Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by southsouthking(m): 12:20pm On Nov 07, 2022
AsomArchitectNG:
For this standard, a budget of 18m will get it done...
Okay, my money never reach like that.
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:24pm On Nov 07, 2022
southsouthking:
Okay, my money never reach like that.
Money must surely come
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by ISTP:
AsomArchitectNG:
Thank you sir...

Today makes it the 40th day...
AsomArchitectNG, please, I'd like to ask a question.

Question 1:

How do you cope with movement?

E.G Presently, you're in Akwa-Ibom for a project.

Client A has a project he/she wants you to supervise and execute until the finish stage in Lagos and at the same time, client B has a project he/she wants you to supervise and execute until the finish stage in Abuja.


How do you shuttle the different locations?

Question 2:

How do you calculate the duration of a building to be completed?

E.G, Engineer A has a 3 bedroom bungalow to be completed for 30 days. Engineer B also has the same 3 bedroom bungalow to be completed for 60 days.

Do you give durations according to your schedules or according to how the building will be constructed or according to how the capital is available?

Question 3:

As a professional architect that you are, do you give customize/specific adjustment/design on buildings?

E.G, Client A wants a basement/underground facility in his/her building but doesn't want it shown on the building plan? Or, client B ask for a 5 bedroom duplex and during construction, he/she wants it changed to a 3 bedroom duplex with a penthouse

I await your response Sir! wink smiley
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 10:12pm On Nov 07, 2022
ISTP:
AsomArchitectNG, please, I'd like to ask a question.

Question 1:

How do you cope with movement?

E.G Presently, you're in Akwa-Ibom for a project.

Client A has a project he/she wants you to supervise and execute until the finish stage in Lagos and at the same time, client B has a project he/she wants you to supervise and execute until the finish stage in Abuja.


How do you shuttle the different locations?

Question 2:

How do you calculate the duration of a building to be completed?

E.G, Engineer A has a 3 bedroom bungalow to be completed for 30 days. Engineer B also has the same 3 bedroom bungalow to be completed for 60 days.

Do you give durations according to your schedules or according to how the building will be constructed or according to how the capital is available?

Question 3:

As a professional architect that you are, do you give customize/specific adjustment/design on buildings?

E.G, Client A wants a basement/underground facility in his/her building but doesn't want it shown on the building plan? Or, client B ask for a 5 bedroom duplex and during construction, he/she wants it changed to a 3 bedroom duplex with a penthouse

I await your response Sir! wink smiley
Answer to question 1

Shuffling between locations is not an issue per say... I have project supervisor's who work with me. They're placed on site's to take up construction supervising projects, then i visit often to inspect the work progress.... Currently, i have an ongoing construction project in Uromi Edo state and also in ekpoma Edo state of which i took to roofing level before leaving my project supervisor's there to monitor and make sure things are handled accordingly...

Like i stated earlier, I visit often to inspect the jobs and when not around, they report to me dialy as per the work progress....

Answer To Question 2

Calculating the time duration for a project has been based on experience over time... I'm able to ascertain when a project is to be completed because of previous projects embarked upon... For instance, if am to engage in the construction of a 4-bedroom residential accommodation, there will be a memorandum of understanding between myself and the client afterwhich we establish a time frame for the project... If he's to supply materials, he should do so when needed and on-time so as to not cause delay in the construction process... Although most times we understand that there can be some sort of delays in delivering materials to site, but we always know how to meet up with the stipulated time...

Answer To Question 3

Yes, we make specific adjustments/changes to building designs as its the right of clients to decide what they need.. We understand that what Mr A likes will not be what Mr B likes therefore, it's only proper we make adjustments in the design to suit whoever we're working for at that point in time...

Thank You Sir and God bless..
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by ISTP: 11:02pm On Nov 07, 2022
AsomArchitectNG:
Thank You Sir and God bless..
Wow! Fantastic! Impressive!

I'm extremely satisfied with your explanations.

I'll get in touch soon.

Thanks for your effort to respond.

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op):
ISTP:
Wow! Fantastic! Impressive!

I'm extremely satisfied with your explanations.

I'll get in touch soon.

Thanks for your effort to respond.
Thank You Sir..

We'll be expecting....
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 9:35am On Nov 08, 2022
Good morning my people, we're on site this morning to begin with the day's work as fencing of the compound continues, pop installation and casting continue....

Up next is tiling and of the house...

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op):
Site view......

Water collector has been fixed and It's coming out really great.... cool cool

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 9:39am On Nov 08, 2022
From our satisfied client smiley smiley cool cool

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 6:58am On Nov 09, 2022
Good morning my people, we're on site already to begin with the day's work as

*Pop ceiling installation continues...

*Pop ceiling casting continues...

*Fencing of the compound continues...

Meanwhile,

Tiling of the house starts today....

I'll bring in pictures and video update much later

I sincerely appreciate you all for staying with us up till this very moment... God's blessings always..

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:12pm On Nov 09, 2022
More from the pop ceiling installation cool...


https://www.youtube.com/watch?v=NS_jUosTRsI
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:16pm On Nov 09, 2022
Pictures showing the pop ceiling installation work cool cool

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:17pm On Nov 09, 2022
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:21pm On Nov 09, 2022
Meanwhile, here's the work progress for the fencing....

We thankGod for progress so-far...

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by ISTP: 12:36pm On Nov 09, 2022
AsomArchitectNG:
Pictures showing the pop ceiling installation work cool cool
AsomArchitectNG:
Meanwhile, here's the work progress for the fencing....

We thankGod for progress so-far...
The neatness of your work fascinates me and it's also a big turn on.

#keepitup
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:48pm On Nov 09, 2022
ISTP:
The neatness of your work fascinates me and it's also a big turn on.

#keepitup
Much appreciated boss. cool
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:49pm On Nov 09, 2022
Video extract from the compound fencing...


https://www.youtube.com/watch?v=nAdNu77hRJw
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:59pm On Nov 09, 2022
Measurements for the fence protector have been taken. We will commence work on that immediately as it should be ready by tomorrow or next..
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 8:45am On Nov 10, 2022
Good morning my people, we're on site this morning to begin with the day's work as....

*Plastering of the fence commence today...

*Pop ceiling installation and casting continues...

*Tiling of the house continues...

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 8:56am On Nov 10, 2022
Meanwhile, we've started fixing the art work design on the fence where the fence light would be...


https://www.youtube.com/watch?v=powheNGwr0w

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 9:17am On Nov 10, 2022
Work progress for the tiling...


https://www.youtube.com/watch?v=Ec5kVSPQvbQ

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 4:44pm On Nov 12, 2022
The fence protector is ready...


https://www.youtube.com/watch?v=A3pyrJ06k8A
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op):
The gate too is ready.... We'll be moving them to site any moment from now....


Meanwhile, plastering for the fence is still ongoing,

Tilling ongoing also...

We'll be rounding up with the pop installation and casting for the house today....

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 4:51pm On Nov 12, 2022
We give God all the Glory for taking us this far.

And also y'all for been with us since inception of this project till this very moment...
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 4:55pm On Nov 12, 2022
Work continues on site as we're getting ready for compund filling....
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 5:01pm On Nov 12, 2022
Work progress for the fence plastering

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by Mandy003: 8:44am On Nov 13, 2022
AsomArchitectNG:
The gate too is ready.... We'll be moving them to site any moment from now....


Meanwhile, plastering for the fence is still ongoing,

Tilling ongoing also...

We'll be rounding up with the pop installation and casting for the house today....
PLZ whats the cost of this gate and that for the fence railings
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 2:48pm On Nov 13, 2022
Mandy003:
PLZ whats the cost of this gate and that for the fence railings
The cost of the gate is 440,000...

While that of the fence railings is 190,000...
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 11:49am On Nov 14, 2022
Good morning my people.... We've already started work on site this morning as tiling work continues...
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:07pm On Nov 14, 2022
We've kick started with filling of the compound as we have tippers bringing in load of laterite to site today.....

Also, we employed labourers to help convey the laterite with wheelbarrow's to every designated area on the site and also help in spreading it until we attain the desired filling level of the compound..


Video of work progress below:


https://www.youtube.com/watch?v=Hwz2mz5T_5w
Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op):
Meanwhile, this is how our construction project is looking today as we've started tilling the surrounding below wall belt level... cool cool

Re: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 12:18pm On Nov 14, 2022
We'll be having a different outlook of the compound before the end of the week.... cool
1 2 3 ... 10 11 12 13 14 15 16 ... 21 Reply

Another Successful Roofing Job Done For A 3bedroom Nairalander In Diaspora At OnConstruction Of A 5bedroom Bungalow With Pent@Ado-EkitiCost, Estimate For Building A 3bedroom Bungalow In Nigeria (Detailed Info)234

Window Blinds At Affordable PricesStorage Container Converted To A Home (photos).Twinstecks Electrical Accessories sale THREAD