Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,151,888 members, 7,814,006 topics. Date: Wednesday, 01 May 2024 at 12:27 AM

Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats - Properties (3) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats (17604 Views)

Distress sale 4 duplex for sale price 22m / Our 4 Bedroom Duplex And 2 Bedroom Flat Journey In Ibadan / 3 And 4 Bedroom Semi & Fully Detached House With 18 Months Off Plan Payment. (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (15) (Reply) (Go Down)

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 5:01pm On Jun 10, 2022
So much rain in this region of the country is very challenging. However, we are trying as much as we can to push through.

Just before the close of work today rain started falling after terrible 4hrs sun.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 8:58pm On Jun 10, 2022
We will continue tomorrow with other works on site.
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 11:53am On Jun 11, 2022
Concrete works now
Lintel and Colums

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 4:11pm On Jun 11, 2022
Working at this time in the east is quite challenging.
But we are doing our best as always

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 4:12pm On Jun 11, 2022
Without wasting much time.
We have started preparing for decking.

Starting with the decking rings/stirrups

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 3:22am On Jun 12, 2022
Good morning Viewers.
Keep following up with us for more update.
We will continue with our works on colum and Lintel today.

Rain was much yesterday. We had to stop concrete works.
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 8:08am On Jun 12, 2022
Result of the area we poured concrete before the rain.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 2:09pm On Jun 12, 2022
More work updates from here
Results and going forward of the concrete works we did yesterday.

Leveling ongoing simultaneously.
We are doing 3 coaches as against 2 coaches initially planned. Client wants more headroom for the decking. For finishing concepts on POP designs.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 3:45am On Jun 13, 2022
Picture update.
Earlier yesterday.
The Duplex has an open Kitchen design.
Picture 1 and 2 - Main Sitting room
Picture 3 and 4 - Showing the Flat Area

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 1:30pm On Jun 13, 2022
So far on the ground floor we have used over 3700 Blocks of 9 inches and still counting.

Our leveling is 3 coaches of blocks after lintel.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 4:36pm On Jun 13, 2022
Leveling works ongoing still

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 9:44pm On Jun 13, 2022
Consistency is Key.
Regardless.
Thank you for those watching and following up silently too. We see and notice your presence on the page views. wink

We will definitely continue to update the thread as work goes on here.

1 Like

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 3:33am On Jun 14, 2022
Keep following
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by BiigTee: 6:48pm On Jun 14, 2022
Welldone.. Diligently following

1 Like

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 4:56am On Jun 15, 2022
BiigTee:
Welldone.. Diligently following

Thanks sir.
Good morning to you.
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 5:00am On Jun 15, 2022
We have successfully completed the application holding leveling.

Total blocks purchased was 4200 pieces in all.

Decking stage is next and we have equally made some procurements for a start.

Bamboo here are sold at 750 but they are full length as compared to Lagos own. Lagos is selling for 650 the last I bought 3 months ago but this one here is x2 Lagos size. So Lagos building material market is quite expensive when it comes to wood and a few other things down here.

There are only but a few building materials in Lagos that I will say are better of than here but they are barely significant when it comes to cost.

Though some practice in the east here are different too than Lagos. Like when you buy stuffs here you pay for loading and Offloading yourself. You pay for transport yourself. Just the few procurements done yesterday costed 40K transport and 20K loading and Offloading.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 5:04am On Jun 15, 2022
Decking materials.
We have got already 350 pieces of planks.
300 pieces of Bamboo sticks.
250 pieces of 2x3x12 wood.
4 Bags of nails.
16mm
12mm
10mm
3 roles of binding wires.
Set for the decking works now.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 5:06am On Jun 15, 2022
In preparation for the decking works
Some 3D models have Been established to show a few adjustments on the design.

The entrance area to the flat have been worked upon. See the updates on the design and watch out for the construction ASAP

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 6:20am On Jun 15, 2022
Would be sharing the 3D Model of the Decking Slab here today!!!

Stay tuned.it's becoming interesting the more.

Designing and Building In real time 3D and Life Construction simultaneously.

Every element is represented.
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 9:58am On Jun 15, 2022
Good morning Viewers.
As promised.
This is the next stage of works
3D Model of the proposed DECKING construction

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 11:57am On Jun 16, 2022
Decking works update

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 3:08pm On Jun 16, 2022
More perspective view of the Building
One of our biggest challenge so far in this project is steady rainfall.

Today, it's been raining since morning till now. sad

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 9:02pm On Jun 16, 2022
Good evening Viewers
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 7:53pm On Jun 17, 2022
Iron works on beams ongoing
Its basically beam formation we are doing at the moment

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 2:47am On Jun 18, 2022
Good morning
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 6:34am On Jun 18, 2022
Still on the Beams.
Duplex area now.
Lots of Beam formation
The bedrock that carries the decking slab.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 2:45pm On Jun 18, 2022
Keep following.
It's getting more interesting.
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 8:25pm On Jun 18, 2022
Final irons arrived Today.
380 Pieces of 12mm Lengths.
30 Lengths of 16mm supplied today
35 Lengths of 10mm more added though from estimated too.

Bamboo sticks.
1x12x12 planks
2x3x12 woods

1 Bag of nail.

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 5:13am On Jun 19, 2022
We continue today.
We will be updating our work progress.
Stay tuned
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 6:14am On Jun 19, 2022
We are going to be forming the cantilivers on the building as well as forming other components of the building elements that will sustain the decking works.

Electrical works and plumbing works are gonna start ASAP.
Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 1:50pm On Jun 19, 2022
Update on the floor Matt

Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(m): 6:00pm On Jun 19, 2022
We are seriously pushing the decking works despite the rain fall here. View of the flat area

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (15) (Reply)

0.45mm Gauge Aluminum Longspan Now Selling @ N1, 070 And 0. 55mm N1, 450 / How Do I Deal With My Landlord? / Nuli Juice Update: Tenants Were Actually Aware Of The "X" Sign On The Structure

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 22
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.