Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded - Properties (3) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded (20459 Views)

Real Cost & Pix For Building 4bed Rm Duplex And 2bed Rm Flat X 2 At Edo State. / The Real Cost Of Building A 6 Bedroom Duplex (reloaded) / 2 B/R FOR SALE AT GOWON ESTATE EGBEDA (NOW WITH PICS) (2) (3) (4)

(1) (2) (3) (4) (5) (6) (Reply) (Go Down)

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by FastShipping: 9:05pm On Sep 11, 2014
Aventures: lump sum for our roof carcass and noggins =N= 853,000 and we ll soon get to roof covering, i will equally update as well, mean while from the pics you posted i found out that your building looks wide
er than ours and so to achieve a high pitch as ours yours may cos a little higher than this, because the basic determinant of roof cost is the pitch and the kind of roof covering you intend to use

..
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Nobody: 4:39am On Sep 12, 2014
following keenly. pls whats the total number of blocks used plus size of blocks
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 8:56am On Sep 12, 2014
GODAKPAN: following keenly. pls whats the total number of blocks used plus size of blocks
block work is still on going we re using both 9 & 6 inches block , as at now we've used close to 4800 blocks of both
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by osarodon(m): 6:35pm On Sep 15, 2014
Good one
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 10:47pm On Sep 16, 2014
osarodon: Good one
Thanks
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 8:08pm On Sep 17, 2014
Work update:
Roof carcass taken to completion, but we decided with permission of the client to improve on the aesthetic.
Roof Tank slab and the block wall around it
Spiral staircase form work
Deforming of the decking woods.
Check below for the pics

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 8:10pm On Sep 17, 2014
more pics

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 8:32am On Sep 18, 2014
Roof Covering work to commence today
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by twinskenny(m): 11:15am On Sep 18, 2014
Aventures: Roof Covering work to commence today
good morning sir,

great job you are doing here...
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Besh1295: 11:35am On Sep 18, 2014
Keep up the good work,please visit this thread https://www.nairaland.com/1906449/supply-timbers-planks-woods-constructions as we would like to supply timbers for your next project
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by jejeman: 11:43am On Sep 18, 2014
Please can I get the cost estimate of 3 bedroom duplex and 2unit of 2bed from foundation to german floor. Is a dry land at gaun Magboro
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 9:41pm On Sep 18, 2014
jejeman: Please can I get the cost estimate of 3 bedroom duplex and 2unit of 2bed from foundation to german floor. Is a dry land at gaun Magboro
yes you can, if we have your drawings.
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 9:39am On Sep 19, 2014
project work update

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 9:20pm On Sep 19, 2014
Today's update

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by FastShipping: 9:33pm On Sep 19, 2014
^^^

Please, give us the breakdown of the cost of wood, roofing sheets and workmanship for this roofing.
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 3:33pm On Sep 21, 2014
FastShipping: ^^^
Please, give us the breakdown of the cost of wood, roofing sheets and workmanship for this roofing.
The detail will come up as soon as i round up this stage
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 12:39pm On Oct 01, 2014
Happy Independence Day to all of us.

Wishing all of us as well Barka de Sallah in advance.

From all of us @ Abidoy Ventures Ltd and Behemoth Engrg Ltd.
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 3:20pm On Oct 10, 2014
pics

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 3:26pm On Oct 10, 2014
more pics

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by FastShipping: 3:27pm On Oct 10, 2014
Yet no details of the roofing as you promised few weeks ago......

I once sent you an email after someone recommended you here but you acknowledged it but didn't reply as promised. Luckily I found someone else on this forum.
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 4:55pm On Oct 10, 2014
FastShipping:
Yet no details of the roofing as you promised few weeks ago......
I once sent you an email after someone recommended you here but you acknowledged it but didn't reply as promised. Luckily I found someone else on this forum.
shai! poor me I am very sorry for that I never wish to loose such opportunity probably I was engrossed in some activities that made me to forget. pls pardon me. I will post the cost update today it is a promised at least to roof level.
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by segcymoor(m): 8:58pm On Oct 10, 2014
Bros It seems we wan do Xmas here. ....
see neat plastering
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 10:36pm On Oct 10, 2014
segcymoor:
Bros It seems we wan do Xmas here. ....
see neat plastering
bros na so we want to"warm" this house by November ending LOL. May God help us.
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 9:13am On Oct 11, 2014
Dear all,
i promised to give out the summary of stages expenditure on this project, kindly find this below:

A. Foundation (strip and Pad fdn with some special attention) = N= 2,907,100: 00 K

B. Ground floor pillars, suspended floor slab and beams = N= 4,0006,500 : 00 K

C. First floor pillars, first floor and grd floor block work, roof
beam, roof tank slab and wall (2Nrs) Grd and first floor
lintel work = N= 3,276,400 : 00K

Total sum for the structure Carcass (excluding roofing) = N= 10,190,000: 00K

Initial Budget at the inception of the project = N= 11, 147,500:00K

Several other works as taken place and still ongoing, such as roofing and its covering, window fabrication, burglary fabrication, Procurement of paragon PVC ceiling from Amoula ventures, POP casting ongoing, plastering ongoing, wardrobe frame and steel doors fabrication ongoing.

For the benefit of those that has been asking for the cost of roofing in particular pls find it below:

Roof wood carcass and Noggins (Melina wood) procurement and labour = N= 853,500:00 K

Roof covering 0.55 gauge Aluminium long span step tiles
(Qualitec Product) = N= 1,072.936.56 K

Total =N= 1,926,436.56 K

Total Sum for Carcass of this structure (roof inclusive) = N= 12,116,436.56 K
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by X2X(m): 9:28am On Oct 11, 2014
Aventures:
Dear all,
i promised to give out the summary of stages expenditure on this project, kindly find this below:
A. Foundation (strip and Pad fdn with some special attention) = N= 2,907,100: 00 K
B. Ground floor pillars, suspended floor slab and beams = N= 4,0006,500 : 00 K
C. First floor pillars, first floor and grd floor block work, roof
beam, roof tank slab and wall (2Nrs) Grd and first floor
lintel work = N= 3,276,400 : 00K
Total sum for the structure Carcass (excluding roofing) = N= 10,190,000: 00K
Initial Budget at the inception of the project = N= 11, 147,500:00K
Several other works as taken place and still ongoing, such as roofing and its covering, window fabrication, burglary fabrication, Procurement of paragon PVC ceiling from Amoula ventures, POP casting ongoing, plastering ongoing, wardrobe frame and steel doors fabrication ongoing.
For the benefit of those that has been asking for the cost of roofing in particular pls find it below:
Roof wood carcass and Noggins (Melina wood) procurement and labour = N= 853,500:00 K
Roof covering 0.55 gauge Aluminium long span step tiles
(Qualitec Product) = N= 1,072.936.56 K
Total =N= 1,926,436.56 K
Total Sum for Carcass of this structure (roof inclusive) = N= 12,116,436.56 K

Excellent. Well done
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by FastShipping: 11:02am On Oct 11, 2014
Aventures:
Dear all,
i promised to give out the summary of stages expenditure on this project, kindly find this below:

A. Foundation (strip and Pad fdn with some special attention) = N= 2,907,100: 00 K

B. Ground floor pillars, suspended floor slab and beams = N= 4,0006,500 : 00 K

C. First floor pillars, first floor and grd floor block work, roof
beam, roof tank slab and wall (2Nrs) Grd and first floor
lintel work = N= 3,276,400 : 00K

Total sum for the structure Carcass (excluding roofing) = N= 10,190,000: 00K

Initial Budget at the inception of the project = N= 11, 147,500:00K

Several other works as taken place and still ongoing, such as roofing and its covering, window fabrication, burglary fabrication, Procurement of paragon PVC ceiling from Amoula ventures, POP casting ongoing, plastering ongoing, wardrobe frame and steel doors fabrication ongoing.

For the benefit of those that has been asking for the cost of roofing in particular pls find it below:

Roof wood carcass and Noggins (Melina wood) procurement and labour = N= 853,500:00 K

Roof covering 0.55 gauge Aluminium long span step tiles
(Qualitec Product) = N= 1,072.936.56 K

Total =N= 1,926,436.56 K

Total Sum for Carcass of this structure (roof inclusive) = N= 12,116,436.56 K


Great job by you.

What is the size of the roof in sq.mt?
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by twinskenny(m): 11:36am On Oct 11, 2014
great job... weldone chief
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 12:48pm On Oct 11, 2014
FastShipping:

Great job by you.
What is the size of the roof in sq.mt?
aluminium is measured in meters I will check my record and revert.

Thank u all for appreciation
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 5:39pm On Oct 11, 2014
window burglary delivered

Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Nobody: 6:53pm On Oct 11, 2014
Aventures:
window burglary delivered

Oga weldone if I may ask what is the size of the rooms, sitting, toilet and kitchen. How much do you think it will cost to deck a building of 9.901 x17.700

Thanks
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 9:10pm On Oct 11, 2014
allen0000:

Oga weldone if I may ask what is the size of the rooms, sitting, toilet and kitchen. How much do you think it will cost to deck a building of 9.901 x17.700
Thanks
Our room sizes are 10ft x 12ft, 12ft x 12ft, sitting room is on average of 15ft x 18 ft.

Concerning the decking you ask budget between 2.5m to 2.8m
Re: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(m): 9:18pm On Oct 11, 2014
FastShipping:

Great job by you.
What is the size of the roof in sq.mt?
Step tiles long span Aluminium roofing sheet 590

Flat Sheet aluminium for Ridge Caps, Gutter
Eave angle 75

(1) (2) (3) (4) (5) (6) (Reply)

Gerrard Building Collapse: Picture Of Ikoyi Building Days Before It Collapsed / Estimate For Decking / How To Buy A Land In Lagos On A Budget And Not Bankrupt Yourself

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 38
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.