Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 9:15pm On Sep 14, 2023
spyder880:
Arrival of more internal doors............
Are these doors better than the local Nigerian fabricated doors
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 11:17am On Sep 15, 2023
Gen2men:
Are these doors better than the local Nigerian fabricated doors
You mean the local wooden doors?
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 8:31pm On Sep 15, 2023
spyder880:
You mean the local wooden doors?
No, local iron doors. I've seen you use doors you fabricated in one of your sites.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op):
Gen2men:
No, local iron doors. I've seen you use doors you fabricated in one of your sites.
Local iron doors are very good, and you can choose to reinforce it with additional security features, or thicker iron plates to make it difficult for anyone to break into. Easier to amend than foreign doors.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 9:20pm On Sep 15, 2023
spyder880:
Local iron doors are very good, and you can choose to re8nforcebit with additional security features, or thicker iron plates to make it difficult for anyone to break into. Easier to amend than foreign doors.
Okay
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:34am On Sep 21, 2023
Front of this building just before we start to plaster............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by erico2k2(m): 1:12pm On Sep 21, 2023
I still dey class
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:14pm On Sep 21, 2023
erico2k2:
I still dey class
Welcome Sir, let me continue to dey show more updates from our works yesterday.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:16pm On Sep 21, 2023
Making more ceiling components...........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:21pm On Sep 21, 2023
Hanging more ceiling boards.........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:24pm On Sep 21, 2023
More.......

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:27pm On Sep 21, 2023
Electrical wiring works all of the flats...............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:30pm On Sep 21, 2023
More pictures from outside this building..............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by ggoldmine(f):
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:38pm On Sep 21, 2023
More pictures from outside.........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by erico2k2(m): 1:41pm On Sep 21, 2023
Well-done Bossman
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 4:12pm On Sep 21, 2023
More pictures from the back...........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 4:24pm On Sep 21, 2023
erico2k2:
Well-done Bossman
Thank you Sir.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 5:56pm On Sep 21, 2023
Looks like you have multiple teams on the ground working on this site. Nice job
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:04pm On Sep 21, 2023
Gen2men:
Looks like you have multiple teams on the ground working on this site. Nice job
Yes, I have my plastering team, ceiling team, screeding team, electrical team all working now, the door crew will arrive this weekend, to work with the windows guys, then all windows and doors will be dressed same time.

We are already moving for tiles and sanitary wares. Welcome.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 7:51pm On Sep 21, 2023
spyder880:
Yes, I have my plastering team, ceiling team, screeding team, electrical team all working now, the door crew will arrive this weekend, to work with the windows guys, then all windows and doors will be dressed same time.

We are already moving for tiles and sanitary wares. Welcome.
Spyder I thought electrical wiring comes after door and window installation?
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by erico2k2(m): 8:04pm On Sep 21, 2023
Gen2men:
Spyder I thought electrical wiring comes after door and window installation?
I think this is down to security.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:50pm On Sep 21, 2023
Gen2men:
Spyder I thought electrical wiring comes after door and window installation?
If I have men working in the site that I think will be there till the finish, then I can have the house wired before doors and windows. The advantage of doing wiring early is the benefit of seeing where there are blocked piping, and the work of braking walls or under decking to correct the piping work when it's still early, which is before wall screeding or ceiling works under the decking as the case may be.

What makes me leave wiring till later in some sites is to save the wires from being stolen if the work is not continuous. Thanks.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:51pm On Sep 21, 2023
erico2k2:
I think this is down to security.
You're correct Sir.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 8:59pm On Sep 21, 2023
spyder880:
If I have men working in the site that I think will be there till the finish, then I can have the house wired before doors and windows. The advantage of doing wiring early is the benefit of seeing where there are blocked piping, and the work of braking walls or under decking to correct the piping work when it's still early, which is before wall screeding or ceiling works under the decking as the case may be.

What makes me leave wiring till later in some sites is to save the wires from being stolen if the work is not continuous. Thanks.
My thoughts
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 9:04pm On Sep 21, 2023
What would the three stages of electrical cost you in this build . I heard the wiring part cost more.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 10:24pm On Sep 21, 2023
Gen2men:
What would the three stages of electrical cost you in this build . I heard the wiring part cost more.
For buildings like this, the 3 stages may cost up to 5m. The wires obviously cost more.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Gen2men: 10:38pm On Sep 21, 2023
spyder880:
For buildings like this, the 3 stages may cost up to 5m. The wires obviously cost more.
wow
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by erico2k2(m): 10:45pm On Sep 21, 2023
spyder880:
You're correct Sir.
I had to leave mine untill all security locks n protectors were in place even so, one wire still got stollen by workers cost 40K to replace, SO I adopted a system were only one group of persons work at a time
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:16pm On Sep 25, 2023
We are busy at this site, work plan for this week;

1. Plastering of exterior walls, to be completed this week
2. Dressing of doors and windows, to be completed this week
3. Ceiling POP, to be concluded this week
4. Wall screeding, to be started this week
5. Wall and floor tiles, to be bought this week
6. Tanks, piping of tanks, to be started this week.

More pictures of work progress later.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:26am On Sep 28, 2023
Our work still continues in this site this week.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:28am On Sep 28, 2023
More pictures of the plastering of the front of the house.............

1 2 3 ... 8 9 10 11 12 13 14 ... 20 Reply

The Making Of Asaba Stepped Up Two Storey Building. COMPLETED !!! • The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" • New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. • 2 • 3 • 4

Christmas Tragedy: Landslide Kills 3 In Abuja, Injures 3 Others • Man Loses Baby In Imo Building Collapse,Escaped With Only Wife & 2 Clothes.PICS • Free 5 Bedroom Bungalow Design and 3D For Nairalanders