Welcome, Guest: Join Nairaland / LOGIN! / Trending / Recent / New
Stats: 2,712,557 members, 6,407,832 topics. Date: Tuesday, 27 July 2021 at 05:39 PM

Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 - Properties (5) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 (4951 Views)

Construction Of Mini Bakery/ Office Space By Rotech77 / Construction Of 8flats, 4units Of 2bdrms /4 Units Of Mini Flats By Rotecch77 / The Finishing Of Osun State Edifice By Rotech77 (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (Reply) (Go Down)

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 9:47pm On May 22
beehorla:
Well done sir, jst a quick one, u don't show
On ur reinforcement works for d over-site concrete before casting or no reinforcement was done? And wat is d dept of ur excavation.

The depth of our trench here is 1m
We used hard core mixed with filling sand for our foundation, that is what the structural details ask us provide and used
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by Mup4life: 3:20pm On May 23
Pls sir can you tell me what you used for this protector?

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by Austinosconst: 5:24pm On May 23
rotecch77:


The depth of our trench here is 1m
We used hard core mixed with filling sand for our foundation, that is what the structural details ask us provide and used

can you please tell me why you didn't introduce plinth beam before the oversite concrete?
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 6:58pm On May 23
Austinosconst:
can you please tell me why you didn't introduce plinth beam before the oversite concrete?

We follow structural details here.
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 6:59pm On May 23
Mup4life:
Pls sir can you tell me what you used for this protector?

We used thick black square pipe
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by Mup4life: 7:47pm On May 23
rotecch77:


We used thick black square pipe
can you give me the dimension of the pipe sir or a clearer pics
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by Austinosconst: 5:22am On May 24
rotecch77:


We follow structural details here.
so your structural engineer didn't tell you the essence of plinth beams for a building of this magnitude.
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 6:08am On May 24
Mup4life:
can you give me the dimension of the pipe sir or a clearer pics

1/2” square pipe
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 1:16pm On May 24
We follow details in our work, not assumptions

Pics update
Columns done, lintel loading ...

1 Like

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 7:51am On May 25
Lintel in progress
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 5:32pm On May 27
Progress work

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 8:35am On May 28
1st floor slab loading...
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 9:33am On May 31
Pics coming soon
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 8:24pm On Jun 01
1st floor slab preparation is in progress

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 6:55am On Jun 02
Exactly 2 months ... ground floor done and dusted

1 Like

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 4:35pm On Jun 03
1st floor slab loading.....
Hmm which way Naija ...... 12mm local reinforcement 425k per tn

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by Jumyg: 4:45pm On Jun 03
rotecch77:
Exactly 2 months ... ground floor done and dusted

Well done Rotech
Can you help share materials and labour costs for (Superstructure) blockwork to decking level.
Thank you.
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 8:59am On Jun 04
Jumyg:

Well done Rotech
Can you help share materials and labour costs for (Superstructure) blockwork to decking level.
Thank you.


I will try do that in my free time and post it here
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 2:34pm On Jun 04
Slab formwork for the EATERY section almost finished.

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 9:34am On Jun 08
Slab reinforcement in progress
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 9:32pm On Jun 09
Pics loading
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 7:03am On Jun 11
Update pics

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 12:09pm On Jun 11
More update pics loading
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 3:52pm On Jun 11
More

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 1:19pm On Jun 12
More update soon
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by BiigTee: 8:55am On Jun 14
We are back to decking... To everyone following this project.. Including the owner of the project.. I have 1 or 2 things to say!
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by dongc(m): 11:17am On Jun 14
BiigTee:
We are back to decking... To everyone following this project.. Including the owner of the project.. I have 1 or 2 things to say!

Please I know you are hurt and I feel for you....let's find a way to sort this....
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 8:46am On Jun 21
Load of update pics coming soon, as we are busy for some days going round to check all our work progress
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 9:10am On Jun 22
Work still in progress on the reinforcement arrangement

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 8:30pm On Jun 22
More progress pics

Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 8:52am On Jun 23
-Remains part of the slab reinforcement setting still in progress.
- electrical piping loading
- mechanical piping also loading
Watch out for update pics
Re: Construction Of Contemporary Eatery (fast food)And 6 Flats By Rotech77 by rotecch77(m): 6:29pm On Jun 23
More

(1) (2) (3) (4) (5) (6) (7) (Reply)

Palm Beach Estate Lekki I / PROPERTIES AVAILABLE FOR LET IN SURULERE RELOADED 4th August / ESTATE AGENT, Drop Your Pin And Add D Following Pin To Ur Contact For Networking

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2021 Oluwaseun Osewa. All rights reserved. See How To Advertise. 67
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.