Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 6:13pm On Aug 16, 2021
We have completed the concrete cast of the DPC on unit 2. More pictures later.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by Pius4me: 8:08pm On Aug 16, 2021
spyder880:
The soakaway system is getting ready to be cast...........
Wow Spyder it is good to see a soakaway system that has more iron than most house suspended slab with top and botton iron. i don't know why we use just one. spyder na you be baba for this job. good soup na money kill am oo.

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 8:16pm On Aug 16, 2021
Pius4me:
Wow Spyder it is good to see a soakaway system that has more iron than most house suspended slab with top and botton iron. i don't know why we use just one. spyder na you be baba for this job. good soup na money kill am oo.
We are preparing the area to be a car park. I need the slab to be adequate for the expected extra load. Thank you bro.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by michlins(m): 8:28pm On Aug 16, 2021
spyder880:
We are preparing the area to be a car park. I need the slab to be adequate for the expected extra load. Thank you bro.
I heard a car park and it's something I do

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 9:26pm On Aug 16, 2021
michlins:
I heard a car park and it's something I do
No problem, we will get there soon. Welcome.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op):
The completion of the soakaway system slab...........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 9:44am On Aug 18, 2021
We have completed the concrete cast of the unit 2 of these fully detached twin duplexes............

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 9:48am On Aug 18, 2021
At the first unit, work is still ongoing despite the rains.......

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 10:02am On Aug 18, 2021
More pictures of this ongoing building from around the first unit.........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 10:12am On Aug 18, 2021
More pictures from the inside of this building, showing the living room, dining room areas..........

The rain here is relentless, but we keep moving with caution......

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 10:27am On Aug 18, 2021
Reinforcement details.........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 6:25pm On Aug 21, 2021
The completed DPC of unit 2 curing slowly under the rain..........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 7:06pm On Aug 21, 2021
Lintels, columns, carpentry completed in unit 1...........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 7:11pm On Aug 21, 2021
More.......

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 7:35pm On Aug 21, 2021
More pictures from this project.......

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 8:10pm On Aug 21, 2021
More pictures from the inside ........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 8:44pm On Aug 21, 2021
Looking at this work from above.........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 7:58am On Aug 23, 2021
We brought a vibrating poker to this site yesterday, we plan to use it for the lintels and columns in this first unit, we plan to start the concrete cast by this morning. Workers are already in the site.......
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op):
Using concrete poker to shake down the concrete casting on the lintels and columns..........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op):
Completed lintel cast..........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 2:25pm On Aug 25, 2021
More pictures of the completed beams...........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 11:01am On Aug 26, 2021
Curing process for the concrete cast, water treatment........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 6:38pm On Aug 30, 2021
Pictures of this house taken on Saturday evening.........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by Kambols95(m): 12:43pm On Sep 01, 2021
@ spyder, you are doing a great job sir......this is how the making up of any building should be especially when the site is water prone.

I only have some few professional questions to ask about your ongoing project sir. Would be glad if you can respond to them all

1. I hope the beams, columns, lintels and slabs achieve the respective curing age before the formwork is removed?

2. I stand to be corrected if am wrong sir, I didn't see anything like a polythene material/membrane used as DPM at the foundation stage.

3. I hope the right type of cement is used for different stages of the construction processes

4. As a good manager on site, one of your major duty is to help the client in reducing the cost of construction but not at the expense of quality. How are you able to achieve this.

Thank you
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 2:09pm On Sep 01, 2021
Kambols95:
@ spyder, you are doing a great job sir......this is how the making up of any building should be especially when the site is water prone.

I only have some few professional questions to ask about your ongoing project sir. Would be glad if you can respond to them all

1. I hope the beams, columns, lintels and slabs achieve the respective curing age before the formwork is removed?

2. I stand to be corrected if am wrong sir, I didn't see anything like a polythene material/membrane used as DPM at the foundation stage.

3. I hope the right type of cement is used for different stages of the construction processes

4. As a good manager on site, one of your major duty is to help the client in reducing the cost of construction but not at the expense of quality. How are you able to achieve this.

Thank you
I am in the market now, I will attend to these questions later this night. Thanks.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op):
Updates

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 3:51pm On Sep 01, 2021
Buying and offloading more blocks in this site today.........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 3:57pm On Sep 01, 2021
Images from the top of the house today...........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 8:49am On Sep 02, 2021
Kambols95:
@ spyder, you are doing a great job sir......this is how the making up of any building should be especially when the site is water prone.

I only have some few professional questions to ask about your ongoing project sir. Would be glad if you can respond to them all

1. I hope the beams, columns, lintels and slabs achieve the respective curing age before the formwork is removed?

Yes, we made sure we treated the completed beams, columns and lintels with more water, we left the work for about a week, and taking that the rains are still falling daily, we are convinced that the curing process here is adequate.

2. I stand to be corrected if am wrong sir, I didn't see anything like a polythene material/membrane used as DPM at the foundation stage.

No we didn't use DPM because the chances of capillary action or dampness of the lower walls are almost zero in this location. There is no natural stream or running water, there is no lakes or even chances of this land or this town ever being waterlogged. I also improved on the situation by lifting this foundation far off from the ground. Some parts of this foundation are as high as 1.5 metres above natural ground level. I am doing this to achieve a good slope which will ensure that all rain water will be channelled outside this compound.

3. I hope the right type of cement is used for different stages of the construction processes

Yes, we have been using recommended cement qualities[/color].

4. As a good manager on site, one of your major duty is to help the client in reducing the cost of construction but not at the expense of quality. How are you able to achieve this.

Advance planning, reuse of wooden formwork and observance of the weather conditions before we start working. This has kept our costs very low in this era of galloping inflation. Thank you Sir.
[color=#000099]
Thank you
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 9:45pm On Sep 04, 2021
Ready for the decking of this house.........

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 12:11pm On Sep 08, 2021
The decking of this house will start anytime soon.

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(op): 6:25pm On Sep 10, 2021
We will be starting the decking of this house as from tomorrow.
1 2 3 4 5 6 7 8 9 10 ... 19 Reply

The Making Of The "7 Bedrooms High Ceiling Bungalow" In AnambraThe Making Of The "Contemporary 6 Bedroom Duplex " In AnambraThe Making Of The "Owerri Royal Manor"234

Know About Geophysical Investigation For Borehole Drilling and othersEver Lived With A Disgusting Roommate? Share ExperiencesUnbelievable..greenland Estate, Sangotedo For #6million (pics attached)

Viewing this topic: 1 guest(s)