Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,150,718 members, 7,809,719 topics. Date: Friday, 26 April 2024 at 01:53 PM

How To Solve Time And Work Alternate Days Working Problems? - Educational Services - Nairaland

Nairaland Forum / Nairaland / General / Education / Educational Services / How To Solve Time And Work Alternate Days Working Problems? (651 Views)

Bachelor Dual Study Program – Study And Work In Poland. / Do You Want To Study And Work In Canada? / Study And Work In South Africa For As Little As N61,000 Monthly (2) (3) (4)

(1) (Reply)

How To Solve Time And Work Alternate Days Working Problems? by aakashbiyani03: 3:24pm On Aug 30, 2016
Dear Naira users!

Please help me find a way out to solve problems related to time and work related problems in which two persons working alternate days. Kindly help me with this.

1 Like

Re: How To Solve Time And Work Alternate Days Working Problems? by Smartkeeda: 3:22pm On Sep 08, 2016
Dear Aakash!

To solve a time and work question in which efficiency of two or more persons is given and we are asked how many days will they take to complete the given work working alternately.

Let's take an example here.
Ex. A and B take 6 days and 4 days alone to do a piece of work. How many days will they take if working alternately?

Explanation:

Step 1. Calculate the combined efficiency of A and B of 2 days = 1/4 + 1/6 = 5/12
Step 2. Think of a multiple of the numerator part of the above fractional value that should be close to the denominator but it shouldn't exceed the denominator. In the given case, it would be 5 x 2 = 10.

Step 3. Multiply this multiple into both the sides LHS and RHS. We thus get,
Combined efficiency of A and B of 4 days = 10/12 or 5/6

Step 4. Calculate the rest of the work by subtracting the combined efficiency from 1. We get, 1 - 5/6 = 1/6

Step 5. Now, as it's A who starts the work, therefore, after working for 4 days it's once again A's turn whose 1 day's efficiency is given as 1/6.
Which means he will take one day to complete the remaining work.

Step 6. Total number of days required = 4 + 1 = 5 days.

We hope it helps. You can drop a query here if anything you want to discuss. You can also go to the link to get more such explanations on the page.

http://smartkeeda.com/Quantitative_Aptitude/Arithmetic/Time_and_Work/newest/all/

Regards,
Smartkeeda
Re: How To Solve Time And Work Alternate Days Working Problems? by Eowriand389: 10:14pm On Sep 14, 2016
Hello every one, how are you? smiley

(1) (Reply)

Study In North Cyprus / Free Project Topics And Materials For Computer Science / !s O S ! Help Pls, Unilag "mba" Program

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 11
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.