WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
The construction processes of a warehouse.

I will be sharing two different warehouses construction processes here. The first was a new work and the other a renovation/ rehabilitation work.

New warehouse construction

This is a composite structure. It comprises of the structural steel ( the portal frame) and the reinforced concrete members of various sizes that were partitioned into various spaces.
These are the offices, large open storage spaces, cloakrooms and toilets.


This project has been completed and delivered. We started the construction works in July 2021 and delivered / handed-over in March 2022.



Pinettum : 08028136294

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
How it started.

The area of the warehouse building is 940sqm

The site and Setting out pictures


Some highlights

Re: WAREHOUSE : New Construction and Renovation works. by DUNKA(m): 9:57pm On Mar 29, 2022
Nice job. You are one architect to put on a shortlist
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Thanks. .

I'm actually a structural Engineer.

DUNKA:
Nice job. You are one architect to put on a shortlist
Re: WAREHOUSE : New Construction and Renovation works. by DUNKA(m): 10:08pm On Mar 29, 2022
Aforxzy:
Thanks.

I'm actually a structural Engineer..
my bad. But you Sabi build grin. Most impressive
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op): 4:33pm On Mar 30, 2022
Pad footing was used for the columns while the walls were placed on strip footing.



Excavation of trenches

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
More excavation pictures

From levels taken we realized that the site is quite lower than the road level. So we reconsidered the depth of excavation to accommodate this level difference. Our intention is to ensure easy and quick flow of runoff or stormwater out of the site.

Note the steps in the trenches

Pinettum: 08028136294

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Blinding and placement of reinforcements for the column bases and starters.

There are different column types and bases.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op): 1:19pm On Apr 04, 2022
Casting of column bases and wall strips

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Foundation block setting.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
The perimeter tie beams and columns: reinforcements and formwork in place.

Casting done

Foundation Blockwall continues.



Contact us for your construction works.

Pinettum: 08028136294

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Sandfilling with laterite.

The volume of filling used was quite much in order to achieve a level higher than the existing road level.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Solid filling the hollow with lean concrete while spreading of the laterite filling continues with the bulldozer.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
The steel members on site: univeral beams, columns and mesh. The mesh were used for partition.


Also the holding down bolts are in place ready for casting.

The holding down bolts and the base plate are very key elements in the installation of the stanchions.

Their size and correct postioning play major roles in the installation process.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Steel installation: Portal frame

The steel columns (UC) and beams ( UB) are being installed. This was done after 2weeks (14days) of casting the columns to enable the concrete attain certain strength.

The sandfilling with laterite and spreading also continued during this period. The volume of fill was much so we had to use a bull dozer to push and dump the laterite into the building panels.

We also had some rainfall which helped to compact the soil.


Pinettum : 08028136294

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
More pictures on the steel frame installation


Contact us for your building construction works.

Pinettum: 08028136294

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
More pictures of the completed portal frame

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Compaction of the sub soil

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Hardcore filling with boulders.

This is necessary because of the intended use of the structure.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Hardcore filling completed and reinforcements in place.

We didn't use BRC mesh for this project rather Y10mm @300mmc/c was used.

Ready for casting.


Contact us for your building construction works.

Pinettum: 08028136294

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op): 6:27am On May 05, 2022
Casting of ground floor slab

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Blockwall setting for the partitioning of offices, toilets , cloakrooms and open storage.

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Roof covering

Re: WAREHOUSE : New Construction and Renovation works. by ArcToyin(m): 5:29pm On May 16, 2022
Well done. Good job
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op): 9:13pm On May 16, 2022
Thanks.

ArcToyin:
Well done. Good job
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op): 7:56pm On May 20, 2022
Block setting continues

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
First floor formworks and reinforcements

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Casting done.

Block wall setting continues

Plastering of walls commences

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Block setting and plastering continues. Aluminum sun breakers installed

Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op):
Plastering continues

Aluminum windows in place

Re: WAREHOUSE : New Construction and Renovation works. by zexy2030(m): 6:06pm On Jun 11, 2022
Did you sub contract ? You did a good job.
Re: WAREHOUSE : New Construction and Renovation works. by Aforxzy(op): 6:53pm On Jun 11, 2022
Yes, some parts of the works were subcontracted.
We actually have a team of subcontractors that we work well with..

zexy2030:
Did you sub contract ? You did a good job.