Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States (9095 Views)

How To Calculate Number Of Blocks For Your Building Project In 2 Simple Steps. / DEVELOPER ADVICE How To Get Building Plan Approval In Lagos / Building Plan Approval Requirements And Processes In Nigeria (2) (3) (4)

(1) (2) (Reply) (Go Down)

Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 7:14am On Mar 03, 2017
The following are the reasons why your building plan approval take long to be approved in Lagos & other states;

1. Not charting your land: charting is wen the surveyor at the planning office helps you check d status of your land may b it under government acquisition, d type of land use dat ur land can be used for.

2. Not pre-screnning your drawings before submitting to approval: pre-screening is when your architectural drawings, structural, electrical or mechanical drawings are checked by d government specialist to check if the drawings a ok or nt, if nt ok they comment and u correct den you show dem again. Ones d drawings a ok, I promise your approval wnt go beyound 4-_6 weeks.

3. Not having correct documents like C of O, tax clearance certificate

4. Nt doing follow up: you need to have at least one person that will give you info on where you file is

For more visit www.egcandassociates.org.ng

Lalasticlala
Seun
Ishilove
Marpol
Semid4lyfe
Obinoscopy

2 Likes

Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by okunfemm(m): 7:29am On Mar 03, 2017
Not charting.... U need me (surveyor) as ur number 1 on land issues..... Check my signature
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 7:30am On Mar 03, 2017
okunfemm:
Not charting.... U need me (surveyor) as ur number 1 on land issues..... Check my signature

I hope u read well, wat wld dey use to chart is it nt survey plan? Mr man pack well
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 10:44pm On Mar 03, 2017
Lalasticlala
Seun
Ishilove
Marpol
Semid4lyfe
Obinoscopy


U guys wnt push Dis to d front nw abi
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by wizzlyd(m): 7:20am On Mar 04, 2017
.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by AdonaiRoofing(m): 7:21am On Mar 04, 2017
Thanks for enlightening us

Contact us for all your roofing jobs and roof maintenance etc
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Hoddor(m): 7:23am On Mar 04, 2017
OK, thanks for the info.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by TenPassfour(m): 7:24am On Mar 04, 2017
PLEASE BE SPECIFIC AS THIS ABOVE INFORMATION MIGHT NOT TOTALLY BE REASON AS PER OTHER STATE IN NIGERIA. THANK YOU FOR PUTTING UP THIS TREAD BUT BE KORE SPECIFIC AS EACH STATE HAS ITS OWN LAW THAT GOVERN THEM.
@SEUN
LALASTICALALA
THANK YOU GUYS FOR THIS FORUM#MY2CENT
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by money121(m): 7:28am On Mar 04, 2017
Ok

Nice one from the Op... Call/WhatsApp 080-85-310-359 for your Next Roofing Project..

See Recommendation below from Loyal clients on Nairaland..

Current Price of Roofing Sheet in Nigeria.. See here >> https://www.nairaland.com/3364135/roofing-sheets-cost-various-types

Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 7:33am On Mar 04, 2017
I help run Building Plan Approval.......If you have building plan you want to approve in Lagos, that's what I do.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by danemenike: 7:37am On Mar 04, 2017
Structural drawing guru
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by okunfemm(m): 8:21am On Mar 04, 2017
shams040:


I hope u read well, wat wld dey use to chart is it nt survey plan? Mr man pack well


And who wil prepare d survey plan u just mention, Pls check my signature for more info
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Zabilon007(m): 8:53am On Mar 04, 2017
Dannyset:
I help run Building Plan Approval.......If you have building plan you want to approve in Lagos, that's what I do.
omonile grin
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 9:15am On Mar 04, 2017
shams040:
The following are the reasons why your building plan approval take long to be approved in Lagos & other states;

1. Not charting your land: charting is wen the surveyor at the planning office helps you check d status of your land may b it under government acquisition, d type of land use dat ur land can be used for.

2. Not pre-screnning your drawings before submitting to approval: pre-screening is when your architectural drawings, structural, electrical or mechanical drawings are checked by d government specialist to check if the drawings a ok or nt, if nt ok they comment and u correct den you show dem again. Ones d drawings a ok, I promise your approval wnt go beyound 4-_6 weeks.

3. Not having correct documents like C of O, tax clearance certificate

4. Nt doing follow up: you need to have at least one person that will give you info on where you file is

For more visit www.egcandassociates.org.ng

Lalasticlala
Seun
Ishilove
Marpol
Semid4lyfe
Obinoscopy

It our work that why we could give you some hints to aid quick approval process.

For more info: www.egcandassociates.org.ng
08165536883, 08116568722
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dieumerci(m): 10:17am On Mar 04, 2017
shams040:
The following are the reasons why your building plan approval take long to be approved in Lagos & other states;

1. Not charting your land: charting is wen the surveyor at the planning office helps you check d status of your land may b it under government acquisition, d type of land use dat ur land can be used for.

2. Not pre-screnning your drawings before submitting to approval: pre-screening is when your architectural drawings, structural, electrical or mechanical drawings are checked by d government specialist to check if the drawings a ok or nt, if nt ok they comment and u correct den you show dem again. Ones d drawings a ok, I promise your approval wnt go beyound 4-_6 weeks.

3. Not having correct documents like C of O, tax clearance certificate

4. Nt doing follow up: you need to have at least one person that will give you info on where you file is

For more visit www.egcandassociates.org.ng

Lalasticlala
Seun
Ishilove
Marpol
Semid4lyfe
Obinoscopy
Thanks for the info, but I thought that Lagos state doesn't require C of O for approval again.

Do they accept that e-tax card?
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 10:26am On Mar 04, 2017
Dieumerci:

Thanks for the info, but I thought that Lagos state doesn't require C of O for approval again.

Do they accept that e-tax card?

The issue on C of O is dat, u must av at least started the processing and payed for it even if it nt out you will be given a clearance letter to process your building plan approval.

Yes they accept it. All you just need is to make photocopy is the card front and back bec the number on it is what they need.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 10:47am On Mar 04, 2017
Zabilon007:
omonile grin
Lolzzz! Nope, I work with Lagos State Building Control Agency(LASBCA).

1 Like 1 Share

Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 10:51am On Mar 04, 2017
shams040:


The issue on C of O is dat, u must av at least started the processing and payed for it even if it nt out you will be given a clearance letter to process your building plan approval.

Yes they accept it. All you just need is to make photocopy is the card front and back bec the number on it is what they need.
You can now do your approval without the C of O. After getting the number you can now proceed with your C of O.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by rafcrown(m): 11:30am On Mar 04, 2017
LETS TALK about it..My email is adecrown22@gmail.com.
Dannyset:
I help run Building Plan Approval.......If you have building plan you wask Nairaland membernt to approve in Lagos, that's what I do.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Nissybright(m): 11:41am On Mar 04, 2017
For your structural, steel and road design...you can contact me 08066385008
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Astrogeotech02: 12:43pm On Mar 04, 2017
no building is safe without a proper soil investigation.
check my signature....
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Fadolistic(m): 1:05pm On Mar 04, 2017
Good day ma'ams/sirs, have you heard of ENVIROSHADE? ENVIROSHADE is a Nigerian company in technical partnership with CAPESHADE of South Africa, dedicated to provide innovativeand cost effective solution in all weather shades! So do you need a carport to protect your lovely cars? Or you just need a shade for your swiming pool? How about an entrance shade to give yourbusiness or home that sophisticated look? What are you waiting for? We offer the best possible quality and design. Original galvanised steel. Best possible finish and design - high density polyethylene shade net triple stitched with a monofilament thread and applying french seam stitching techniques...... Get in touch with ENVIROSHADE now via email: Frankfounder@gmail.com or through their telephone number: 0703 859 2625, 08077356782, 08029226311. Hurry!!!! You wont regret it ..

Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 1:39pm On Mar 04, 2017
Dannyset:

You can now do your approval without the C of O. After getting the number you can now proceed with your C of O.

It not so my brother am a Town planner and u knw we a more into dat. U must av payed for ur C of O and get ur clearance letter. Aldo ur C of O myt nt even b ready bt u must av payed d necessary fees.

When ever u a grated approval check d big stamp on it, it is writing that 'this approval those nt garranty you ownership of land' which means C of O is needed bt due to delay in getting C of O Lagos govt nw say u can process approval without c of O bt u must av atleast made payment for C of O.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 1:41pm On Mar 04, 2017
Astrogeotech02:
no building is safe without a proper soil investigation.
check my signature....

This is needed if d building is above 3 floors or commercial
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 1:44pm On Mar 04, 2017
Dannyset:


Lolzzz! Nope, I work with Lagos State Building Control Agency(LASBCA).

Whc district a u?
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 1:59pm On Mar 04, 2017
shams040:


It not so my brother am a Town planner and u knw we a more into dat. U must av payed for ur C of O and get ur clearance letter. Aldo ur C of O myt nt even b ready bt u must av payed d necessary fees.

When ever u a grated approval check d big stamp on it, it is writing that 'this approval those nt garranty you ownership of land' which means C of O is needed bt due to delay in getting C of O Lagos govt nw say u can process approval without c of O bt u must av atleast made payment for C of O.
No Sir! All that is needed now is the authenticity of your survey plan and this can be thru your land information.

1 Like

Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 2:00pm On Mar 04, 2017
shams040:

Whc district a u?
Ikorodu
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 2:17pm On Mar 04, 2017
Dannyset:

No Sir! All that is needed now is the authenticity of your survey plan and this can be thru your land information.
all

All Dis must b done for u to get c of o man. Ask ur district officer for better explanation. U need a clearance letter or else ur file will end up in dat store call kiv keep in view
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 2:18pm On Mar 04, 2017
Dannyset:

Ikorodu

Ok, dat my TPL shomolu side
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 2:44pm On Mar 04, 2017
shams040:
all

All Dis must b done for u to get c of o man. Ask ur district officer for better explanation. U need a clearance letter or else ur file will end up in dat store call kiv keep in view
I think we should stop arguing on this.
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by Dannyset(m): 2:45pm On Mar 04, 2017
shams040:

Ok, dat my TPL shomolu side
Shomolu has been posted out of Ikorodu. Beckly is now the D.O
Re: Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States by shams040(m): 2:49pm On Mar 04, 2017
Dannyset:

Shomolu has been posted out of Ikorodu. Beckly is now the D.O

Ok

(1) (2) (Reply)

Finishing Our Beach House (new Dimension To Nigerian Architecture) / Property At Sani Abacha Road G.r.a Port Harcourt / Do You Have Any Questions Or Enquiries On P.O.P Ceiling? Get In Here

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 46
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.