PropertiesRe: Urgent Advice On Construction by SVPROJECT(m): 4:12am On Jan 05, 2019
Crownofwealth:
Like which stage sir?
Lintel Level
PropertiesRe: Urgent Advice On Construction by SVPROJECT(m): 7:46am On Jan 04, 2019
Crownofwealth:
Happy new year Nairalanders. Please i urgently need your advice on this issue.
Will the sum of 2 million naira be enough to buy a small piece of land and erect a three bedroom flat apartment up to roofing level?

NB: Its just an average house.
It can progress to a considerable level, But cnt be completed.

example is this our project of 3bedroom flat https://www.nairaland.com/4936862/cost-construction-three-3-bedroom

Can provide you sketch with detailed estimate

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: FINISHING DIARIES: Pop,Screeding,Window Works,Plastering&Rendering, Gate Et Al by SVPROJECT(op): 7:32am On Jan 04, 2019
Plastering of Outer Walls


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com

PropertiesRe: FINISHING DIARIES: Pop,Screeding,Window Works,Plastering&Rendering, Gate Et Al by SVPROJECT(op): 7:28am On Jan 04, 2019
Plastering Of Parapet Fascia

PropertiesRe: FINISHING DIARIES: Pop,Screeding,Window Works,Plastering&Rendering, Gate Et Al by SVPROJECT(op): 7:25am On Jan 04, 2019
Erection of Scaffold

PropertiesFINISHING DIARIES: Pop,Screeding,Window Works,Plastering&Rendering, Gate Et Al by SVPROJECT(op):
https://www.nairaland.com/4843886/cost-how-built-project-3

In continuation of the project on the aforementioned link above, We commenced the finishing ranging from POP,Screeding,Window Works,Plastering&Rendering, Gate Fabrication, Window Hood, Burglar Proof, Tiling, Plumbing & Electrical Works.


Land Size |392.04 sqm
Project Status | Ongoing Development:
Budget | Confidential
Duration | Work As You Pay
Commencement Date: December 2018
Client | A Nairalander.
Location: Lagos Mainland.



We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(op): 10:45pm On Jan 03, 2019
Asquare84:
50 k for omonile if I am the owner of the building I will go to the site with my AK 47
We should have done that project since 2016, They Omo Onile demand was unbearable, We had to wait till we were able to soften their balls.
PropertiesRe: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(op): 10:43pm On Jan 03, 2019
oginga:
I am following this thread closely so as to serve as a guide to me. I am starting my second project at the end of this month and I want to complete everything within a month.

It's going to be a 5 bedroom bungalow... 6500 blocks, 350 bags of cements, 3 tippers of granites,10 tippers of sharp sand, water tank and borehole all already paid for.

POP and roofing experts please come_In with price of various roofings for 2019... Thanks
Still updating the project on another thread, I used stonecoated roof tiles, POP and Screeding too has been completed.

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com

PropertiesRe: Builder Needed In Benin City by SVPROJECT(m): 8:24pm On Jan 03, 2019
Check my moniker for cost friendly project we have embarked on.


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(op): 8:14pm On Jan 03, 2019
Materials Total: 308,500
50 Bags of Cement: 125,000 only 20 Bags used for substructure
20 Tons of Granite: 90,000
Sharpsand: 55,000
Water: 4,000
Starter Column Reinforcement: 32,500
DPM: 2,000


Labor : Setting Out, Block Trans-loading, Trench/Column Base Excavation,Concrete Blinding, Reinforcement Works, Block Works to DPC Level, Casting of DPC Hollow Space: Confidential But Considerate

Misc Total: 57,800
Omo Onile Foundation Settlement: 50,000
Refreshment & Drinks: 7,800

PropertiesRe: Material Requirements For 2bedroom Flat by SVPROJECT(m): 7:55pm On Jan 03, 2019
istorenig:
Pls could any proffessional tell the quantity of blocks and sink I need for this plan?

Thanks in advance
Roughly 2,105 blocks From Foundation to Lintel/Final Level.
Your Roof type determines the wood d roofing sheet needed.

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: Electrical Quotation Needed For 5bedroom Flat(PICTURES) by SVPROJECT(m): 7:48pm On Jan 03, 2019
Chimex388:
Good day all, Happy sunday. smiley.Jst hope this is the right section for this..
Please I'm in need of a estimate for a standard electrification or wiring of a 5bedroom flat. From the piping, wiring to the fittings..I'm sorry i dont have the plan..
Please Engineering guyz, buulding gurus, electricians, help me out..

1.) 5Rooms with(Toilet, Bathroom n small Kitchen

2.) 1 Sitting room
3.) 1 Dinning
3.) 1 Varender
4.) 1 Visitors toilet
Note the ffg please..
1.Its a full internal conduit wiring design..
2.The toilet and Bath are under one room-unit
2.Only 1 kitchen is Big enough for Cooker unit...
3.Sitting Room will have about 5 lighting points..
4.Whats the best wire type in Nigeria or good enough? Because thats what i want to be used.

Breakdown of materials and price will be much appreciated.

Thanks guyz...Any input parameter needed, just drop the qtn(s), i will gladly attend to them..Thanks..
Lije i said,No drawing plan at the moment,its in progress
Looking forward to your replies..
Are you making use of water heater for the rooms and kitchen? Conduit Wiring or Surface Wiring?
Any provision for A/C ?

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: Building Contractor Needed. by SVPROJECT(m): 7:45pm On Jan 03, 2019
ifexsmarttech:
My name is Mr. David and I reside in Anambra state, please I want to build six rooms with (just) toilets inside the room. For tenants, the rooms will be on a straight line. How much should I budget for this project and if I can get a break down, I will really appreciate.
What's the dimension of the land? Any provision for kitchen?
i can provide a detailed plan if suitable to your taste, Estimate will e provided without delay.

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: Plz Want Know How Much Dey Are Doing Digging And Pegging . by SVPROJECT(m): 7:34pm On Jan 03, 2019
fizcoo20:
3 bedroom.
Have you got a building plan or i provide you one if suitable to your taste? Call or Whatsapp 07031112625
PropertiesRe: Plz Want Know How Much Dey Are Doing Digging And Pegging . by SVPROJECT(m): 9:49am On Jan 03, 2019
fizcoo20:
d site his behind Caleb university. iyana- emuren.
Iyana Emuren is firm, Imota/Aleke axis.

What’s the plan to be pegged, How many flats/bedroom?
PropertiesRe: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(op): 8:41pm On Jan 02, 2019
The Proposed Building is to be sited behind the Cassava plantations as a setback
PropertiesRe: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(op): 8:39pm On Jan 02, 2019
We Moulded 32 Bags of Cement.
2 Trip of Sand: 38,000 X 2: 76,000
32 Bags of Cement X 2,500: 80,000
Labor: 800 per bag X 25,600
Water: 2,000
Total: 183,600

Outcome: 9";800 Unit
6: 400 Unit

PropertiesCost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(op): 8:30pm On Jan 02, 2019
Project Status | Ongoing Development:
Duration | 10 Days
Commencement Date: December 2018
Client | A Nairalander.
Location: Ogun State
To Do: Block Moulding,Sub-Structure Level to Lintel Level, Excavation of Septic Tank for Filling Purpose


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com

PropertiesRe: Plz Want Know How Much Dey Are Doing Digging And Pegging . by SVPROJECT(m): 8:29pm On Jan 02, 2019
fizcoo20:
want to know how much dey are doing digging and pegging for foundation @ IKORODU. thanks in anticipation.
The design and the actual area will determine the cost, I have done some projects in Ikorodu d i can tell you the soil condition differs (Ebute/Oluodo is slightly swampy with loose Soil, Maya/Adamo/Agbowa is a bit rocky)


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 7:54pm On Jan 02, 2019
OK

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by SVPROJECT(m): 6:50am On Dec 31, 2018
miracle1997:
I will like to ask a question,is it advisable to use a 6inch block for foundation(dry land)... Like is it ok
It’s advisable you stick to 9inchs on your foundation to enable uniform structural stability. subsequent partition walls can be 6”.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by SVPROJECT(m): 6:49am On Dec 31, 2018
Sumuni:
Hello everyone, please can someone help me with contact details of competent builders at Imota after Ikorodu that can help complete a building and monitor the quality of work done. Thank you all.
I’m familiar with Imota and Ikorodu in General, Call or WhatsApp 07031112625 then we take it up from there.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by SVPROJECT(m): 6:23am On Dec 21, 2018
Godson213:
Please how much can do foundation of two bedroom in Borija Ibadan? Can 400 do foundation plus workmanship?
Why Not? It all depends on size of the features (living Room,Bedrooms et al) and the nature of the land( Firm or Swampy)
Let’s discuss 07031112625(Call&Whatsapp)
PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 7:34pm On Dec 01, 2018
We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com

PropertiesRe: Solution For A Leaking Decking by SVPROJECT(m): 8:16am On Nov 27, 2018
Apply Waterproof cement on it.
PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 3:52am On Nov 26, 2018
More coming
PropertiesRe: Can 500,000 Naira Raise A Foundation Of 4 Bedroom by SVPROJECT(m): 7:31am On Nov 21, 2018
businessman7:
Good day house please I need your help I am 23 years old student of laspotech and I've been able to raise money to get the land and other documentation ha e been put in place please I want to know how far 500k can go in building a 4 bedroom bungalow please your advice and estimation is needed thanks you in advance
Absolutely Possible, Depending on the dimension of the proposed project and land condition.

We are starting something similar with a low budget by 1st Week in December.
PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 7:20am On Nov 21, 2018
Ground Floor Block Work
2 Units of 2Bedroom Flat

PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 2:05pm On Nov 19, 2018
G.F Slab

PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 2:04pm On Nov 19, 2018
Ground Floor Slab Works

PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 1:55pm On Nov 19, 2018
DPM; 7,000 naira
Boarding of DPC.
Delivery of Ground Floor Slab Material

PropertiesRe: Cost & How We Built A Project Of 3 Nos Of 2bdrm & 1 Nos Of 3bdrm Aptmt(14m.) by SVPROJECT(op): 1:44pm On Nov 19, 2018
Casting of Starter Columns and Sand Filling of DPC/ Wetting and Compacting.