Properties › Re: Procedure For Building A Storey Building by Hum2020: 6:26pm On Apr 08, 2019 |
tundysho: Good day folks, I would like the experts in the house to take a look at this procedure in starting a storey building of four flats. Advise me on the merits and the demerits in any of the processes, considering safety, structural viability, proper usage of materials, and of course, cost.I would also like to know the importance of German floor, is it very necessary
Dig 3ft deep X 1.5ft wide for the foundation Dig basket base 6 inches deeper 3ft X 3ft Cast basket in basket base with mortar of 1in granite cement and sand Basket is made with Y 16 High yield steel Blind the foundation with 5 inch thick mortar of 1 in granite, cement and sand Lay 6 coaches of 9in block for the foundation Cast the pillars with pre fabricated 16mm rods,3/4in granite cement and sand Fill foundation with laterite Wet laterite with water ram laterite German floor with 3/4in granite Laying of blocks for partitioning the rooms ETC Casting of pillars and lintels ETC |
Properties › Re: Cost Of Building 4 Bedroom Bungalow In Ibadan by Hum2020: 6:33pm On Apr 07, 2019 |
Open good day I know that cost for labour in Ibadan is very cheap so for your 4 bedroom bungalow just bedget between 7 to 9m thanks |
Properties › Re: Best Of Price On Tiles,water Closet,pipes And Fitting Free Home Delivery by Hum2020: 6:12pm On Apr 07, 2019 |
Change your password |
Properties › Re: Best Of Price On Tiles,water Closet,pipes And Fitting Free Home Delivery by Hum2020: 6:11pm On Apr 07, 2019 |
Rotech77Ditto: Old user name "rotecch77" is difficult to access now. |
Properties › Re: Architectural Design & Construction by Hum2020: 8:51am On Apr 07, 2019 |
Ok thanks for your responses I will get back to you let finish with my survey first ok |
Properties › Re: Building A New 6 Bedroom Duplex, A Diary. by Hum2020: 6:54am On Apr 07, 2019 |
Thanks sir nice for your responses |
Properties › Re: Building A New 6 Bedroom Duplex, A Diary. by Hum2020: 11:31pm On Apr 06, 2019 |
Oga spyder greet you thanks for the good job you showcasing on this forum plus I have questions to ask because I see that a top level you start the windows level after 3 courses of setting block plus may I know why thanks for your responses |
Properties › Re: Architectural Design & Construction by Hum2020: 7:05am On Apr 06, 2019 |
Op good day how many unit of flats is this your plans |
Properties › Re: Architectural Design & Construction by Hum2020: 7:04am On Apr 06, 2019 |
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 6:24am On Apr 06, 2019 |
I don't understand what we gain by cheating and lies most buiders.work hard make their moneywhar a roofer to give the right measurement for the job infant if you paid him that amount ir will end up in beer parlour and sleeping around wirh woman whata shame |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 6:12am On Apr 06, 2019 |
|
Properties › Re: Nigerian House Plans: Construction Of A 4-b/room Bungalow@ An Affordable Budget by Hum2020: 6:12pm On Apr 02, 2019 |
Op the wood work and the parapet how did you spend thanks |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 6:10pm On Apr 01, 2019 |
Op good day may we know where gef your breakng news |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 6:05pm On Apr 01, 2019 |
Chekitaut: Breaking New: Cement price raise to N2,500 minimum order of 600bags, N2,550/bag below 600bags |
Properties › Re: 1 by Hum2020: 6:03pm On Apr 01, 2019 |
Good day op what it mean no additon. Strutture should be building on the plot after you may have viur choice of buliding and if you to build and must meet with the management of the estate |
Properties › Re: Present Cost Of Building A 5 Bedroom Duplex In Ikorodu by Hum2020: 5:09am On Apr 01, 2019 |
Since the project ia within lagos budget 8m to 10mn  but i don't think fence and gate is. Induced in the budget thankd |
Properties › Re: QUALITY DOORS HERE FOR SPECIAL DEMAND by Hum2020: 7:29am On Mar 31, 2019 |
Nice door pls can you send the price of this doors to my email humokwara@yahoo. Com thank |
Properties › Re: Architectural Masterpieces From Black Lake House by Hum2020: 5:49pm On Mar 25, 2019 |
Nice job keep it up you remain the best |
Properties › Re: Quick Sales, Plot Of Land In Gwagwalada, Abuja by Hum2020: 7:47pm On Mar 24, 2019 |
Pls are you on What up so we can chat |
Properties › Re: Nigerian House Plans: Construction Of A 4-b/room Bungalow@ An Affordable Budget by Hum2020: 4:35pm On Mar 24, 2019 |
Op nice work you are doing so far how muvh have being. Spend on this project thanks |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 8:17am On Mar 24, 2019 |
Oga Haiji m pls can i have your n number thanks |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 8:15am On Mar 24, 2019 |
Stop your advertisement on this thread. Advert not allowed.
Hajji M.[/quote] |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 5:31am On Mar 22, 2019 |
Pls be careful i dont see the reason why over 336 bag of cement has being use to this stage in thè first place how much is rhe Total cost of this project i Mean the carcass from foundation to roofing Congrat |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 5:25am On Mar 22, 2019 |
Alkanelly: Experts in the house, Please I need help and advice here. Here is my situation. I am in diaspora building a block of 2 bedroom flats, 2 down and 2 up So am currently on the beam and first floor slab of my 4 units of 2 bedroom flats in port Harcourt. At this point the engineer has used 226 bags of cement to do the staircase, beams and one of the two flats on the ground floor, the other flat will be done today which I think may take another 90 bags of cement, so in total I am looking at around 312 bags of cement. My worry is that is that I think so much bags of cement has gone into the slab and beam. The mix ratio he is using is 1:2:3 according to him. I bag of cement, 2 wheelbarrow of sand and 3 wheelbarrow of granite. Is this acceptable, what your advice. The area of slab is 288m2 and I have currently spent up to 3.6 million naira. |
Properties › Re: QUALITY DOORS HERE FOR SPECIAL DEMAND by Hum2020: 12:18pm On Mar 16, 2019 |
Dfameguy: Good evening everyone pls what cost price of this doors |
Properties › Re: Nigerian House Plans: Construction Of A 4-b/room Bungalow@ An Affordable Budget by Hum2020: 6:40am On Mar 16, 2019 |
Op you ate doing a nice work but my queston is on the amount stated for this project can it finished it knowing the cost of building materials in the marketing |
Properties › Re: Nigerian House Plans: Construction Of A 4-b/room Bungalow@ An Affordable Budget by Hum2020: 6:12am On Mar 16, 2019 |
Good work you are dping but can the account s stated. Be able to finished this very project |
Properties › Re: Five School Children Rescued From Collapsed Building In Lagos (Photos) by Hum2020: 5:16pm On Mar 13, 2019 |
Since Buhari came into leadership killing and death every now collasped building in different state within nigerian i think it is hugh time government should look into various types of materials use in building and as well as the contraor handing building in nigeria may the soul of the deptared rest in peace Amen |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 6:04am On Mar 13, 2019 |
Pls op this quotation is too high ok just look for other builder ok |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by Hum2020: 6:02am On Mar 13, 2019 |
shelliz: Good day all. Please i need help, got this bill of quantity from an engineer for the construction of 2 septic tanks/2 soak away with decking. I think the cost is high, what are your opinions please? Is there a recent thread for septic tanks construction here? Thanks all
(60) 12mm rods @2100 unit price =#126000 (5) 8mm rods @unit price 1100 = #11000 (60) 1×12×18 wood @unit price = 2300 = #138000 40 bags of cement @unit price 2500 = #75000 7 tonnes of granite = #45000 half role of binding wire =#3500 Bag of nail #8000 20 bamboo @unit price 200 =#4000 (20)2×3 wood @unit price 1050 =#21000 2 trips of sand #50,000
Labour Digging of 2 septic tanks/soak away #50,000 Setting of the blocks #48000 Plastering #48000 capenter (without decking work) #32,000 Labour for casting #36000 Welder (without decking work) 16000 To pour the decking of the 2 septic tanks #24000
Supervision #40,000
Total #775,200 + cost of blocks + cost of welder and capenter for the decking.
LOCATION : EDO STATE/BENIN CITY |
Properties › Re: For sale half pilot by Hum2020: 7:38am On Mar 09, 2019 |
Good day op pls how much is this half of land |
Properties › Re: Building A New 6 Bedroom Duplex, A Diary. by Hum2020: 7:26am On Mar 09, 2019 |
Oga spyder you have not give us the breakdown of this project well i am looking forward for it thanks |