Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,149,756 members, 7,806,072 topics. Date: Tuesday, 23 April 2024 at 11:02 AM

Construction Process Of A Wing Duplex+flat At Ajah - Properties (4) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Process Of A Wing Duplex+flat At Ajah (101020 Views)

PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI / CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI / . (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (40) (Reply) (Go Down)

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:17pm On May 11, 2012
Beam

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:54pm On May 12, 2012
DAY 38

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:59pm On May 12, 2012
men at work

Re: Construction Process Of A Wing Duplex+flat At Ajah by Oluwa4Sure: 10:05pm On May 12, 2012
Mr. Segcy.moor,

Can you please tell me the purpose of 'kickers' you mentioned earlier


Secondly, I noticed your Columns you used a 4" by 6" square rod(the name escaped my head)

But i thought the 6" by 5" or even 8" by 8" would have being better. So if i may ask,
is the 4" by 6" better than the later?
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 2:37pm On May 13, 2012
pls i dont understand what u mean by 4 or 6.
I used imported ukraine of 16mm and 18mm for column
Re: Construction Process Of A Wing Duplex+flat At Ajah by Akdams(m): 1:48am On May 14, 2012
Landscaping work, flowers and car ports

Contact us

Dapo
08120160199
Email : akdam_multiwealth@yahoo.com
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:03pm On May 14, 2012
DAY 39--Working on slab reinfocement

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:06pm On May 14, 2012
men at work

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:48pm On May 15, 2012
DAY 40--REINFORCEMENT

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:51pm On May 15, 2012
TECHNICAL WORK

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:54pm On May 15, 2012
men at work...

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:54pm On May 16, 2012
DAY 41

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:52pm On May 17, 2012
DAY 42

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:57pm On May 17, 2012
men at work

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 9:52pm On May 20, 2012
DAY 43-45

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 10:13pm On May 20, 2012
casting

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:02pm On May 21, 2012
I met this project Client on NL and he reside in UK. We are able to manage his fund well

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:09pm On May 23, 2012
DAY 46---Having wait for 4 days for decking to dry. we intend to continue block work

Re: Construction Process Of A Wing Duplex+flat At Ajah by ahf(m): 6:33am On May 24, 2012
Please is there any standard (or industry) criteria for period to wait after decking before commencing upper blockwork?

How does the 28days for concrete to cure factor in ?
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 10:55am On May 25, 2012
DAY 47-Blockwork

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 11:04am On May 25, 2012
Having cast d decking. we need to do what we call after treatment(the decking will be througly wet with water early monring before d sun rise and in the evening consecutive for atleast 4 day of casting) this is to ensure the decking absorbe water and this make it more stronger. Meawhile, one can proceed to set block after 4 day but to remove the plank after 28 days of casting
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:04pm On May 26, 2012
DAY 48

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 4:50pm On May 29, 2012
DAY 49-50

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 4:52pm On May 29, 2012
Meanwhile, that was part our step. The theory behind this step is Aeroplane with
wing. The wing of the step stand without anything hold it......it's
purely structural work. By the time one put mable on this step. Forget
it!

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:44pm On May 31, 2012
DAY 51-53

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:35pm On Jun 02, 2012
DAY 54

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:32pm On Jun 05, 2012
DAY 55-56

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:36pm On Jun 08, 2012
DAY 57-59

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:54pm On Jun 11, 2012
DAY 60-61

Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:01pm On Jun 13, 2012
DAY 62-63

Re: Construction Process Of A Wing Duplex+flat At Ajah by Nobody: 3:07pm On Jun 14, 2012
Great job.

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (40) (Reply)

WATCH THIS SPACE (Electrical Showcase & Review) / Cost Of Building A Four Bedroom Bungalow From Foundation. / Man Builds House With 14,800 Plastic Bottles In Kaduna (pics)

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 21
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.