Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,195,305 members, 7,957,773 topics. Date: Tuesday, 24 September 2024 at 07:55 PM

What Is The Standard Sequence Of Finishing Activities - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / What Is The Standard Sequence Of Finishing Activities (470 Views)

Cost Of Finishing A 2bedroom Apartment? / Designed Pillars, Interlocking Tiles, Fancy Finishing / Estimate Of Finishing A Block Of 4 Flats (2) (3) (4)

(1) (Reply)

What Is The Standard Sequence Of Finishing Activities by jidody(m): 5:48pm On Sep 30, 2014
Hi guys,

Please I need recommendations on the set sequence of the following activities required to finish a duplex under construction at Ajah Lagos.:
1. Installation of outdoor plumbing pipes.
2. Tiling of the indoor floors and walls.
3. POP of the ceiling and some walls.
4. Fixing of the doors (internal and external).
5. Painting of the internal; walls.
6. Painting of the external walls.
7. Installation of the Electrical fittings.
8. Installation of the plumbing fittings (toilet seats, baths etc).
9. Outdoor landscaping (flooring, interlocking stones etc).
10. Changing regular gate to gate with wheels.

Thanks

(1) (Reply)

Beacon Court Selling Now!!!!!! / Clean And Standard Apartments In A Serene Environment In Port Harcourt(view Pics / 4 Sale Newly Build 4brm Detached Duplex At Ogudu Gra Lagos See Pic 120m,100m,70m

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 7
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.