Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 9:26pm On Jan 15, 2018 |
K.C SYSTEMS LTD Architect and Builder Construction Of Semi-detached 8Unites Of 2bedroom flats attached with an office complex @ Illorin in Progress Construction works started December 2017. Below are the progress reports and pictures of work so far done; 1) Site Clearing and Excavation completed 2) Raft beam formwork, reinforcements and concrete work completed 3) Reinforced floor slab concrete works completed 4) Ground floor block works and plumbing works completed
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Rubbiish(m): 9:46pm On Jan 15, 2018 |
Why raft foundation sir? Do they also have poor soil in illorin? |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by ArcSEMPECJ(m): 2:06am On Jan 16, 2018 |
The drawing plans have the same design pattern chief,..that staircase at the rear view is not relating,..hope you made mistake in pasting the wrong plan....... Modified ,....I can now relate it well,...feels the staircase is too much for just two spaces,....good luck on your project...hope to see site photographs |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 4:07pm On Jan 16, 2018 |
Rubbiish: From the soil test result the soil is bad and raft was one of the recommendation |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Rubbiish(m): 4:08pm On Jan 16, 2018 |
kcsystems:Okay sir |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Rubbiish(m): 4:10pm On Jan 16, 2018 |
ArcSEMPECJ:The circular staircase will be use for emergency exit I think it is cool |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 4:16pm On Jan 16, 2018 |
Rubbiish: Thanks |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 4:17pm On Jan 16, 2018 |
ArcSEMPECJ: Thanks for the observation |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 4:24pm On Jan 16, 2018 |
1) Site Clearing and Excavation completed 2) Raft beam formwork, reinforcements and concrete work completed 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 3:35pm On Jan 17, 2018 |
3) Reinforced floor slab concrete works completed 4) Ground floor block works and plumbing works completed 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 5:44pm On Jan 18, 2018 |
5) First floor form work slab competed 6) Reinforcement still in progress
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 1:45pm On Jan 24, 2018 |
1) Reinforced upper floor slab completed 2) Upper floor slab concrete works completed 3) Upper floor electrical and plumbing works completed 4) Upper floor block work in progress 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 2:41pm On Jan 28, 2018 |
Progress of works so far 1) Block works in progress 2) Reinforcement work on lintels and columns in progress 3) Form work on lintels and columns in progress 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Enyinne(f): 7:22pm On Jan 28, 2018 |
Weldon. Is this project being done on a full plot of land. |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 12:15am On Jan 30, 2018 |
Enyinne: Yes |
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 5:35pm On Feb 13, 2018 |
Progress of work so far 1) Form work of 2nd floor in progress 2) Reinforcement work in progress 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 12:41pm On May 03, 2018 |
Above are Pictures of progress of work so far 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 9:34am On Aug 18, 2018 |
Quite a while this is the completed stage of the project thank you 1 Share
|
Re: Construction Of Semi-detached 8unites 2bedroom Flats with atached Office Complex by Nobody: 5:25pm On Jan 05, 2019 |
THANK YOU ALL FOR MAKING 2018 A FRUITFUL YEAR FOR US WE SINCERELY APPRECIATE YOUR PATRONAGE *WISHING YOU A PROSPEROUS 2019* |
(1) (Reply)
Promo Promo Promo Buy 5 Get 1 Free At Just 700k.bricks Courts Scheme 2, / If You Are In Abuja Kano Or Kaduna Check Out This Floor Finishings / .
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 18 |