Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 6:19pm On Oct 21, 2023 |
Final course of blockwork
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 7:52am On Oct 20, 2023 |
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 7:51am On Oct 20, 2023 |
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 7:50am On Oct 20, 2023 |
Lintel and column works ongoing
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by raymondFirstborn(m): 9:26am On Oct 17, 2023 |
Adedward: Without burglaries for imported materials,
(1) 1.5 by 1.5 =# 60,000 (2) 3mtrs by 1.5= #100,000
For tower materials without burglaries
(1) 1.5 by 1.5 = # 80,000 (2) 3mts by 1.5= #135,000
Thanks, Add cost of burglaries please. I have got a job for you. |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by raymondFirstborn(m): 6:31am On Oct 17, 2023 |
Adedward: GOOD EVENING HOUSE Hi, what's the cost for 1500 x 1500 window. (Casement) 3000 x 1500 (casement windows) 5mm glass. Both imported and local materials |
Properties › Re: Cost Of Building A 4 Bedroom Duplex In Ibadan by raymondFirstborn(m): 6:55pm On Oct 14, 2023 |
oliverwrites: Hi All, I am considering start a project in Ibadan. A 4 bedroom duplex. I want to be well informed of what my likely cost will be before going into it.
For those who have experience, how much ( ballpark ) am I likely to spend for a 4 bedroom duplex from foundation to having doors, windows and plastering. I understand finishing is as expensive as my taste is so let's leave finish out of it.
How much will I spend to have a 4 bedroom to the point of roofing, plastering, windows and doors. Foundation to plastering budget is N35m. Foundation to decking - N19m If you need a simplified breakdown , message me on 09056082348(call & Whatsapp) |
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 9:48am On Oct 12, 2023 |
 we commence work on Friday
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 9:47am On Oct 12, 2023 |
Block work for second unit , starting in few days
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 8:03pm On Oct 10, 2023 |
Reinforcement for columns and lintels
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:43pm On Oct 10, 2023 |
Spot our staircase
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:41pm On Oct 10, 2023 |
 Focusing more on the detailing. We are selling a unit for N300m next year. Approach view has to speak
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:39pm On Oct 10, 2023 |
.
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:38pm On Oct 10, 2023 |
Front view
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:37pm On Oct 10, 2023 |
. 9 coaches done already
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:37pm On Oct 10, 2023 |
Meanwhile block work for first unit has started
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:36pm On Oct 10, 2023 |
Done. Total cement bags used here 200bags
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:35pm On Oct 10, 2023 |
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:35pm On Oct 10, 2023 |
Work progress decking for both unit's done
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 5:37pm On Sep 30, 2023 |
Cantilever beams for second unit
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 5:36pm On Sep 30, 2023 |
Update. We have CAST our first floor slab. Second unit wood work ongoing
|
Properties › Re: Building Of House: Engineers In The House,your Advise Is Needed. by raymondFirstborn(m): 4:06pm On Sep 25, 2023 |
QuestionMan016: Good days nairalanders,this is a new account to hide my identity here,I'm an old popular member.
My elder brother already have 50/100 plot available in Benin city .In the community where he have the land they are several borrow pits to easily buy sand through tipper drivers,infact the oba own the pit that is about five minutes away from the plot.
The land is even at the back of a TV station and many other things are there.The plan is to build 4 room bedsitter, because here many people are building room and parlour self and many single tenants are looking for bedsitter to rent.Bedsitters even produces more rent than room and parlour self contained .
That four room each will have their own toilet combine with Bathroom and sink,we plan to use pvc ceiling and the basic aluminium not that expensive stone coated one oh.
Since my brother is not in Nigeria,he ask me to find out like how much it will cost us to build such. Depends on the design. Where is the land located , is around TV road |
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 12:42pm On Sep 20, 2023 |
This staircase is one of the selling points in this project. Not your regular straight flight
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 12:38pm On Sep 20, 2023 |
First in Nigeria
|
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by raymondFirstborn(m): 11:35am On Sep 20, 2023 |
ladyteeks: Raymondfirstborn
He immediately refunded the money but that's not the issue. I paid him on Sep 9, he said the entire duration was 2 weeks but would send the sketch in few days. I asked him some questions on Sep 10 and didn't contact him until Sep 15. He promised to send it on September 17. I didn't hear from him and sent him a message. He sent me a rough plan different from what I specifically requested. I knew it was a rush job. He sent me a 3d design that I have already seen online without including the specific balcony design I wanted. I hate to harass anyone but then sending me a message about "me harrasing you and how busy you are blah blah is not professional". As a professional, you must be able to balance work and task. Most importantly, communication is very important.
Floor plan should take 3 to 5 days. I am the one who constantly send a message to this man. I understand that "he is busy." I don't like harrasing people but I
quote author=folmus post=125907507]
Please, mention name. You will be supporting and abetting bad behaviour if you are making it cryptic. Shebi you don pay? Ok una don finally drag me. I visited the site on Saturday 9th. With my architectural team. We took measurements. Started work on 11th. Sent her the 3d and sketch on the 18th. She wanted amendment which I told her on the 19th would be ready today 20th. She sent a message today, saying delivery was slow and I refunded in full . Please note delivery was supposed to be 2weeks from site visit. Meaning working drawings supposed to be delivered this Saturday. |
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 11:24am On Sep 20, 2023 |
Working on our floating staircase.
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 8:24am On Sep 18, 2023 |
.
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 5:00am On Sep 14, 2023 |
Good morning |
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 5:52pm On Sep 13, 2023 |
1& half tonnes of 16mm used so far
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:49pm On Sep 13, 2023 |
..
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:48pm On Sep 13, 2023 |
|
Properties › Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(op): 3:48pm On Sep 13, 2023*. Modified: 5:51pm On Sep 13, 2023 |
Reinforcement works for our beam ongoing.
|