Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Roofing. Handled single handedly by my young Site Engineer Ola. While I was away to Kano

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Suspended ceiling for wind floor. Handled mainly by my Site Engineer Ola

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 7:59pm On Dec 24, 2020
Plastering finished for inside and bamboo scaffolds removed

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 8:08pm On Dec 24, 2020
POP

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:40am On Dec 25, 2020
Finishing in top gear for dedication deadline

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:41am On Dec 25, 2020
Finishing touch

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:43am On Dec 25, 2020
Gallery before cleaning

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Fence

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 8:36am On Dec 25, 2020
Glass Curtain walls

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:16pm On Dec 25, 2020
smiley

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 12:17pm On Dec 25, 2020
Not 100% like the Model due to so many adjustments made by client

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by psychologist(m): 12:23pm On Dec 25, 2020
abragr8:
Underneath those 14m span Deep Beams.
Weldone sir

What is the depth of this 14m span beam?
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by Donsheddy: 1:37pm On Dec 25, 2020
abragr8:
Not 100% like the Model due to so many adjustments made by client
how much will it cost to get this done from scratch to finish?
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by kopell: 1:41pm On Dec 25, 2020
abragr8:
Finishing in top gear for dedication deadline
Congratulation Engineer, this is massive project deliver in record time. If I may asked how long the entire project took from foundation to roofing its astonishing to me. I know those government agencies are pain in the butt. I'm going through the same thing. It is never in the best interest of the owner to settle them, paying to government direct, get it well documented otherwise they will keep coming like termite. Can you please post the source of those shining pillars in the hall where it's sold or how it's made there. Here the application is clear, it's made up of paint and other addictive products. I'm trying to get something similar over there but I don't know where. I must commend you, you did a very nice and professional job.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by kopell: 1:59pm On Dec 25, 2020
abragr8:
Gallery before cleaning
The pillar that you're standing next to, is what I'm referring to as a shining pillar.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:05pm On Dec 25, 2020
kopell:
Congratulation Engineer, this is massive project deliver in record time. If I may asked how long the entire project took from foundation to roofing its astonishing to me. I know those government agencies are pain in the butt. I'm going through the same thing. It is never in the best interest of the owner to settle them, paying to government direct, get it well documented otherwise they will keep coming like termite. Can you please post the source of those shining pillars in the hall where it's sold or how it's made there. Here the application is clear, it's made up of paint and other addictive products. I'm trying to get something similar over there but I don't know where. I must commend you, you did a very nice and professional job.
Thank you bros.
When I said we settled them, it's not just to pay their Agents that come to the site. We settled the statutory fees directly from their head offices. Very many of them including Omonile.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:07pm On Dec 25, 2020
kopell:
The pillar that you're standing next to, is what I'm referring to as a shining pillar.
As for the "Shinning Pillars" it's someone who handled that directly.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op):
Donsheddy:
how much will it cost to get this done from scratch to finish?
Let's chat. Check my signature
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:11pm On Dec 25, 2020
DEDICATION OF THE EVENT CENTRE WAS CARRIED OUT BY A PREACHER FROM UYO CALLED DR ABEL DAMINA

Social Distancing didnt allow us to arrange the seats tightly as the capacity can carry

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:12pm On Dec 25, 2020
Dedication in December 2020

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:15pm On Dec 25, 2020
Ok

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:20pm On Dec 25, 2020
psychologist:
Weldone sir

What is the depth of this 14m span beam?
I used 3 and a half FULL 300mm Planks for the Bottom beam. 1100mm for the drop. Then you add the Slab thickness to it which is 200mm you get 1.3m deep beams. And very wide
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 4:22pm On Dec 25, 2020
View from the Gallery

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 6:37am On Dec 26, 2020
Sitting on the stage

Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by Stevengold(m):
Very nice sir. I followed all through. But is this really 3000 capacity? It looks small in my eyes though.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by nedekid: 7:28am On Dec 26, 2020
Op just give a rough idea of the cost turnkey. Eg +50m, - 100m etc.
It will enable some where their power reach and if it is necessary to call.
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 9:19am On Dec 26, 2020
Stevengold:
Very nice sir. I followed all through. But does is this really 3000 capacity? It looks small in my eyes though.
The chairs were arranged with social Distancing so that is why it seems like that.
Also the 2nd floor is a whole stretch is another long hall
So I made the Structural strength to be so strong that it can even contain 10,000 people standing at worst case scenario
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 9:27am On Dec 26, 2020
nedekid:
Op just give a rough idea of the cost turnkey. Eg +50m, - 100m etc.
It will enable some where their power reach and if it is necessary to call.
With construction, finishes, Electrical and Digital installations etc it is N350m
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by abragr8(op): 8:56pm On Dec 26, 2020
In 2021 we are putting together a group of investors to build the best Event Centre with some Lodging suites in Lekki. 500 persons. And each person would invest a Minimum of N1m. You get 100% returns and can divest (exit).
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by kopell: 11:24pm On Dec 26, 2020
abragr8:
In 2021 we are putting together a group of investors to build the best Event Centre with some Lodging suites in Lekki. 500 persons. And each person would invest a Minimum of N1m. You get 100% returns and can divest (exit).
Are you serious, what part of Lekki will be prefer location for the project, as we speak I have a friend that as about 60 plots for sale in Ibeju before eleko along lekki epe express on that main road. I can send you the video of the location tomorrow if you don't mind
Re: CONSTRUCTION PROCESS FOR A 3000 SEATER EVENT CENTRE by kopell: 11:32pm On Dec 26, 2020
abragr8:
In 2021 we are putting together a group of investors to build the best Event Centre with some Lodging suites in Lekki. 500 persons. And each person would invest a Minimum of N1m. You get 100% returns and can divest (exit).
That is a lot of investors, I think is better to have few investors that can put better resources together in form of share to the project. That is smart thinking.