BeamNIGERIA's Posts
Nairaland Forum › BeamNIGERIA's Profile › BeamNIGERIA's Posts
Rejoice04:Quite obvious from the attached pictures, DPM and DPC was omitted during construction process, resulting to movement of moisture (dampness). Meanwhile using of bad plaster sand (with salt content), poor workmanship in mortar joints, vegetations e.t.c. can also result to similar defects. In solution, I advise you employ one or combinations of the below listed techniques. 1. Insert a new DPM or DPC; it's technical in approach and will cost you quite much but it's a lasting solution. 2. a. Hack off existing plaster from wall (within the affected level) and expose through about a course layer below the external ground level. b. Apply about 3 layers of bituminous paints and cement wash at intervals c. Plaster the affected wall with water resistant admixtures. 3. As mentioned earlier by gbadexy, carry out concrete flooring around the perimeter of the building. Thanks |
HENDRICK123:To start with, I advise you engage a professional and relate your concept with him |
Jdesigns:Greetings The answer to the question you asking is relative. There is a standard price rate for excavation per cum. Calculate the cum of total foundation excavation from the drawing multiple by the rate. Its going to help you bargain with labour. My observation..... please on that plan where is the kitchen? What's the rationale behind having the windows less that 1m? even in the sitting room? A whole lot of coordination and spatial issues on that drawing. My advice, engage a professional, at least for the client's sake. Thanks all the best |
Currently the blocks are going and it's my pleasure to share with you progress of work so far till date.
|
We commencing blockworks with the timeline of five days
|
Work had resumed on site a long time ago but we have been so occupied to keep updates. Apologies please. Amongst this, we have had issues with funding from the client, because we committed to delivering not only quality but sustainable works we recognized the challenges and bear with the client. Foundation The foundation is completed on schedule, we have three courses of blocks at the front of the building and seven courses at the rear, this was due to the steppy nature of the soil we had mention earlier. Consuming total of 1200 9 inches blocks. Spetic tank The spetic tank is 85% completed. To reduce burden cost of back filling, the soil excavated from the soil is used to backfill the foundation. Backfilling and Oversite concrete Total number of 5 trips of 20tons laterite filling was bought in addition to backfill the foundation which compacted manually at three intervals. Oversite concrete was recently completed, despite the fact that the client shows his concerns as regards the projected cost of carrying out this activity, we kept our stand, stressing the importance of following construction standards by using fabric mesh and having a damp proof membrane. This was difficult for him and we understood him clearly, But again it pays to do it right at first attempt. We couldn't compromise even if we had to carry out some at our own cost.
|
Successbay:Good morning, as you have requested, it's important you attach corresponding architectural drawings to obtain a realistic quotation and timeline for plastering the mentioned property or least, a site visit is made to obtain physical measurements. Thanks |
Excel70:y In your approach to correct or contain these defects few questions needs to be asked, as it will give a precise insight. No two structure is 100% identical Like... What's the type of structure in question? Are sure it's just a column that's failing or it's only noticeable on a column alone? where is this column located in the structure/on floor? ...... |
Raddie:It's called roof ties |
Royruky:Possible, you can install back splash at sink level. I believe this would take care of water coming in contact with your wall and prevent your paint from losing its appealing qualities in quick time. |
BananaTree:That point on third mainland bridge is unilag water front |
Nkemakonam62:but wait, above picture isn't lagos trade fair complex, thats TBS/race course. |
The 150mm drilling process lasted for a day using manual method, terminating at the depth of 20meters. The quality water obtained from physical examination and taste is good for construction purposes.
|
The pace of work is quite impressive as we were able to achieve blinding, using 1:4:8 and casting of column base (1:2:4) on day 2. To aid smooth operation of all site activities, we needed to facilitate easy access to good water, we had to sink a borehole. This is covered under project preliminaries. Having hinted the client on amount of filling sand that would be required for backfill the foundation. He approved the exacavation of septic tank (4m x 2m x 3m). This excavated earth will be used to backfill the building foundation and the Septic tank will serve temporarily as a water reservoir.
|
The site is been characterized with steep slopes up to -900mm to the site datum at the deepest part. Which will require a lot of filling |
Site clearance has been carried out and foundation setting followed up almost immediately. The site soil condition is very firm and stable, however we have a very bad topography having up to -900mm change in level. This necessitated a stepped foundation (strip), consisting of 18 column pits 750mmx750mm.
|
Brick et al a multi-faceted indigenous construction company, establishes strong expertise providing quality construction and environmental solutions. Our team comprises of qualified Built environment practitioners. We currently constructing a four (4) bedroom bungalow on a plot of land in Ikorodu area of Lagos state. The client's brief specified a contemporary country home, has to be efficient in energy consumption and sustainable and low budget. The projected analysis and architectural drawing is contained below. SITE ANALYSIS Site Area - 648 sqm Area of building - 169 sqm (26.08%) sqm Landscape area - 479 sqm (73.92%) Estimated budget for construction - N4.5million PROJECT timeline - 6 months We are mobilizing to site on the 10th of January, 2018, God willing and we will be glad to provide updates as site activities progress. THANKS
|
