Notice: For the Column Base, we are using Y12 and for the Column, we are using Y16. For strength, the bending schedule for the base shows Y12 returned as a capped basked totaling 24nos at 1500mm spaced at 125mm...the weight is tremendous when carried. For the column, the bending schedule is 12 nos Y16 at 8inches spacing bound by a Y8 ring. The column was designed to withstand load stress and the column base to withstand downward movement. This is the scenario we want to create: Imagine a rigid flat Tray sitting on 10 packets of match box erected vertically & loaded, supporting this tray carrying 15 cans of Coca Cola Drink. Since the foundation is considered weak, we are supporting the building with these massive columns. The total number of columns to be put in place is 14. 6nos in front, 4nos at the back and 2nos at each side.
|
More....
|
Starting the first face of reinforcing and strengthening the house with double size columns, the Fitter and the Carpenter gets to work bending the reinforcement rods according to the bending schedule and the carpenter forming the wood-works. The columns thickness are meant to flush with the existing walls so as not to deface the house. Our action are to present the building as new building at the end without anyone suspecting that it was worked on.
|
Will post more later as work is currently on-going at site... |
PeoplesArmy:Terrible Construction mistake. |
umuokezie:Thank you Sir |
We have longed mobilized to site with the needed materials having arrived as required. Me and some of my team analyzing the building and taking measurement.
|
We Quickly re-drew the architectural drawing of the house so as to produce the structural drawing and as well insert our supporting columns.
|
Going Further, after an indepth analysis, we've decided to to tackle the project headlong but in stages as listed below: First Stage: Insert massive columns with a large base. The Columns measure: 500mm x 225mm with a total length of 15ft and the column base measuring: 1500mm x 1500mm x 300mm sitting on a concrete blinding of 50mm and a Sharp Sand base of 200mm to resist movement. Second Stage: Construct and Place 3000mm x 1200mm x 300mm massive Sub-surface retaining drain like wall 5m from the north elevation of the building. This Sub-Surface retaining drain like wall will span a total of 50m, this is to prevent the ground water moving from the top of the slope to make contact with the building foundation. Third Stage: Tear down the existing front foundation with the ground floor super-structure only at the front and Rework the entire front foundation measuring 26.7m to the both sides measuring 2.7m each. Raise the super-structure again, Under-pin some section of the partitioning walls in the ground floor, unearth the foundation filling at some points and refill, compact and cast the DPC. Reinforce 10 existing columns in the building and finally, finish the ground floor. |
More Pictures...
|
Its a multi-floor block of 8 flats built 6 years ago but on a wrong foundation type for such building and soil type. I will give a brief description of every aspect of the building before the reconstruction works: CONTRACTOR: KDI Structures Ltd. CLIENT: Can't disclose for want of Security. PROJECT TITLE: Reconstruction of the failed section of a multi-floor 3 bedroom block of 8 flats. LOCATION: Umuahia, Abia State. PROJECT COST: N16.7million DURATION: 4 months (This is because the works will be done in stages to ensure the curing duration for every concrete work is met before any other work is carried out). BUILDING SIZE: 26.7m X 11.2m. NATURE OF THE SITE: Sloppy with very shallow ground water level. Geotechnical analysis has been done on the site and below are the results: Ground water level: 1m at BH2 & 1.5m at BH1. Particle size distribution: Sandy-clay to Pure shale seen between 0.5m - 4m at BH1 and Sandy-clay to shale seen between 0.5m - 3.2m at BH2. the top soil showed a high level of moisture at 0.2m - 0.5m at BH2. Soil Load Bearing Capacity: 32kN/m2 - 310kN/m2 Structural Engineering Analysis carried out on the building revealed that the total Load from the building is 200kN/m2 which is within the laod bearing capacity range of the Soil. FOUNDATION TYPE: Strip foundation with varying depth of 5ft - 6.7ft at different points because of the slope but the mistake was the chaining beam wasn't anchored to the columns and the foundation beam wasn't reinforced. The entire building foundation is immersed in ground water to a depth level of 1.5m - 2.2m from the north elevation to the south elevation. due to this reasons, DIFFERENTIAL SETTLEMENT took place shown by multiple structural failures and massive cracks, entire failure of the front section of the foundation, slight tilting of the entire building, failure of the DPC section at the sitting and dinning room for the 2 ground floor flats. To avert further failure, Anchor bars has been place at a spacing not greater that 450mm at the every point in the ground floor and to also serve as a means of artificial support system to permit for reconstruction works.
|
FOLYKAZE:Which you made this statement at the beginning of this year or end of last year. But coming now, its as useless as ever because journalism has completely grounded Nigeria leading to the general Elections. So stop crying , You guys enjoyed it while it lasted and sure it did last up till now. Every seed sowed must be reaped. |
baralatie:Total difference from Adjusted budget and Declared budget: N460 billion. That's a huge amount to have been neglected or purported to be swept under the carpet. Nigerian's observe this indepth. Nice work @Baralatie |
datola:They resumed buying, rather then went to sign nuclear deal with iron in return for Oil Market control. thats ehy they lifted the ban on Oil Export. Its part of the International politics at play to knock down some large economies like the Asian Tigers and the African largest economy. |
No doubt, the immediate past president of Nigeria, President Ebele Goodluck Jonathan GCFR, has earned himself the 'Most Mentioned name of the year 2015. Months leading to the general Elections, he saw his name mentioned so widely both Nationally & Internationally. His defeat at the April Polls saw another spike in the mentioning of his name alongside President Buhari. Whether it was for negative reasons or for positive reasons, he has enjoyed a large appeal and Name mentioning. The coming into power by the APC led Government has seen President Goodluck Jonathan being mentioned more by the APC and the Government. The populace isn't left out in contributing to the Name mentioning. GEJ or President Goodluck has been on the lips of many either blaming or accusing him or eulogizing and extolling him. On the Social media, for every 100 - 300 words mention, the work 'GEJ' is mentioned at average of 30% - 40%, whether for hate speech, comment or posts or for positive affronts. Every inability of the Present Administration in tackling Nigeria's Problem has a mention of the 'GEJ' or President Jonathan. Every recourse to democracy in the recent has the mention of the word 'GEJ', either as a hero or a valian. Thought or touted to be the most celebrated Past President of the Federal Republic of Nigeria, President Ebele Azikiwe Goodluck Jonathan, has won to himself this year: Vanguard Man of the Year together with President Buhari and also the Conspicuous '2015 MOST MENTIONED NAME OF THE YEAR' |
airsaylongcon:Standard Concrete curing duration is 28 days to attain 25N/m strength for every kind of concrete work: Beam, Column, Slab e.t.c. Though the strength value differs depending on mix ratio and mix materials but a range of 23N/m to 25N/m is perfectly suitable to carry any kind of dead or life load in the entire construction. |
mannobi:Sounds more like a broken record. To you, supporting APC or aligning with PMB means to move on. You are an Igbo nepotic! If the Igbo's choose to clamour for their inalienable right or choose not to be relevant in this administration, does that mean that they have not moved on. Indeed they have moved on and that's why they are agitating for self determination. Stop bereaving yourself of non-supporting of this Administration by the Igbo's. When a fool talks |
Flashh:Young Man, The bill is being sponsored by an APC Senator and Supported by Senator Dino Melaye and other APC Senators, So its no PDP Propaganda! Study and be wise, Stop being driven by useless partisan sentiment. |
Good work Sir, I am consistently learning following your thread. I greet my Ogas Mufatu, phlemmy, segcymoore... Congratulations Sir. C.Obinegbo KDI Structures |
Learning From the masters is always a rare priveledge. Keep up the good work and God's speed on this project. I am keenly following. In-between, when I was involved in the construction works at the Lake-View estate behind Nike Lake Hotel, the Land wasn't water-logged as the case is in your site which is some meters away from Nike lake its self. Thanks |
One good fact here is that learning fast is guaranteed at every point. Comprehensive work Oga Segymoore, I am thrilled and beyond impressed. God's speed and Grace. |
The work is Simple and classic. The work is very impressive, keep it up Sir. |
searching4love:This guy must be drinking and reading. The guy interviews, is he an Igbo or a Yoruba Man? Check very well before you say anything. The man complaining is a core Yoruba Man. |
Nice works at amazinghomes. Sorry came late to class, but learning a great deal. |
I know i came late but i am seated and have learned a great deal. Please who can give me his note so i can copy. My engineer, weldone. |
abdulwastecx:My Engineer, your idea on this is simply mind blowing. I have never thought in this regard before, making sense deeply. |
meetmonde:Though a small piece of land, A 3 bedroom all ensuite duplex, with the bedrooms upstairs and the sitting room/dining room and kitchen down stairs. I am currently working on one now and its sitting on exactly the land size. If you are ready and would want to develop that property of yours, Hola at me 08039154723, kdistructures@gmail.com |
Slaw12:With NGN 4million, you have your 4 bedroom bungalow with modern facility in Ibadan. I can handle that, do you have a survey plan already? |
laurel03:But if it was finished, your senile Prof. Osinbajo would be staying in a N7billion mansion and you will be happy. Nigerians think in reverse. Thank God GEJ refused to approved the variation, we're a very wasteful nation. |
TGEE LIMITED, an Oil & Gas and Engineering firm with indepth business activities in the oil and gas industry as well as in the Engineering Industry has need for an astute, smart and coordinated business development personnel for the advertized position of: BUSINESS DEVELOPMENT EXECUTIVE. COMPANY: TGEE LIMITED LOCATION: PORT HARCOURT, RIVERS STATE. POSITION: BUSINESS DEVELOPMENT EXECUTIVE RESPONSIBILITIES: Develop business and marketing plans in coordination with Managing Director to achieve revenue goals. Assist in company’s branding and media communication activities such as press releases, advertisements, marketing collaterals, and web site. Analyze the current and past budgets, expenses, sales, revenues and services deficiencies in order to provide recommendations for business growth and problem resolution. Research the market for identifying new business opportunities. Explain prospective clients about the advantages of the services offered and follow up with them in order to close the business deals. Respond to the client queries regarding the services in a timely fashion. Develop business proposals for new and existing customers. Develop creative strategies to retain the clients including interviewing them to take their feedback and incorporate it into the growth plan. Prepare the annual marketing budget and track the expenses against the budget. Develop in-depth knowledge about business development practices, marketing activities, prospective clients and industry trends. Maintain a knowledge repository of clients, referrals, RFPs, prospects and presentations. Develop strong customer relationships in order to generate high volume of prospective clients. Manage customer calls and appointments effectively for new opportunities. Participate in industry forums, client discussions, and conferences as a representative of the organization. Determine cross-selling opportunities among different offices. Supervise the client relationship management database and utilize it to manage customer contacts and mailing lists. Hire, train and guide the marketing and business development associates. Business Development Manager Skills and Qualifications: Closing Skills Motivation for Sales, Prospecting Skills Sales Planning Selling to Customer Needs Market Knowledge Presentation Skills Meeting Sales Goals. QUALITIES: Must be a Smart Young lady with high marketing ambition. Must possess a cognate years experience in closing deals and securing jobs. Must be skilled in Information technology Interested Persons should apply by Sending the CV and an application for the position advertized above to the email shown below with the subject: TGEEL-BDE 001 keepdigginginc@hotmail.com |
?