RichYoungRuler's Posts
Nairaland Forum › RichYoungRuler's Profile › RichYoungRuler's Posts
bjonze:Thank you for your kind words,Amen. GOD BLESS YOU MORE. |
More Progress Photos |
More Progress Photos...
|
More Progress Photos
|
Project Handed Over To The School Today OOU 92.1
|
Tower Construction progress photos
|
topsy23:Thanks Boss, we didn't use marconite as we already tested our earth pit even before applying any charcoal and we had good resistance as we had 2 different loops round d building and round d tower connected together. We eventually had it installed after plastering, good observations. I'm quite hopeful we'll work together soon. |
Elevations,Plastering, window subframes and hoods construction...
|
Timber Roofing Carcass and roof covering
|
Tower Construction progress photos
|
Hi guys, I think you both are right depending on how you look at it. Ghana removed 2 zeros truly which was what Professor Soludo wanted to do here but our then Govt didn't buy it so in that wise you cannot compare 1 naira to 1 cedi but 100 naira to a cedi which is actually what it is . On the contrary, if 1 looks at the face value comparing both for someone who isn't aware of this history of the cedi then the cedi is stronger because what you have NOW is also called a cedi whether or not 2 zeros have been taken away from it. So right now,since a cedi is a cedi and going by international foreign exchange standards it is stronger except Nigeria also does what they did. |
Fence work, setting out for tower base, tower base excavation, roofing work....casting of wall capping.
|
Septic tank
|
johnson232:Thank you. Yes, with the roof beams at the ends. |
More photos on septic tank construction and earthing...
|
Week 6 1. Removal of roof beams formwork 2. Septic tank and soak-away construction 3. Dwarf fence construction
|
Hi Sir, I have noticed this over time and my studies reveal they are settlement and shrinkage cracks like abdulwastecx wrote. It can usually be remedied by hacking that area off and replastering. One thing I do now in fresh buildings is to install nets around those prone to areas before screeding and I have seen improvements tho you ma not be able to predict all areas but its limited with that. Nothing will do your building should you decide to leave it too just unsightly for a new building. |
EndiaSami:Compliments Boss. Noted and Weldone Sir. |
More photos from Week 5
|
Week 5 schedule 1. Blocksetting to roof beams levels 2. Electrical piping (1st fix) 3. Formwork for roof beams and entrance canopy 4. Iron(Rebar) works for roof beams,roof gutters and entrance canopy 5. Concreting (casting) of roof gutters,entrance canopy and roof beams.
|
Week 4 1. Blockforming(set out) on the ground floor slab 2. Blocksetting to the ground floor slab 3. Iron works for columns and lintels 4.Formwork for lintels and columns
|
topsy23:I like the products you use Boss. This one is already gone as it's almost done but we can keep in touch for upcoming ones. Compliments of the season. |
After the mechanical compaction, we laid boulders, took levels again, installed side formworks using locally available wood called Somi from Ijebu Igbo then spread mesh wire A142 over which we the cast the groud floor slab. |
A couple of photographs are not available for now. Will locate them and update later, for the substructure basically I.e the foundational blocks and concrete filling as the difference between the natural ground floor levels in the front and at the rear end of the site is about 1.5m. After the foundational blocksetting, we filled the hollow spaces of the blocks with concrete for rigidity and to increase stiffness. Next, we backfilled the excavated laterite and compacted in stages using the density of water to our advantage before mechanical compaction. We didn't use a damp proof course as the height difference was quite remarkable as I earlier noted and the terrain is such that the water table cannot be encountered even if you dig to 10m, so we figured rising damp isn't an issue. Thank you for viewing this thread.
|
Installation and alignment of pad bases and columns into respective locations. Notice Concrete covers also known as biscuits on the floor to be used for increased protection against fire,corrosion and the elements. Our foundation cover was 50mm as site conditions were judged to be mild or moderate.
|
Blinding followed excavation. We did blinding for 2 basic reasons...
|
mostyg:I hope your questions have been answered Sir? |
Excavation in progress. We had 21 columns with the maximum span being about 6m. 1 of the reasons for the columns and foundation type is the presence of Roof Drainage (gutter) for rain water collection and for AC water collection too.
|
Foundation type was Strip and Pads, structure is a bungalow. The basic construction was the building itself that housed the main and live studios, offices, control room, toilets etc and a telecommunication mast for the transmitter and antenna. Setting out was done in 3days as there were level differences not captured in the survey and because we believe if we make mistakes here it could continue and the end users might live with it for as long as the building exists, so we take our time in setting out.
|
The Construction site is located within OOU's permanent campus behind the Mass Communication Department. Site Clearing was done in a day and grubbing was done the next day in preparation for setting out and excavation.
|
We are a Building Construction,Civil Engineering and Project Management Company. We are Rich Ruler Limited and we are being run by Young Dynamic Engineers and Builders. This is about a recent project that (is yet to be handed over to the end users) has been handed over in January 2016. It is about how we built/are building Olabisi Onabanjo University, (OOU) Radio Station. We are the main sub-contractor as a bigger and well known construction company is the main contractor. Questions,Criticisms etc are welcomed. I hope someone can learn a thing or two from our processes and methods. We are also still learning and improving. E-mail: info@richrulergroup.com Twitter: @richrulerltd Please find below a link to another thread showing past works by us too: https://www.nairaland.com/3148593/built-1980-capacity-doubled-2012#46307906 ***modified Thank you for viewing. |
Ronkuns:yes but it isn't subject to witholding tax just as treasury bills. JIJO depends on your risk(s) appetite Sir. The same way it could go your way is d same way it could go against you. |