PropertiesRe: Newly Built 4 Bedroom Duplex With Swimming - 1 Plot 60/120fit by Dennis3D(op): 5:54am On Aug 16, 2018
EgunMogaji:
Out of curiosity:

Why is the house facing away from the pool?

Why is the pool taking up primary space in the compound?
That's the best position of the pool on such plot and the client wants it that way. Thank You.
PropertiesNewly Built 4 Bedroom Duplex With Swimming - 1 Plot 60/120fit by Dennis3D(op): 3:53am On Aug 16, 2018
When we talk about building design and construction. We don't just talk. We actually do what we say and we mean business in saying that. Guaranteed. Space management and beautiful landscape is paramount with air ventilation. When you go through our page profile you think it's just designs we do or we just do like others do. No we lead others follow. To cut the story short. Our very active page here and on Facebook at www.facebook.com/Dennis3Ds says the rest. We design and build homes not houses +2347038166370, +2348081465833, Dennis3ddesigns@gmail.com

Details of Site
- 4 Bedroom Duplex
- Swimming Pool
- Security House and Gen House
- Car park for 4 cars minimum.

See photos for yourself...

PropertiesRe: Build This Executive 4 Bedroom Bungalow With 10m Naira (Foundation - Finishing) by Dennis3D(op): 7:06am On Aug 12, 2018
mexxy1:
I am the same person that talked to you about blurring. I already saw the plan. I told you about blurring because you exposed the interior of a clients living room and his name which is unprofessional.

What I'm asking is to understand it properly and how a modification of your design will affect the price you stated. I hope you get me now?

You can paste a clients plan (but, with clients permission) and not exact location or interiors when client has moved in.
Modifications like these can affect the cost of building this...

- Roofing sheet to be used
- Roof Facial Design
- Interior Finishing
- Painting Choice of quality
- Kitchen modification
PropertiesRe: Vacant Thread by Dennis3D(op):
.
PropertiesRe: Build This Executive 4 Bedroom Bungalow With 10m Naira (Foundation - Finishing) by Dennis3D(op): 12:36pm On Aug 11, 2018
The building plan is uploaded here already but I personally blurred it however if you can zoom in. You will see it's the plan for the designed 3D.

We don't reveal clients internal plans online on a public space like this however, serious prospective clients can check out some of our works when you contact us.

We have loads and loads of work. We work everyday and so we always have something to show you.

Our Facebook page speaks volumes for us... www.facebook.com/dennis3ds
PropertiesRe: Build This Executive 4 Bedroom Bungalow With 10m Naira (Foundation - Finishing) by Dennis3D(op): 12:33pm On Aug 11, 2018
mexxy1:
Very lovely exterior and, details are interesting. I hope we can see all the views if you don't mind?

A few questions;
1. Assuming you site this building on a plot like you have done, where will the soak away be?

2. What are the dimensions of the building (LXW)?

3. Assuming the sitting room seats 10 persons max., dining room seats 6 persons max. and we jettison the bar. What would the estimated cost be?

4. Does the #10m cost include the fence, paving stones, borehole and tank stand and, the external bar in the 3D or just the building from foundation to finish. Kindly clarify.

Thank you.
To answer your questions
1. Soak away and all are behind with place to spread clothes and over head water tank. I may share the site plan here.

2. I can share the building area here when I upload the site plan.

3. Cost can only be done when I have the client brief on choice of quality.

4. No. 10m here is the main building. Fencing, paving doesn't come in together with landscaping. Just the main building. Borehole not included. Septic tank not included. Soak away not included.

But like I said. We can always work with client budget if it's feasible. If it's not we will tell you. Because we are on field and we have first hand information about the cost of these things in a building of which clients can verify on their own.

In building construction. There are things for the following categories of client.

- Low income
- Average Income
- High Income
- Executive income as the case may be...
PropertiesRe: Build This Executive 4 Bedroom Bungalow With 10m Naira (Foundation - Finishing) by Dennis3D(op): 4:50am On Aug 11, 2018
More views

PropertiesBuild This Executive 4 Bedroom Bungalow With 10m Naira (Foundation - Finishing) by Dennis3D(op): 4:48am On Aug 11, 2018
Hello Great Nairalanders,

We bring to you once again another design. This time a four bedroom executive Bungalow. Mark that word executive Bungalow. It's a Bungalow that challenges a Duplex any day any time but in terms of exterior design and interior design. Trust me when I say this because I did the design.

Plan contains the following spaces:
- Visitor's waiting area with visitors toilet
- Large Sitting Room that can seat 10people minimum
- Bar of 7 people minimum
- Dinning for 6 minimum 14 people maximum
- Guest Room with toilet and Bath
- 2 Other Rooms with toilet, bath and wardrobes
- Large Masters Bedroom of 25sqm room area, large wardrobe, toilet and bath contains jacuzzi, stand alone shower, WC, Two Taps and space also in it.

Now who best can give you such plan. This will seat comfortably with car parks at a plot of 60/120fit as shown in the 3D. Now the finishing would comprises of POP, Screeding, good tiles and painting...


Please Note:
The design is not for low income client to start with.
Location and Economic Factors like inflation and prices different in location can affect budget either positively or negatively...
We can design a low budget design too for average client for less building cost as well... We are keen to delivering quality services and designs according to their budget...

Interested in having our plan. Contact Dennis3D on +2347038166370, +2348081465833 or email at Dennis3ddesigns@gmail.com we respond 24/7. Visit our profile to see more of our Designs and construction here or on our Facebook page which is active 24/7 - 365days a year on www.facebook.com/dennis3ds like page to be getting updates from new designs uploads. Share with your friends. Our Instagram handle and Official website is on the way where you can quickly upload your request with your brief of work directly.

We give quality service and construction management.
We lead, others follow...

Now get the calls coming...

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 4:23am On Aug 11, 2018
Hello guys,
Sorry the updates haven't come recently. Have really been busy on site.

We can gladly tell you now that we are at the parapet as at August 9th. Every concrete work is done.

It's been a collective efforts of all...

Now it's time for the building to set well more. No roofing for now till some weeks later.

PropertiesVacant Thread by Dennis3D(op):
.
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 3:29pm On Aug 06, 2018
mexxy1:
I have been following you and your jobs and, you're doing well but, I have to point out to you that you're very unprofessional in your approach to showcasing your jobs.

Take note of the following;
1. Try as much as possible to post pictures of your jobs and not of you.

2. It is very unprofessional to post the interior of a client's living room no matter what statement you're trying to make.

3. Another unprofessional attribute you have is posting actual names of clients. I would rather you post the clients moniker (for those on nairaland) or blur the names (for those on or not on nairaland).

That being said, I wish you well in your jobs. Thank you.
Thank you for your observations
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op):
....
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 12:21am On Aug 06, 2018
Photo update from today

Day 20 — August 5th
Dennis3D is working
07038166370, 08081465833
Dennis3ddesigns@gmail.com

We don't stop at anything... We are almost there. Started the parapet carpentry works today... Welder to commence tomorrow Day 22 - August 6th.

First see photos

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 12:12am On Aug 06, 2018
mufutau55:
You don try well, well o. Keep it up Sir.

Hajji M.
Pls how do I advertise - boost my posts here. Pay and boost on property section. I need more details on how to go about this...
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op):
Today been day 20 of this construction. Watch out as we start the parapet carpentry works today. Leveling was completed yesterday 4th August making it Day 19.

We are still moving on and on... See photos of yesterday works before leveling commenced...

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 5:12am On Aug 04, 2018
mufutau55:
You don try well, well o. Keep it up.

Hajji M.
Thanks Hajji. Your guy is loyal. Doing stuff gradually
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op):
DAY 18 of the Project.

More photos from today August 3rd...
Seeing is believing...

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 8:44pm On Aug 03, 2018
Today 3rd August - This is how far we went. Casting of the upper floor Lintel and Columns just after two days block work.

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 6:02am On Aug 03, 2018
After going to check for the design roofing facial we initially designed and couldn't get it in the market here in pH. We therefore resort to casting parapet now. But first I have redesigned the roof pattern just yesterday. Reviewed with client and its accepted.

Here is the new approach now. Now that's why we are extremely competent and fast because from design to construction. We are always on ground providing additional support to our client.

Note: this parapet design is more cost effective than the curved shaped one. Which we did the design too and presented the 3 different roofing designing to the client to pick from.

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 5:55am On Aug 03, 2018
August 2nd 2018

We are at Lintel already. That's day 17 of our work
.. More pictures to follow as we cast today August 3rd.

PropertiesRe: Construction Of 3bdrs Cottage structure By Rotecch. by Dennis3D(m): 5:51am On Aug 03, 2018
Well done partner
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 4:44pm On Aug 02, 2018
Dominionng:
Cost depends on size and thickness. Ranges from 10k - 35k a piece

Sizes: 1.2m x 2.4m, 1.2m x 3m

Thickness: 6mm, 8mm, 10mm 12mm, 20mm
You are 100% correct with this info. I confirmed from the dealers in Lagos this exact information you wrote here.
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 11:38am On Aug 02, 2018
gordonbarrett:
Thanks for the information. Do you have any idea of the size and cost of the board?
I have a contact for the board dealer in Lagos but not here in ph. In fact I went out this morning to look for the board at mile 3 in PHC here. I didn't find it. So am going to change the roof facial now to concrete facial with its own design. Am currently designing it on my system now. I have communicated with the client about it though so we have other options...
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 8:51am On Aug 02, 2018
InvertedHammer:
/
Ever considered concrete and materials lift. It pays for itself overtime. I try to bypass waste.

You are trying o! Rain in PH is on another level. I had to abandon ship in June after rain no gree make we progress.

No rain on Fridays because of Ikwerre burials ( grin grin grin) that's what I heard and it seemed to work.

Well...Kudos!

/
Hmmm rain in PHC is something else especially at this time of the year. It's been raining everyday here but thank God that the times I don't need the rain to fall it wouldn't. Thank God for that. Not my power. Example. The day we cast decking. It rain heavily on the Sunday morning 30th July in PHC. In fact I almost gave up on the rain. By 8am it stopped and was drizzling. By 10am sun ☀ came out and was really shining very well. Till evening. The next day was sun too for two days. It's been nice and challenging at the same time.
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 8:47am On Aug 02, 2018
Dominionng:
It is called Cement Board sir. Kalsi is a brand.

Beautiful thread by the way.
Thanks for that info. Very important
PropertiesVacant Thread by Dennis3D(op):
.
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 11:35pm On Aug 01, 2018
Client: Nairaland
Project Location: Gbagada Project Lagos State
Architect: Dennis3D
Contractors: Dennis3D

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 11:33pm On Aug 01, 2018
This year alone I have been opportune to do 4 projects currently ongoing. I designed all and am doing the construction.

I have an in depth knowledge of these foundation types.

- Strip
- Strip and Pad.
- Isolated Pad
- Raft
- A combination of either of two or more foundation types.

The locations I have projects ongoing are
- Lakowe Ajah Lagos
- Oke Aro Ogun State
- Gbagada Lagos State
- Uratta North Imo State
- PHC River State of which this thread is capturing it. Other projects listed here have their own thread and posts here in my profile. You might want to take your time to check it out...

We design and build homes not houses...
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 11:27pm On Aug 01, 2018
An ongoing project I designed for a Nairaland client and am currently building it too in Ajah. Started it February this year. Here is the 3D and the real life construction images.

PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op): 11:24pm On Aug 01, 2018
ogaibe1:
Mr Dennis, I see your doing your thing already, I like the bold steps you have taken to feature your work here, there are a lot of professionals just like you and be ready to answer questions so that the trust and confidence in your work can stand out. I like what am seeing already and am confident that you have more project including mine loading.
Thank you sir. Pls feel free to ask your questions anytime for anything about construction. I am very deep into building design and construction and am willing to help.

As we speak. Am currently doing some projects for two Nairaland clients. Big projects... And I can share the pictures here
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Dennis3D(m): 10:43pm On Aug 01, 2018
educhigo:
please urgent advise needed,can i build 1 upstair 6flat with 5 inches blocks please i need and urgent answer
No. It's not advisable.
PropertiesRe: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(op):
Hello guys. Today 1st August Birth to this... We are already at the upper floor lintel level... Pillars in place, lintel to continue tomorrow while the Carpenter starts upper floor chain round again...