What Is The Standard Sequence Of Finishing Activities by jidody(m): 5:48pm On Sep 30, 2014
Hi guys,

Please I need recommendations on the set sequence of the following activities required to finish a duplex under construction at Ajah Lagos.:
1. Installation of outdoor plumbing pipes.
2. Tiling of the indoor floors and walls.
3. POP of the ceiling and some walls.
4. Fixing of the doors (internal and external).
5. Painting of the internal; walls.
6. Painting of the external walls.
7. Installation of the Electrical fittings.
8. Installation of the plumbing fittings (toilet seats, baths etc).
9. Outdoor landscaping (flooring, interlocking stones etc).
10. Changing regular gate to gate with wheels.

Thanks

(1) (Reply)

One Bedroom Available In A Very Clean Compond In Port Harcourt. Call 08137844500 / Very Reasonable Real Estate Investment / Water Front For Sale In Wimpey,port Harcourt.

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 6
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.