Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 12:20pm On Jul 27, 2019 |
Using a dome shaped tank for the digester is informed by various reasons
1. The dome helps distributed the load on the tank easily to the Foundation, thereby making it as stable and strong as a concrete tank
2. The dome shaped tank help to trap the emitted gas better, thereby giving a higher yield (same reason the top of your gas tank has same dome shape)
The digester is constructed with clay bricks, as is stronger than your average blocks and is easier to shape into a dome shape , because of the size of each brick.
Also every mortar mixture is mix with a water proofing cement/against to ensure the tank is water tight ..
The tank is also plastered as the construction is ongoing, we have at least four layers of plaster at each level to ensure the digester is also air tight .. |
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 12:13pm On Jul 27, 2019 |
More pics of the construction process, building a dome is a very intricate and slow process
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 12:11pm On Jul 27, 2019 |
More ...
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 12:09pm On Jul 27, 2019 |
More
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 12:07pm On Jul 27, 2019 |
More on the digester wall
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 11:56am On Jul 27, 2019 |
Building the digester dome
|
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 5:27pm On Jul 26, 2019 |
dahosa: Could you send me this floor plan to eidahosa96@gmail.com
very nice design Sent |
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 5:05pm On Jul 26, 2019 |
Excavation of digester (dome shaped)
Height: 1.8m Radius: 1.8m
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 5:02pm On Jul 26, 2019 |
Work begins ... Our site is a 8 units 4 bedroom bedroom + attached bq at ikate - elegushi , lekki, Lagos state, built by yours truly
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 5:00pm On Jul 26, 2019 |
Various segment of the biodegradable system are:
1. The inspection chamber /inlet 2. Digester 3. Hydraulic pit 4. Septic tank/slurry pic |
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 10:59am On Jul 25, 2019 |
How it works
When organic material (including human feces, animal waste, and plants) is digested by microorganisms in the absence of oxygen (anaerobic digestion) a gas is released consisting of 60% methane and 40% carbon dioxide. This gas is typically called biogas and because it can be ignited, it may be used as a cooking and heating agent. |
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 6:05pm On Jul 24, 2019 |
Schematic of the system
|
Properties › Re: Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 5:31pm On Jul 24, 2019 |
The methods that would be employed in this process isn't new or recent , it's actually well in use in Ghana, Kenya and some areas in Cameroon, but it's just making its way to the Nigerian market ..
Ps.: I'm not a pro in the construction process yet, but just sharing my experience and little knowledge acquired in working with these guys |
Properties › Documentation Thread: Construction Process Of A Biodegradable Septic Tank System by darenyx(op): 5:26pm On Jul 24, 2019 |
Waste management, disposal and treatment has always been a major and reoccurring problem in the building and construction industry, especially in most areas in Lagos that's are always flooded or where the water table is very high. Septic tanks and soak-away pits tends to get filled up easily, which leads to frequent evacuation, thereby making it uneconomical..
The construction of biodegradable septic tank system is aimed at eliminating totally then need to evacuate waste (both solids and liquids) |
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 12:59pm On Jul 23, 2019 |
... |
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 6:01pm On Jul 18, 2019 |
Contemporary 3 bedroom open floor plan...
Would be posting contemporary open plans , let's see if hv open floor plan lovers here...
Personally open plans are my favourite kind of plans..
All rooms doesn't HV to be ensuite and the kitchen doesn't always HV to be hidden
|
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 10:29pm On Jul 12, 2019 |
Upcoming threads :
Construction of 6 units mini flat Construction of a biodegradable sewage treatment system
|
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 10:27pm On Jul 12, 2019 |
Event center and guest house remodel
Features
Even hall 7 room Pool + outdoor bar Kitchen Laundry
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 8:05pm On Jul 10, 2019 |
Daboomb: Certainly not true! I did TWO plots for #350K in Lagos recently and they initially asked for #200K per plot.
Some actually do it for as low as #150K per plot. Just say that YOU cant do it for that amount, not that others cant do it for that amount or even less. I know your association upped the price about a year or two ago but that does not means some members who are reasonable and flexible will stick to that exorbitant directive.
And this is a Registered Surveyor that l had known for over two decades when survey was #50K/plot so the issue of "wrong hands" is a red herring. Firstly , I'm not a surveyor, Secondly , I posted a document that clearly shows what it cost to get a registered survey done in various areas in Lagos state. And I don't believe fees paid to government agencies are negotiable.. So how you where able to get a registered survey for the stated amount is beyond me, or maybe you did a back dated survey. |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 2:08pm On Jul 06, 2019 |
Part 2
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 1:56pm On Jul 06, 2019 |
Here you go
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 11:25am On Jul 06, 2019 |
zellfoxx: Wow! That's why we are here. For information sharing. I have never seen this document before. What's the title or source of this document or booklet please? Do share so we can be enlightened. These are summary of schedule of survey fees from the office of the surveyor general for Lagos state, can't post a complete PDF files here, so would try and screenshot the entire document and post , so you can see clearly what it entails/cost to get a registered survey done in Lagos state . |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 11:05am On Jul 06, 2019 |
Hum2020: Pls if you spend the sum of 600k to do a survey on a haif plot of land within lagis pls how much was the cost of the land i think this is too much to survey just for half plot of land abba If you have ever tried doing a building approval or any other payments with regards to either buildings and lands you would be shocked as well... That's just the Lagos state government for you , doing things the right way, through the right channel especially with Lagos state government, doesn't come cheap.. |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 9:50am On Jul 06, 2019 |
Just for those doubting ... There's no way you can do a survey in Lagos for 200k.. don't be fooled or decieved
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by darenyx(m): 9:47am On Jul 06, 2019 |
zellfoxx: I've heard people asking for close to 400k sometimes to do a survey in Lagos. I believe its pure extortion.
Meanwhile, to our supply experts. Are 8ft security doors available in the market? And I discovered wooden-finish internal doors are making big waves these days. Are they also available in 8ft height? It not extortion, I recently did a survey for a half plot for 600k... There's no way you can get a survey in Lagos for 200k, that's how people fall into wrong hands |
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 12:28am On Jul 06, 2019 |
6 units 2 bedroom flats
|
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 7:28am On Jul 05, 2019 |
... |
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 11:52am On Jul 01, 2019 |
8units 2 bedroom
|
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 11:07pm On Jun 27, 2019 |
6 units mini flats on a half plot
|
Properties › Re: Contemporary Nigeria Building Designs By Hafux Consuls by darenyx(op): 11:05pm On Jun 27, 2019 |
Event centre + guest house
Ground floor : event hall, reception, kitchen, store , courtyard, pool, outdoor kitchen and poolside bar
First floor : 7 bedrooms , staff area and offices
|
Properties › Re: Building The Badore Block Of Flats by darenyx(op): 11:01pm On Jun 27, 2019 |
New project alert
Construction of 6 units, mini flat on a half plot of land ,.. creating a thread for this soon
|
Properties › Re: Building The Badore Block Of Flats by darenyx(op): 10:58pm On Jun 27, 2019 |
Our ongoing project in warri, Delta state , construction of 6 unit 2 bedroom apartments
|