My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 8:05pm On Apr 12, 2019 |
Ok, I want to share with you guys the progress of my building. First and foremost I'm in the category of low income earners. I earn a little above 100k and for the progress so far, it all boils down to planning and focus. I bought the land from Adron home for N1,275,000 and paid additional fees of N950,000. So far so good these payment took me like two and half years After being allocated the land I started buy materials gradually. So I will list them as much as I can remember - 1000 9 inches block @155 - 155,000 - 30 tons of granite - 145,000 - 20 tons of sharp sand - 55,000 - Setting out, digging of foundation, laying of block to DPC level - 130,000 (Depending on your negotiating power) please engage the service of a competent engineer and do direct labour 7 Likes |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 8:15pm On Apr 12, 2019 |
I dug the soakaway 45,000 and poured the literate into the foundation and also paid labor 20k, engineer chopped me here and gave the guy only 5k (Epic) 1 Like 1 Share
|
Re: My 3 Bedroom Bungalow At Shimawa by Mgbadike80: 8:25pm On Apr 12, 2019 |
Joshcoli:Nice, God would see you through. Please, can you specify the state or city that the project is located? I'm planning a similar project in Niger state. Can you post the floor plan? |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 8:34pm On Apr 12, 2019 |
Ok, I paid someone 20k to evacuate all the dugged sand from the soakaway into the building and also paid about 58,000 to put pillers. These 58k covers 11 piller plus the front 3 pillers, the irons, cement, water, labour and also the carpentry work
|
Re: My 3 Bedroom Bungalow At Shimawa by erico2k2(m): 9:05pm On Apr 12, 2019 |
Joshcoli:Well done fire down 1 Like |
Re: My 3 Bedroom Bungalow At Shimawa by twinskenny(m): 9:11pm On Apr 12, 2019 |
Joshcoli:well done I live in Ibafo close by.. God will see you through when I get to the stage of electrical and plumbing let Me know... Gods speed 1 Like |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:28pm On Apr 12, 2019 |
Filling
|
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:33pm On Apr 12, 2019 |
Bought four trip of literate at 18,000 each for filling 1 Like
|
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:48pm On Apr 12, 2019 |
Mgbadike80: Thanks, the project is located at Shimawa ogun state 1 Like |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:50pm On Apr 12, 2019 |
twinskenny: Thanks,I will hook you up when I get to that stage |
Re: My 3 Bedroom Bungalow At Shimawa by twinskenny(m): 10:04pm On Apr 12, 2019 |
Joshcoli:God will bless you |
Re: My 3 Bedroom Bungalow At Shimawa by Tammynator(m): 10:57pm On Apr 12, 2019 |
God will help u. As you have planned and begun, you will certainly finish it. But, u didn't include bags of cement bought for the project so far. We would also relish the pleasure of seeing the floorplan. Well done. 2 Likes |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:26am On Apr 13, 2019 |
Tammynator: Ok, many thanks I forgot to mention bags of cement used So far I've used 47 bags of cement Dangote which then was 2,550 per bag. It has gone up to 2,650 per bag now Another thing I want prospective builders to note is that, engineers makes things very difficult for builders because they know you wont be on ground to monitor their work. My little advice is if you can get someone trustworthy to be on site to monitor the work and pay like 3k, it will be very worth it... But those crazy engineers can even buy them over sef... Lol 5 Likes |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:28am On Apr 13, 2019 |
Here at the concrete footing 15 bags of cement was used here 1 Like
|
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:30am On Apr 13, 2019 |
I was playing arround with the plan and I came up with something like these. If you want to do something like this simply go to homebyme.com Register and just draw your plan 4 Likes
|
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:36am On Apr 13, 2019 |
This is the floor plan... 3 Bedroom ensuit with a laundry 1 Like
|
Re: My 3 Bedroom Bungalow At Shimawa by Flocky: 10:33am On Apr 13, 2019 |
This is cool mehn I am sure following this thread. May God see u through |
Re: My 3 Bedroom Bungalow At Shimawa by Mgbadike80: 11:02am On Apr 13, 2019 |
Joshcoli:that's a very compact and economical plan. Good one. |
Re: My 3 Bedroom Bungalow At Shimawa by twinskenny(m): 11:36am On Apr 13, 2019 |
Joshcoli:well designed |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 12:15pm On Apr 13, 2019 |
Right now, I'm at the site about to cast the German floor so far 40 bags of cement has being budgeted, And we killed a snake today... It fell inside one of the soakaway... I tell you that creature is beautiful at the same time fearful Beauty plus fear... What do you call that 1 Like
|
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 12:35pm On Apr 13, 2019 |
Brief analysis of money spent today, I already bought 30 tons of granite (145,000) which was used for the blinding and casting of the pillars. The 20 tons of sand is remaining small so I added another 20 tons of sharp sand (55,000). carpentry is 12,000, renting of Gen plus pipe 5,000 German floor casting 60,000. 40 bags of dangote cement 104,000 Total cost 55,000 + 5,000 + 12,000 + 60,000 + 104,000 Total = 236,000 1 Like |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 3:56pm On Apr 13, 2019 |
Believe me some engineers are devil expecially these my engineers ... Because I decided to be on site the increase the cement mixture ratio just for the sake of wickedness. After these German floor is done I'm changing him ASAP
|
Re: My 3 Bedroom Bungalow At Shimawa by twinskenny(m): 4:10pm On Apr 13, 2019 |
Joshcoli:can u imagine... |
Re: My 3 Bedroom Bungalow At Shimawa by Rubbiish(m): 4:41pm On Apr 13, 2019 |
Joshcoli:Before u change him, ensure he didn't make changes to the floor plan, if he did, tell him to effect it on the plan, so another engineer can continue from the German floor 1 Like |
Re: My 3 Bedroom Bungalow At Shimawa by erico2k2(m): 7:29pm On Apr 13, 2019 |
Joshcoli:U did not add blocks cost |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 8:27pm On Apr 13, 2019 |
Even at 42 bags of cement the job was not done though remaining small From my calculation, if the engineer had used half bag of cement for the mixture, it would have being more than enough but my presence made him to waste cement. He used half and quarter, that is almost one bag for the mixture, I called my friend who is a builder and he told me the engineer is wasting cement because of my presence. It was later corrected after he has already used 32 bags of cement, if not I would have being using about 70 bags of cement to caste a German floor because the idiot was already requesting for additional 20 bags Just imagine
|
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 8:29pm On Apr 13, 2019 |
erico2k2: Just for the German floor alone, I even forgot the plumbing work... 23,000 materials and workmanship From my little experience... You can't escape the fiery hands of an engineer. I think it's better you cooperate with them and give them what they want Just beg them to have mercy on you |
Re: My 3 Bedroom Bungalow At Shimawa by erico2k2(m): 8:39pm On Apr 13, 2019 |
Joshcoli:Not true, You need to know what you want, ie your mix ratio and stick to it, agree on a price with them and stick to that too. Be on the ground as well very important. |
Re: My 3 Bedroom Bungalow At Shimawa by Joshcoli(m): 9:12pm On Apr 13, 2019 |
erico2k2: Though I'm getting the experience now... That's why they say experience is the best teacher |
Re: My 3 Bedroom Bungalow At Shimawa by msrk: 10:29pm On Apr 13, 2019 |
Which of the adron estate, phase 2 or phase 2 extension? |
Re: My 3 Bedroom Bungalow At Shimawa by melvin0004(m): 10:42pm On Apr 13, 2019 |
Nice 1 |
Re: My 3 Bedroom Bungalow At Shimawa by VickyES300: 1:32am On Apr 14, 2019 |
Nice one boss, I bought mine from Adron as well (West Park Garden, Ibadan) and by God's grace next month I would be allocated and I want to start my project immediately. Please keep updating about everything most especially the cost and I wouldn't mind if you can also connect me to a good engineer if you can find one. |
How To Get Building Plan Approval In Lagos / Nigerian Bungalow House Design / Mini Flat, 2 & 3 Bedrooms Flats For Rent @ Ota, Ogun State .
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 52 |