Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,151,674 members, 7,813,244 topics. Date: Tuesday, 30 April 2024 at 09:30 AM

Construction Of A 4bedroom Duplex With A Bq@ Abeokuta - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Of A 4bedroom Duplex With A Bq@ Abeokuta (20353 Views)

Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures / CONSTRUCTION & DESIGN OF 4bedroom Duplex With 2bedroom 2flat Attach IN LAGOS / Construction Of 4bedroom Duplex With 2bedroom 2flat Attach At AIT Road Alagbado (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (12) (Reply) (Go Down)

Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 1:27am On Oct 03, 2018
All thanks to God for the privilege this time.
I will be uploading Construction images starting from the 3D Visualization to the completion both interior and exterior finishing.

We are putting in a Dioritestructures limited IN AN IN-STYLES DIMENSIO[b]NS @ABEOKUTA.
[/b]
You are all welcome as we all learn together this time again.



FOR YOUR INFORMATION WE RENDERING THE FOLLOWING SERVICES:

ARCHITECTURAL DRAWINGS
STRUCTURAL DRAWINGS
MECHANICAL DRAWINGS
PLUMBING DRAWING
ELECTRICAL DRAWINGS
BUILDING RENOVATION
3D VISUALIZATION
AND MANY MORE WITH 99.99% QUALITY @AN AFFORDABLE BEST PRICE.

CONTACT INFO:

081-0045-2977(WhatsApp)
https:///send?phone=2348100452977
081-2716-7275(Other)
Mail: dioritestructureslimited@gmail.com
Blog: www.dioritestructures..com
Web:
http://www.dioritestructures.com.ng/

4 Likes

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 1:32am On Oct 03, 2018
*4BEDROOM DUPLEX WITH A BQ*

_EXTERNAL DIMENSION_: 21.325m By 12m
CLIENT: NON-NAIRALANDER



PLOT LOCATION: ABEOKUTA IN OGUN STATE.
PROJECT DURATION: 12WEEKS.

_FEATURES_

*Ground Floor*

Entrance
Anteroom
Lobby
Visitor WC
Main Family Lounge
Elevated dining
Kitchen with Island
Store/Laundry
Verandah
Equipped* Room
Lobby
Guest Bedroom ensuit
Dogleg Stairway


*_BQ FEATURES_*

Entrance
Living Room
WC
Lobby
Kitchen
Bedroom ensuit.


*First Floor*

Lobby
Upper Family lounge
Library/Office
Sit-Out
Gallery
Lobby
Master Bedroom(T/Bath with W.I.C)
Lobby
Madam Bedroom(T/Bath with W.I.C)
Lobby
Bedroom 4 ensuit
Dogleg Stairway

*PENT FLOOR*

Lobby
Pent Lounge
Kitchenette
Sit-Out

2 Likes 1 Share

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 1:38am On Oct 03, 2018
Here is the site to transfer the load on.
Yesterday @Abeokuta

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 1:42am On Oct 03, 2018
...

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 1:44am On Oct 03, 2018
..

2 Likes

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 1:49am On Oct 03, 2018
More update towards to weekend on borehole and site storage.
The family want a fast work,so moving everything as fast as possible and achieving what I designed.
Our target is Christmas.
For 12weeks from now you know 3months isn't complete so and we can't rush the construction at all critical point only in some places but with money availability,we plan to speed up the FINISHING.

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by aladesuyi(m): 2:01am On Oct 03, 2018
Best of luck bro

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:46am On Oct 03, 2018
aladesuyi:
Best of luck bro
Thanks bro

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 2:06am On Oct 05, 2018
As we get the drawings set and sealing the drawings.
Storage house and bore hole next.
Construction kicks on 12th Friday
more update shortly
There is a change in plan now ordered from the client and we need to comply so 15ths.
Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 5:27pm On Oct 08, 2018
More update coming soon.
Wanna upload pix with less talk instead.
Agreement with the client family is to start work on 15th of October,site storage this week and raising of the fence.
Bore hole planned Wednesday for it's own execution.
And all materials being set towards 15th.

Thanks for following
Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 5:28pm On Oct 08, 2018
Architectural Drawings
Sealed and Signed.

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 5:29pm On Oct 08, 2018
More check out today @Abk.

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 8:07pm On Oct 08, 2018
Point for our bore hole.

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 5:25pm On Oct 10, 2018
CONTACT INFO

WHATSAPP: 081-00-45-29-77
OTHERS: 081-27-16-72-75 MAIL: dioritestructureslimited@gmail.com
WEBSITE: www.dioritestructures..com COMMITTED TO GIVEN THE QAULITY & BEST

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Nobody: 6:07pm On Oct 10, 2018
Timtol:
Architectural Drawings
Sealed and Signed.

Please consider removing your clients private details.

Also, consider getting an intern that will help manage your social media communications.

Good luck on the build.

3 Likes

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 11:42pm On Oct 10, 2018
EgunMogaji:


Please consider removing your clients private details.

Also, consider getting an intern that will help manage your social media communications.

Good luck on the build.
Thanks sir

2 Likes

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:11pm On Oct 11, 2018
We have the following drawings ready;

ARCHITECTURAL DRAWINGS
STRUCTURAL DRAWINGS
MECHANICAL DRAWINGS
ELECTRICAL DRAWINGS

BILL ALMOST READY... MATERIALS FOR SITE STORAGE SET.

We kick off site storage tomorrow by God's grace.
Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:14pm On Oct 11, 2018
We kick off bore hole today

3 Likes

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:16pm On Oct 11, 2018
....

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:18pm On Oct 11, 2018
Part of the ready materials is the water tank.
3000litres

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:24pm On Oct 11, 2018

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Hajivince(m): 9:22pm On Oct 11, 2018
You should acknowledge the contractor too Oga Timtol!... Crystal Links International should be @ the top page as Contractor on the project

2 Likes

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 10:48pm On Oct 11, 2018
Hajivince:
You should acknowledge the contractor too Oga Timtol!... Crystal Links International should be @ the top page as Contractor on the project
Yeah!
THANKS

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:06pm On Oct 12, 2018
Here is the water... making progress

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 3:19pm On Oct 13, 2018
Site storage set

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 7:45pm On Oct 14, 2018
A relaxing weekend for tomorrow journeys and project kick off.
Thanks for following

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 10:54pm On Oct 15, 2018
On arrival to the site lately.
A little of what we were able to achieve.
More update below.

These are the soil stages. The 3-4th type from the left is Abt 30m from the natural ground level,going deeper we got a lot more soil type,we hit a rock,we had to break the rock before having the the water.

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 10:55pm On Oct 15, 2018
Timtol:
On arrival to the site lately.
A little of what we were able to achieve.
More update below.

These are the soil stages. The 3-4th type from the left is Abt 30m from the natural ground level,going deeper we got a lot more soil type,we hit a rock,we had to break the rock before having the the water.
Different stages...after breaking of the rocks works continue.

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 10:57pm On Oct 15, 2018
Here is our clean water.

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 10:59pm On Oct 15, 2018
More update
Profiling and setting out

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Timtol(m): 11:04pm On Oct 15, 2018
More update tomorrow

1 Like

Re: Construction Of A 4bedroom Duplex With A Bq@ Abeokuta by Hajivince(m): 11:05am On Oct 16, 2018
Timtol:
More update tomorrow
My good partner, keep it coming

4 Likes

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (12) (Reply)

Yaba Building Collapse: One Person Recovered Dead From The Rubble / Ikorodu Houses Marked For Demolition By LASG; The Residents React / Tips From A Property Lawyer About Renting & Sale Of Property Especially In Lagos

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 22
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.