Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 3:21pm On Dec 09, 2023
Chidimercy:
Please engineer, what's the size of this soakaway, and what's the labour cost for digging the soakaway?
This soakaway is 13 feet deep, 14 foot length, 7 feet wide. Labour N80,000 for digging only.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 4:00pm On Dec 09, 2023
spyder880:
This soakaway is 13 feet deep, 14 foot length, 7 feet wide. Labour N80,000 for digging only.
Thank you Engineer
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op):
After tiling all the rooms in this house, we are now completing the tiles of the staircase ..............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:30am On Dec 10, 2023
Then we supplied all the sanitary wares needed for this house this week.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:32am On Dec 10, 2023
Then we started to install the WC in all the bathrooms.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:34am On Dec 10, 2023
More.

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:50am On Dec 10, 2023
All the ceiling in this house has been painted............, now we're starting to paint inner room walls........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:55am On Dec 10, 2023
Meanwhile, outside this house...............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:03am On Dec 10, 2023
We have painted the parapet and some hoods and designs on this building............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:44am On Dec 10, 2023
A view from the back of this house..........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 12:41pm On Dec 10, 2023
spyder880:
We have painted the parapet and some hoods and designs on this building............
Engineer please I am almost this partner of house but a 3 storey building. I am bothered how the parapet and belting would be painted since I have removed the scaffold.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:13pm On Dec 10, 2023
Chidimercy:
Engineer please I am almost this partner of house but a 3 storey building. I am bothered how the parapet and belting would be painted since I have removed the scaffold.
The only other option is hiring a painter that can do the same work with a ladder. Another option, although will be costly will be to erect a makeshift iron scaffolding work for the painting of the parapet and window hoods. Thanks.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 2:06pm On Dec 10, 2023
spyder880:
The only other option is hiring a painter that can do the same work with a ladder. Another option, although will be costly will be to erect a makeshift iron scaffolding work for the painting of the parapet and window hoods. Thanks.
Engineer God bless you,
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 10:32pm On Dec 13, 2023
spyder880:
We have painted the parapet and some hoods and designs on this building............
Is this off-white Engineer
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:59am On Dec 14, 2023
Gen2men:
Is this off-white Engineer
No this is white.

Welcome.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by denzel231: 8:25am On Dec 15, 2023
Oga Spyder and the engineer in the house. See the quotation they give me for floor stamping.. na Edo state I dey. I feel it's a bit expensive.. how una se am .


***Estimate for 200 sq meter foreign stamp floor**

1. cement 105bags× 5,700 =#598,500
2. 30tones of half inch granite with transport =#585,000
3.3
4trips of sharp sand (2in1 tipper)×45,000= #180,000
4. 15 (buckets) of color hardener 12,500=187,500
5. Release Agent 1 bucket #70,000
6. Ranging pipe 10×5,500=#55,000
7.Ramming machine 35,000
8. polish (70 litres)×4,000=#280,000
9. color paste 5kg = 25,000
10. transport to bring load to site #20,000
Materials Total=#2,036,000

Labour 1700×200msq= #340,000

SUM TOTAL #2,376,000
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 11:46pm On Dec 22, 2023
We are still working at this site...............

Painting of walls in progress, the staircase now has new tiles............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 11:52pm On Dec 22, 2023
Balconies all painted.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:27am On Dec 23, 2023
Painting of the outside walls of this house started a few days ago...............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:33am On Dec 23, 2023
Gradually taking shape............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:38am On Dec 23, 2023
More...........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:32pm On Dec 30, 2023
Painting of this house continues.................

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:41pm On Dec 30, 2023
More from around the house......

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:48pm On Dec 30, 2023
Some pictures from the back of the house ...............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:51pm On Dec 30, 2023
Closer at the balconies at the back of the flats................

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:54pm On Dec 30, 2023
More from the works we're doing around the house, ducts, covers and scaffolding removal............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:58pm On Dec 30, 2023
From the other side of the back..............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:00pm On Dec 30, 2023
Tiling the bottom of the walls, with wall belts to top off..............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by kingralph(m): 9:29pm On Dec 31, 2023
spyder880:
Tiling the bottom of the walls, with wall belts to top off..............
Spyder your work remains impressive as always! Happy new year
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 10:13pm On Dec 31, 2023
kingralph:
Spyder your work remains impressive as always! Happy new year
Happy new year bro
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 3:59am On Jan 04, 2024
spyder880:
More from the works we're doing around the house, ducts, covers and scaffolding removal............
Spyder is this the usual ducts cover made with aluminum profile.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:13am On Jan 04, 2024
Gen2men:
Spyder is this the usual ducts cover made with aluminum profile.
No, this particular duct cover is made with metal fabrications. Its more stylish and the opening process is better.
1 2 3 ... 12 13 14 15 16 17 18 ... 20 Reply

The Making Of Asaba Stepped Up Two Storey Building. COMPLETED !!!The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms"New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East.234

Two-Storey Building Collapses In Zaria, Four People Dead (Photos)Beautiful Pictures Of Life In Festac Town During Its Early StageDemolition Going On At Ojudu/Alagbole For The Ogun Road Project