Details of this foundation. Estimated cost 14.4m Foundation height is 1.5meters or 5 boards as you may call it. Foundation dimension width is 13meters by 19.5meters in length. Filling of foundation is estimated to cost about 20 Trips of 20 Tons Sharp sand.
Bags of Cement for entire foundation work is estimated to cost 435Bags. Of which 258 was used for the ground beam (base and Raft)... And 30 For Blinding. The remaining would be for the foundation slab concrete works.
The formwork and reinforcement make up a large portion of the foundation Budget while sharp sand and granite followed suite... We estimated 8 trips of 20 Tons granite and sharp sand.
Sharp sand here is 95K while granite here is 195K for each 20 Tons respectively |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 2:28pm On Jun 30, 2023 |
... |
Properties › Re: Luxury Construction - 7 Bedroom Smart Duplex (mansion) - Lekki Lagos by Dennis3D(op): 2:28pm On Jun 30, 2023 |
... |
Properties › Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(op): 2:28pm On Jun 30, 2023 |
... |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 2:22pm On Jun 30, 2023 |
We are starting the filling of the foundation today.
|
Properties › Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(op): 10:03am On Jun 29, 2023 |
Our work |
Properties › Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(op): 10:03am On Jun 29, 2023 |
... |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 9:57am On Jun 29, 2023 |
.... Formwork removal...
|
Properties › Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(op): 9:53pm On Jun 28, 2023 |
Our work |
Properties › Re: Luxury Construction - 7 Bedroom Smart Duplex (mansion) - Lekki Lagos by Dennis3D(op): 9:52pm On Jun 28, 2023 |
Our work |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 9:50pm On Jun 28, 2023 |
More views from our work here during Raft concrete works
|
Properties › Re: Isheri Construction - 4 Bedroom Luxury Duplex with 2 Bed BQ by Dennis3D(op): 2:44pm On Jun 28, 2023 |
BiigTee: Thank you chief.. Range plastering? Range Plastering may be more. Because now and then are not the same |
Properties › Re: Isheri Construction - 4 Bedroom Luxury Duplex with 2 Bed BQ by Dennis3D(op): 1:26pm On Jun 28, 2023 |
BiigTee: Oga Dennis...i know it's not ideal to ask but pls what's the projected cost of labour for plastering this building and fence without cost of supervision... Trying to use this as a guide since mine has a similar size to this! Good afternoon sir, about 700K |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 8:01am On Jun 28, 2023 |
We were able to finish up the concrete works yesterday as planned. We budgeted about 250Bags of Cement for the ground beam works. We ended up using 258 total with the Base casting included.
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 8:00am On Jun 28, 2023 |
BiigTee: Following keenly . Welldone oga Dennis Good morning Sir. Thanks sir. |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 1:34pm On Jun 27, 2023 |
More views from here
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 1:33pm On Jun 27, 2023 |
We are doing the Raft concrete works today. Find attached pictures of this...
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 6:28pm On Jun 26, 2023 |
Preparing the Raft for concrete works
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 10:34am On Jun 26, 2023 |
We are forming the Raft itself now. Hoping to do concrete works tomorrow before wallah break.
|
Properties › Re: Isheri Construction - 4 Bedroom Luxury Duplex with 2 Bed BQ by Dennis3D(op): 5:29am On Jun 26, 2023 |
Good morning Viewers |
Properties › Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(op): 5:29am On Jun 26, 2023 |
Good morning followers |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 5:28am On Jun 26, 2023 |
Good morning Viewers |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 7:00pm On Jun 25, 2023 |
.
.
.
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 10:25am On Jun 25, 2023 |
Keep following up with us |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 4:53pm On Jun 24, 2023 |
Concrete works on the base of the Raft first. We decided to deploy this method to increase work quality and efficiency...
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 4:01am On Jun 24, 2023 |
Plumbing piping from foundation
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 10:15am On Jun 23, 2023 |
Reinforcement Works and detailing
|
Properties › Re: Isheri Construction - 4 Bedroom Luxury Duplex with 2 Bed BQ by Dennis3D(op): 6:24pm On Jun 22, 2023 |
Our work |
Properties › Re: Owerri Project - 4 Duplex And 4 Units Of 2 Bedroom Flats by Dennis3D(op): 6:23pm On Jun 22, 2023 |
Stay tuned |
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 5:56pm On Jun 22, 2023 |
Work update from here today Plumbing Materials arriving to site
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 8:01pm On Jun 21, 2023 |
Reinforcement detailing now ongoing
|
Properties › Re: 6 Bedroom Contemporary Smart Duplex - Isheri North by Dennis3D(op): 9:35am On Jun 21, 2023 |
We just commenced concrete Blinding
|