Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:38pm On Jul 25, 2021 |
We return all Glory to God Almighty for providing us yet with another contract. We have been contracted to construct a 3Bedroom Semi-detached Duplex and 6units of a room and parlour self-contained for residential and commercial purpose. Location: Oba, Anambra state. Client: A secondary school classmate. Contractor: STINOS ENGINEERING AND CONSTRUCTION SERVICES LTD. 09033750422. stinos.engineering@gmail.com Features: Ground floor: Entrance Porch. Ante-room. Guest toilet. Main Lounge. Dinning. Kitchen with store. Laundry. 2units of a room and parlour self-contain. First floor. Master's bedroom. Madam's bedroom. Children's bedroom. Private family lounge. 2units of a room and parlour self-contain. Pent floor. 2units of a room and parlour self-contain.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:41pm On Jul 25, 2021 |
We cleared the little grasses we met at the site.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:44pm On Jul 25, 2021 |
This is where our building will stand.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:51pm On Jul 25, 2021 |
...
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:53pm On Jul 25, 2021 |
Setting out profile.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:55pm On Jul 25, 2021 |
Pegging
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:57pm On Jul 25, 2021 |
Setting completed and the labourers are ready to start excavating.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:59pm On Jul 25, 2021 |
...
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 5:01pm On Jul 25, 2021 |
Men at work.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 5:05pm On Jul 25, 2021 |
Our excavation depth is 1000mm and width is 675mm
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by itzitz: 5:58pm On Jul 25, 2021 |
Good work sir Am really Following Want to really learn from here Just graduated as civil engineer |
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 2:15am On Jul 26, 2021 |
itzitz: You are welcome bro. Stay tuned. |
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 2:21am On Jul 26, 2021 |
We have about 3000 pieces of 9" blocks ready to be used and about 90 tons of coarse and fine aggregates. This will be enough for the foundation block work and blinding of the foundation footings/concrete work for the starter columns and plinth beams respectively.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 2:21am On Jul 26, 2021 |
9" blocks
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 2:22am On Jul 26, 2021 |
More
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 2:26am On Jul 26, 2021 |
16mm steel bars are also available for the column base basket and starter columns. More steel reinforcements will be be supplied later.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 3:10pm On Jul 26, 2021 |
Iron benders are preparing the column base baskets and starter columns.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 3:14pm On Jul 26, 2021 |
To ensure that the 6" thickness of concrete for the foundation footing is at the same level we used this pieces of bamboo sticks. This can also be done by using steel rod. 1 Like
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 3:18pm On Jul 26, 2021 |
Our column base baskets and starter columns are being positioned. 1 Share
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 4:37am On Jul 27, 2021 |
Concrete work for the foundation footings.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 10:24am On Jul 27, 2021 |
Still on the blinding of the foundation footings.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 10:25am On Jul 27, 2021 |
Men at work
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 10:26am On Jul 27, 2021 |
Adequately compacted.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 6:11am On Jul 28, 2021 |
Concrete work for the foundation footings has been completed and foundation block work will commence ASAP.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 3:05pm On Jul 30, 2021 |
Foundation block work in progress.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 3:06pm On Jul 30, 2021 |
All will leveled at the plinth level today.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 3:49pm On Jul 30, 2021 |
Rounding off the block work for this high foundation.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 5:46pm On Jul 30, 2021 |
More foundation block work.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by STINOS(m): 5:50pm On Jul 30, 2021 |
Iron benders will start work tomorrow for the plinth beams.
|
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by Plomo: 5:51pm On Jul 30, 2021 |
Nice |
Re: Construction Of Semi-detached 3bedrm Duplex & 6units Of 1room & Palour Self Con. by Tinubuadvocate: 6:55pm On Jul 30, 2021 |
That land doesn't look like swampy area so why the high foundation is for you engineer know how to waste materials. |
12500 ft with a 4 bedrooms Bungalow @ Ilorin -ajase Expressway / Where To Settle - Ibadan Vs Abuja? Analyse Or Give Your Opinion Please / Newly Built Houses For Sale In VGC And Lekki Phase 1
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 16 |