Cost & Construction Of Three(3) Bedroom Flat . - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Cost & Construction Of Three(3) Bedroom Flat . (1745 Views)

Construction Of 4bedroom Duplex With 2bedroom 2flat Attach At AIT Road Alagbado / Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) / Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice (2) (3) (4)

(1) (Reply) (Go Down)

Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 8:30pm On Jan 02, 2019
Project Status | Ongoing Development:
Duration | 10 Days
Commencement Date: December 2018
Client | A Nairalander.
Location: Ogun State
To Do: Block Moulding,Sub-Structure Level to Lintel Level, Excavation of Septic Tank for Filling Purpose


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com

2 Likes

Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 8:39pm On Jan 02, 2019
We Moulded 32 Bags of Cement.
2 Trip of Sand: 38,000 X 2: 76,000
32 Bags of Cement X 2,500: 80,000
Labor: 800 per bag X 25,600
Water: 2,000
Total: 183,600

Outcome: 9";800 Unit
6: 400 Unit

1 Like

Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 8:41pm On Jan 02, 2019
The Proposed Building is to be sited behind the Cassava plantations as a setback
Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 8:14pm On Jan 03, 2019
Materials Total: 308,500
50 Bags of Cement: 125,000 only 20 Bags used for substructure
20 Tons of Granite: 90,000
Sharpsand: 55,000
Water: 4,000
Starter Column Reinforcement: 32,500
DPM: 2,000


Labor : Setting Out, Block Trans-loading, Trench/Column Base Excavation,Concrete Blinding, Reinforcement Works, Block Works to DPC Level, Casting of DPC Hollow Space: Confidential But Considerate

Misc Total: 57,800
Omo Onile Foundation Settlement: 50,000
Refreshment & Drinks: 7,800

Re: Cost & Construction Of Three(3) Bedroom Flat . by ZhyonKross(m): 9:14pm On Jan 03, 2019
Nice work please continue really looking forward to seeing you soon
Re: Cost & Construction Of Three(3) Bedroom Flat . by Asquare84(m): 9:35pm On Jan 03, 2019
50 k for omonile if I am the owner of the building I will go to the site with my AK 47

1 Like

Re: Cost & Construction Of Three(3) Bedroom Flat . by oginga: 10:34pm On Jan 03, 2019
I am following this thread closely so as to serve as a guide to me. I am starting my second project at the end of this month and I want to complete everything within a month.

It's going to be a 5 bedroom bungalow... 6500 blocks, 350 bags of cements, 3 tippers of granites,10 tippers of sharp sand, water tank and borehole all already paid for.

POP and roofing experts please come_In with price of various roofings for 2019... Thanks

1 Like

Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 10:43pm On Jan 03, 2019
oginga:
I am following this thread closely so as to serve as a guide to me. I am starting my second project at the end of this month and I want to complete everything within a month.

It's going to be a 5 bedroom bungalow... 6500 blocks, 350 bags of cements, 3 tippers of granites,10 tippers of sharp sand, water tank and borehole all already paid for.

POP and roofing experts please come_In with price of various roofings for 2019... Thanks

Still updating the project on another thread, I used stonecoated roof tiles, POP and Screeding too has been completed.

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com

1 Like

Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 10:45pm On Jan 03, 2019
Asquare84:
50 k for omonile if I am the owner of the building I will go to the site with my AK 47
We should have done that project since 2016, They Omo Onile demand was unbearable, We had to wait till we were able to soften their balls.
Re: Cost & Construction Of Three(3) Bedroom Flat . by oginga: 2:54am On Jan 04, 2019
SVPROJECT:


Still updating the project on another thread, I used stonecoated roof tiles, POP and Screeding too has been completed.

We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
Nice one sir.
Re: Cost & Construction Of Three(3) Bedroom Flat . by macho44(m): 6:51pm On Feb 02, 2019
Asquare84:
50 k for omonile if I am the owner of the building I will go to the site with my AK 47
That wan small, at Oko-afo they requested for 150k for fence alone and another 150K for Foundation. See as pipu take wicked�
Re: Cost & Construction Of Three(3) Bedroom Flat . by Crownofwealth(m): 8:05am On Apr 01, 2019
SVPROJECT:
We Moulded 32 Bags of Cement.
2 Trip of Sand: 38,000 X 2: 76,000
32 Bags of Cement X 2,500: 80,000
Labor: 800 per bag X 25,600
Water: 2,000
Total: 183,600

Outcome: 9";800 Unit
6: 400 Unit
How many blocks did you mould? was it sufficient for the construction to roofing level?
Re: Cost & Construction Of Three(3) Bedroom Flat . by Tonymegabush1(m): 9:08am On Apr 01, 2019
Happy stumbling upon this thread I have done building contract as a site contractor, hopefully will be overseeing another building after easter ( 3storey building) location enugu state.... Hopefully I will learn 4rm this thread and improve on areas of correction....
Re: Cost & Construction Of Three(3) Bedroom Flat . by Tonymegabush1(m): 9:15am On Apr 01, 2019
At op i was made to understand that erecting a building on top a cassava farm was not really a gud move as in the site need to stay close to 1-2 yrs even after cutting down and uprooting those cassava roots, I stand to be corrected am just curious to learn
Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 12:44pm On Apr 01, 2019
Crownofwealth:

How many blocks did you mould? was it sufficient for the construction to roofing level?
We got some blocks on site before moulding the current one to compliment what’s on site
Re: Cost & Construction Of Three(3) Bedroom Flat . by SVPROJECT(m): 12:45pm On Apr 01, 2019
Tonymegabush1:
At op i was made to understand that erecting a building on top a cassava farm was not really a gud move as in the site need to stay close to 1-2 yrs even after cutting down and uprooting those cassava roots, I stand to be corrected am just curious to learn
What we constructed was right behind the cassava Farm.
The Cassava Plantation was a cover for the activities at the back.
Re: Cost & Construction Of Three(3) Bedroom Flat . by oalandAgents2: 2:17pm On Apr 01, 2019
nice one follow my post too
SVPROJECT:

Project Status | Ongoing Development:
Duration | 10 Days
Commencement Date: December 2018
Client | A Nairalander.
Location: Ogun State
To Do: Block Moulding,Sub-Structure Level to Lintel Level, Excavation of Septic Tank for Filling Purpose


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
Re: Cost & Construction Of Three(3) Bedroom Flat . by soulchuks: 2:23pm On Apr 01, 2019
good
SVPROJECT:

Project Status | Ongoing Development:
Duration | 10 Days
Commencement Date: December 2018
Client | A Nairalander.
Location: Ogun State
To Do: Block Moulding,Sub-Structure Level to Lintel Level, Excavation of Septic Tank for Filling Purpose


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
Re: Cost & Construction Of Three(3) Bedroom Flat . by soulchuks: 2:27pm On Apr 01, 2019
nice one
SVPROJECT:

Project Status | Ongoing Development:
Duration | 10 Days
Commencement Date: December 2018
Client | A Nairalander.
Location: Ogun State
To Do: Block Moulding,Sub-Structure Level to Lintel Level, Excavation of Septic Tank for Filling Purpose


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
Re: Cost & Construction Of Three(3) Bedroom Flat . by soulchuks: 2:39pm On Apr 01, 2019
GOOD
SVPROJECT:

Project Status | Ongoing Development:
Duration | 10 Days
Commencement Date: December 2018
Client | A Nairalander.
Location: Ogun State
To Do: Block Moulding,Sub-Structure Level to Lintel Level, Excavation of Septic Tank for Filling Purpose


We Design,Build,Renovate and Manage Construction Projects.
S.V Project
Reach Us: Voice & Whatsapp 07031112625
SVProject@yahoo.com
Re: Cost & Construction Of Three(3) Bedroom Flat . by Tonymegabush1(m): 3:41pm On Apr 01, 2019
SVPROJECT:

What we constructed was right behind the cassava Farm.
The Cassava Plantation was a cover for the activities at the back.



OK sir.... Tnks 4 d clarification

(1) (Reply)

Land For Sale At Command (ipaja, Lagos) At 14.5m Asking / Invest in Magodo G.R.A Phase 1, 30Million per plot / First Upstairs Built In Obosi Anambra State

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 26
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.