Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:22pm On Sep 18, 2020 |
Pic 10
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:21pm On Sep 18, 2020 |
Pic 9
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:19pm On Sep 18, 2020 |
Pic 8
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:18pm On Sep 18, 2020 |
Pic 7
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:15pm On Sep 18, 2020 |
Pic6
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:14pm On Sep 18, 2020 |
Pic 5
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:13pm On Sep 18, 2020 |
Pic 4
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:11pm On Sep 18, 2020 |
Pic3
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:10pm On Sep 18, 2020 |
More
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:08pm On Sep 18, 2020 |
Next phase of work is setting of blocks to lintel level
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:07pm On Sep 18, 2020 |
More pic
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:05pm On Sep 18, 2020 |
More
|
Properties › Re: Construction Of 5bedroom Bungalow For A Nairalander by Heymus(op): 11:04pm On Sep 18, 2020 |
Oversite concrete/ German floor
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:58am On Sep 11, 2020 |
Now the project at window level,
Duration for this is 3days. Many hands on your project, in order to deliver quick.
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:54am On Sep 11, 2020 |
Still more
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:52am On Sep 11, 2020 |
More pics
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:51am On Sep 11, 2020 |
Coming
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:49am On Sep 11, 2020 |
Still
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:47am On Sep 11, 2020 |
More
|
Properties › Re: Construction Of 5 Units Of A Room And Parlour Self Contained For A Nairalander by Heymus(op): 7:43am On Sep 11, 2020 |
Commencement of works continues on this project after sand filling, no German floor as the owner says. But later we do flooring.
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 12:00am On Sep 03, 2020 |
Progress
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:50pm On Sep 02, 2020 |
Upper floor blocksettings
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:49pm On Sep 02, 2020 |
Upper floor blocksettings
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:42pm On Sep 02, 2020 |
Iron works
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:32pm On Sep 02, 2020 |
In preparation for the casting of upper floor reinforced slab(decking). Propping the formwork for the floor with bamboo
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:16pm On Sep 02, 2020 |
Blocksettings
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:14pm On Sep 02, 2020 |
Blocksettings
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 11:02pm On Sep 02, 2020 |
German floor/oversite concrete
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 10:56pm On Sep 02, 2020 |
Sand filling prior German floor
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 10:48pm On Sep 02, 2020 |
Setting of blocks to dpc level
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 10:47pm On Sep 02, 2020 |
Foundation footings and positioning of short columns.
|
Properties › Re: Construction Of Mixed Developments Building by Heymus(op): 10:34pm On Sep 02, 2020 |
Still digging
|