Nairaland Forum / Nairaland / General / Properties / WAREHOUSE : New Construction and Renovation works. (3704 Views)
New Construction Of A Block Of 4 Flats Of 3 Bedrooms At Awka, Anambra state / NEW Construction - 3 Bedroom Bungalow - Executive Design / New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. (2) (3) (4)
WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 9:05pm On Mar 29, 2022 |
The construction processes of a warehouse. I will be sharing two different warehouses construction processes here. The first was a new work and the other a renovation/ rehabilitation work. New warehouse construction This is a composite structure. It comprises of the structural steel ( the portal frame) and the reinforced concrete members of various sizes that were partitioned into various spaces. These are the offices, large open storage spaces, cloakrooms and toilets. This project has been completed and delivered. We started the construction works in July 2021 and delivered / handed-over in March 2022. Pinettum : 08028136294
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 9:16pm On Mar 29, 2022 |
How it started. The area of the warehouse building is 940sqm The site and Setting out pictures Some highlights
|
Re: WAREHOUSE : New Construction and Renovation works. by DUNKA(m): 9:57pm On Mar 29, 2022 |
Nice job. You are one architect to put on a shortlist 1 Like |
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 10:00pm On Mar 29, 2022 |
Thanks. . I'm actually a structural Engineer. DUNKA: |
Re: WAREHOUSE : New Construction and Renovation works. by DUNKA(m): 10:08pm On Mar 29, 2022 |
Aforxzy:my bad. But you Sabi build . Most impressive 1 Like |
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 4:33pm On Mar 30, 2022 |
Pad footing was used for the columns while the walls were placed on strip footing. Excavation of trenches 1 Like
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 11:25am On Apr 01, 2022 |
More excavation pictures From levels taken we realized that the site is quite lower than the road level. So we reconsidered the depth of excavation to accommodate this level difference. Our intention is to ensure easy and quick flow of runoff or stormwater out of the site. Note the steps in the trenches Pinettum: 08028136294
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 11:58am On Apr 01, 2022 |
Blinding and placement of reinforcements for the column bases and starters. There are different column types and bases.
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 1:19pm On Apr 04, 2022 |
Casting of column bases and wall strips
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 6:02am On Apr 05, 2022 |
Foundation block setting.
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 6:24pm On Apr 06, 2022 |
The perimeter tie beams and columns: reinforcements and formwork in place. Casting done Foundation Blockwall continues. Contact us for your construction works. Pinettum: 08028136294
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 7:18pm On Apr 10, 2022 |
Sandfilling with laterite. The volume of filling used was quite much in order to achieve a level higher than the existing road level.
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 7:04pm On Apr 11, 2022 |
Solid filling the hollow with lean concrete while spreading of the laterite filling continues with the bulldozer.
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 8:03pm On Apr 13, 2022 |
The steel members on site: univeral beams, columns and mesh. The mesh were used for partition. Also the holding down bolts are in place ready for casting. The holding down bolts and the base plate are very key elements in the installation of the stanchions. Their size and correct postioning play major roles in the installation process.
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 4:57pm On Apr 16, 2022 |
Steel installation: Portal frame The steel columns (UC) and beams ( UB) are being installed. This was done after 2weeks (14days) of casting the columns to enable the concrete attain certain strength. The sandfilling with laterite and spreading also continued during this period. The volume of fill was much so we had to use a bull dozer to push and dump the laterite into the building panels. We also had some rainfall which helped to compact the soil. Pinettum : 08028136294 1 Share
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 5:36pm On Apr 18, 2022 |
More pictures on the steel frame installation Contact us for your building construction works. Pinettum: 08028136294
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 8:26pm On Apr 21, 2022 |
More pictures of the completed portal frame
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 5:53am On Apr 25, 2022 |
Compaction of the sub soil
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 8:47pm On Apr 27, 2022 |
Hardcore filling with boulders. This is necessary because of the intended use of the structure. 3 Likes
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 6:44pm On May 01, 2022 |
Hardcore filling completed and reinforcements in place. We didn't use BRC mesh for this project rather Y10mm @300mmc/c was used. Ready for casting. Contact us for your building construction works. Pinettum: 08028136294 1 Share
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 6:27am On May 05, 2022 |
Casting of ground floor slab
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 4:47pm On May 10, 2022 |
Blockwall setting for the partitioning of offices, toilets , cloakrooms and open storage.
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 4:15pm On May 16, 2022 |
Roof covering
|
Re: WAREHOUSE : New Construction and Renovation works. by ArcToyin(m): 5:29pm On May 16, 2022 |
Well done. Good job 2 Likes |
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 9:13pm On May 16, 2022 |
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 7:56pm On May 20, 2022 |
Block setting continues
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 9:36pm On May 26, 2022 |
First floor formworks and reinforcements 1 Like
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 8:37pm On May 31, 2022 |
Casting done. Block wall setting continues Plastering of walls commences
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 5:39am On Jun 06, 2022 |
Block setting and plastering continues. Aluminum sun breakers installed
|
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 8:29am On Jun 09, 2022 |
Plastering continues Aluminum windows in place 1 Like
|
Re: WAREHOUSE : New Construction and Renovation works. by zexy2030(m): 6:06pm On Jun 11, 2022 |
Did you sub contract ? You did a good job. |
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(f): 6:53pm On Jun 11, 2022 |
Yes, some parts of the works were subcontracted. We actually have a team of subcontractors that we work well with.. zexy2030: |
Builders & Developers Wise Up! / Dangote Cement At Distributor Price For Your Construction Project / Newly built Blk Of 6 Nos Luxury 3 Bedrm Flats Wit Bq To Let @ Ikeja GRA. GONE!!!
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 23 |