6:47pm On Dec 21, 2020
I love using super strong concrete blocks that I produce. However I didnt use concrete blocks on this project
I will.use these blocks to build your own house. I mean YOU!

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:58am On Dec 22, 2020
Blockwork

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 5:00am On Dec 22, 2020
We build with a super fast methodology that doesnt compromise the high quality we are known for.

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 5:01am On Dec 22, 2020
Carpenters are ready to start the columns (pillars)

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:15pm On Dec 22, 2020
Carpentry works

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:16pm On Dec 22, 2020
Carpentry