The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms - Properties (17) - Nairaland

Nairaland ForumNairaland GeneralPropertiesThe Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms (26836 Views)

1 2 3 ... 14 15 16 17 18 19 20 Reply (Go Down)

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:52am On Feb 10, 2024
Fence coping, fence plastering, electrical piping...............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:54am On Feb 10, 2024
Generator base plastering, dressing.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:00am On Feb 10, 2024
From the outside.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:03am On Feb 10, 2024
More.....

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:16pm On Feb 23, 2024
We have completed works on the fence and gate of this building...............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:20pm On Feb 23, 2024
The inside of the compound..................

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 1:31pm On Feb 23, 2024
More pictures...........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 1:54pm On Mar 16, 2024
spyder880:
No, only the building alone. Foundation till parapet and roofing with 0.45 aluminium sheets.
Good afternoon and happy weekend engineer.
Please, I would like to know is its necessary to use a basket for column while constructing a soakaway where cars would be allowed to pack on top of the soakaway?
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 9:27am On Mar 17, 2024
Chidimercy:
Good afternoon and happy weekend engineer.
Please, I would like to know is its necessary to use a basket for column while constructing a soakaway where cars would be allowed to pack on top of the soakaway?
Yes, I usually put baskets, 2 feet width.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 10:50am On Mar 17, 2024
spyder880:
Yes, I usually put baskets, 2 feet width.
Thanks so much Engineer
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:17am On Mar 20, 2024
The sand filling of this compound had since started..........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:20am On Mar 20, 2024
More pictures of the compound.............

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:38am On Mar 20, 2024
More pictures from the compound........

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by vastolord4(m): 12:29pm On Mar 24, 2024
Good day Mr Spyder880. I've been following your tread from 7 bedroom high ceiling... the way the sand fill is sloppy to the fence, could the weight, flood (especially in anambra) affect the fence?
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op):
vastolord4:
Good day Mr Spyder880. I've been following your tread from 7 bedroom high ceiling... the way the sand fill is sloppy to the fence, could the weight, flood (especially in anambra) affect the fence?
Good afternoon bro, there is no flood in the area of the 7 bedroom high ceiling house in Anambra. The house and fence is inside a fenced compound and the fringes of the concrete floor could be covered with carpet grass which is erosion resistant.

As for this thread and the filling here, the land is naturally sloped to the back, we did a water drainage channel to wedge this sand fill from pushing against the back fence.

Thank you Sir.

Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 3:49pm On Mar 24, 2024
Please engineer, happy Sunday..
I am currently constructing a soakaway system which would be in front of the compound that cars would be parking on top. Please can complete 12mm rod be used for the column or must it be 16mm rod?
Because regarding the hike in prices of materials and I am trying to achieve the most efficient and less cost for the the soakaway. Please I need your contribution.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 3:57pm On Mar 24, 2024
spyder880:
Good afternoon bro, there is no flood in the area of the 7 bedroom high ceiling house in Anambra. The house and fence is inside a fenced compound and the fringes of the concrete floor could be covered with carpet grass which is erosion resistant.

As for this thread and the filling here, the land is naturally sloped to the back, we did a water drainage channel to wedge this sand fill from pushing against the back fence.

Thank you Sir.
Please engineer, happy Sunday..
I am currently constructing a soakaway system which would be in front of the compound that cars would be parking on top. Please can complete 12mm rod be used for the column or must it be 16mm rod?
Because regarding the hike in prices of materials and I am trying to achieve the most efficient and less cost for the the soakaway. Please I need your contribution
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 4:01pm On Mar 24, 2024
Chidimercy:
Please engineer, happy Sunday..
I am currently constructing a soakaway system which would be in front of the compound that cars would be parking on top. Please can complete 12mm rod be used for the column or must it be 16mm rod?
Because regarding the hike in prices of materials and I am trying to achieve the most efficient and less cost for the the soakaway. Please I need your contribution
Use 16mm since cars will be passing on it. Please use a column base with a mat of at least 2 feet wide under each column. Doing the right thing will make your projects last without too much maintenance for the longest period.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by Chidimercy: 4:31pm On Mar 24, 2024
spyder880:
Use 16mm since cars will be passing on it. Please use a column base with a mat of at least 2 feet wide under each column. Doing the right thing will make your projects last without too much maintenance for the longest period.
Thank you engineer. I will do exactly as you advised.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by horlabiyi(m): 1:27pm On Mar 26, 2024
Hi my Oga,

Please after casting DPC of a bungalow building, how many days should one wet the casting before laying of blocks? Thank You
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by double3(m): 8:54pm On Mar 26, 2024
Chidimercy:
Please engineer, happy Sunday..
I am currently constructing a soakaway system which would be in front of the compound that cars would be parking on top. Please can complete 12mm rod be used for the column or must it be 16mm rod?
Because regarding the hike in prices of materials and I am trying to achieve the most efficient and less cost for the the soakaway. Please I need your contribution
Please I'm interested in the cost of this project. Cos I got an outrageous quotation fo construction of soakaway from my engineer .
@spyder880 please how much would it cost in this present day economy to construct a basic "soakaway" for 2 units of 3bedroom flat.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by collele(m): 11:21pm On Mar 26, 2024
spyder880:
Use 16mm since cars will be passing on it. Please use a column base with a mat of at least 2 feet wide under each column. Doing the right thing will make your projects last without too much maintenance for the longest period.
Wonders shall never end... grin grin grin....This building is right after me in Asaba...My house is the building just before this house...the one with the flat roof...what a small world
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:12am On Mar 27, 2024
collele:
Wonders shall never end... grin grin grin....This building is right after me in Asaba...My house is the building just before this house...the one with the flat roof...what a small world
It's a small world bro, I pass the house regularly and even stand around the side to get better pictures of this house. It's a cool area, the neighbohood is gradually filling up.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:14am On Mar 27, 2024
horlabiyi:
Hi my Oga,

Please after casting DPC of a bungalow building, how many days should one wet the casting before laying of blocks? Thank You
You should wait for at least 4 days for the concrete to cure properly, however, if there were plans and the concrete was mixed to be used in a shorter period, 2 days will be enough. It's all about the mix. Thanks.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 7:16am On Mar 27, 2024
double3:
Please I'm interested in the cost of this project. Cos I got an outrageous quotation fo construction of soakaway from my engineer .
@spyder880 please how much would it cost in this present day economy to construct a basic "soakaway" for 2 units of 3bedroom flat.
To build a normal soakaway system of about 12ft length, 7 feet width and 10 feet depth will cost about N850,000 in today's costs, materials, workmanship, etc.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by collele(m): 8:07am On Mar 27, 2024
spyder880:
It's a small world bro, I pass the house regularly and even stand around the side to get better pictures of this house. It's a cool area, the neighbohood is gradually filling up.
True...Lemme know when next you're around make I knack you one bottle of beer
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 8:11am On Mar 27, 2024
collele:
True...Lemme know when next you're around make I knack you one bottle of beer
Thank you bro. cheesy
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by double3(m): 2:36pm On Mar 27, 2024
spyder880:
To build a normal soakaway system of about 12ft length, 7 feet width and 10 feet depth will cost about N850,000 in today's costs, materials, workmanship, etc.
Thanks...ur estimate sounds very reasonable. Got a bill of 1.9million
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by double3(m): 2:37pm On Mar 27, 2024
.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 4:31pm On Mar 27, 2024
double3:
Thanks...ur estimate sounds very reasonable. Got a bill of 1.9million
Things are going haywire now, people are getting scared to take on more jobs.
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by horlabiyi(m): 9:59pm On Mar 27, 2024
spyder880:
You should wait for at least 4 days for the concrete to cure properly, however, if there were plans and the concrete was mixed to be used in a shorter period, 2 days will be enough. It's all about the mix. Thanks.
Thank You My Oga
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by horlabiyi(m): 3:04pm On Mar 28, 2024
With the standard of today building materials in Nigeria especially iron rod. Is it advisable to use 12mm for columns of a bungalow building and is chain beams necessary if we are going to have precast parapet on the building? Thank You Sir
1 2 3 ... 14 15 16 17 18 19 20 Reply

The Making Of Asaba Stepped Up Two Storey Building. COMPLETED !!!The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms"New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East.234

Surulere Super Shopping Plaza On FireRoofing A 3 Bedroom Block Of 4 Flat In LagosAwka,enugu, Ibadan, Lekki Projects (electrical, Cctv, Audio System) Installation