Help With Costing Of 4 Bedroom Bungalow by grafixdon: 1:35pm On Mar 04, 2020
Hello Nairalanders,

Please I need your assistance with costing of 4 bedroom bungalow somewhere at Agbara.

See attached pictures.

So far I've spent 600k plus for 3 coaches level which I think is very expensive compare to what I'd read on this site. Now the engineer is asking for another 810k for German floor.

Kindly help me do the costing so I won't be ripoff.

Thank you.

Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 1:39pm On Mar 04, 2020
Spent 600k plus to this level

Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 1:43pm On Mar 04, 2020
Na Wa o. No one is willing to help
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 4:52pm On Mar 04, 2020
Help a brother o
Re: Help With Costing Of 4 Bedroom Bungalow by charlesELIKIBA: 5:33pm On Mar 04, 2020
grafixdon:
Help a brother o

thats a huge bungalow bro
...so far its realistic the prices.
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 7:30pm On Mar 04, 2020
charlesELIKIBA:

thats a huge bungalow bro ...so far its realistic the prices.
OH you mean the quotation is justifiable?
Re: Help With Costing Of 4 Bedroom Bungalow by Godisgreatest1: 10:41pm On Mar 04, 2020
The number of cement in bags is tooooooo much. 100 bags?! Wonderful!.
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 3:25pm On Mar 05, 2020
Godisgreatest1:
The number of cement in bags is tooooooo much. 100 bags?! Wonderful!.

Thank you, this's what I'm saying. The quotation is too high . I need an expert to help costing this
Re: Help With Costing Of 4 Bedroom Bungalow by lightofjoy(m): 4:05pm On Mar 05, 2020
The quote is high. Talk to me if you need a BOQ that will assist you in your cost planning. Thanks
Re: Help With Costing Of 4 Bedroom Bungalow by Godisgreatest1: 8:22pm On Mar 05, 2020
grafixdon:


Thank you, this what I'm saying. The quotation is too high . I need an expert to help costing this
Don't talk to anyone for any BOQ, I managed mine by 'playing to the script'. Don't buy those materials in bulk the way it is listed, do it gradually, you won't buy up to that quantity. What you should negotiate is the 'workmanship'.

4 Likes

Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 9:45pm On Mar 05, 2020
Godisgreatest1:

Don't talk to anyone for any BOQ, I managed mine by 'playing to the script'. Don't buy those materials in bulk the way it is listed, do it gradually, you won't buy up to that quantity. What you should negotiate is the 'workmanship'.

Thank you bro
Re: Help With Costing Of 4 Bedroom Bungalow by charlesELIKIBA: 3:39pm On Mar 06, 2020
grafixdon:


OH you mean the quotation is justifiable?
yes
Re: Help With Costing Of 4 Bedroom Bungalow by Smartwave: 5:22pm On Mar 06, 2020
Too high.
Re: Help With Costing Of 4 Bedroom Bungalow by dandy2222: 9:04pm On Mar 06, 2020
300-400k could do dt thing am seeing there. D quotation is high. 30-40 bags of cement, 2 trips of sand , 1 trip of gravel, 8lengths of 12mm rod, 1,500 blocks at most and 30-50k labour cost can comfortably achieve dt. So u can check d cost of dis materials urself .

2 Likes

Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 12:36pm On Mar 07, 2020
dandy2222:
300-400k could do dt thing am seeing there. D quotation is high. 30-40 bags of cement, 2 trips of sand , 1 trip of gravel, 8lengths of 12mm rod, 1,500 blocks at most and 30-50k labour cost can comfortably achieve dt. So u can check d cost of dis materials urself .


I really appreciate this. Maybe I need to change engineer
Re: Help With Costing Of 4 Bedroom Bungalow by Valentine87: 7:21am On Mar 18, 2020
Bro search for this thread on properties section and post your request on it ........ General Topic Thread-To Discuss Anything And Everything in Building Construction
Re: Help With Costing Of 4 Bedroom Bungalow by Perfecttouchade: 7:23am On Mar 18, 2020
grafixdon:
Na Wa o. No one is willing to help
cc: saydfact
Re: Help With Costing Of 4 Bedroom Bungalow by Perfecttouchade: 7:25am On Mar 18, 2020
Valentine87:


Bro search for this thread on properties section and post your request on it ........ General Topic Thread-To Discuss Anything And Everything in Building Construction
the link to the thread: https://www.nairaland.com/2550211/general-topic-thread-to-discuss-anything/1345
Re: Help With Costing Of 4 Bedroom Bungalow by Valentine87: 7:41am On Mar 18, 2020
this what some else spent in finishing all his bock work of a bungalow that is even bigger


This what I have spent to this stage.

Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000

Blinding
Cement - 30 bags @ 2500 = 75,000
Sharp Sand - 20 tonnes = 32,000
Granite - 25 tonnes = 105,000
Total = 212,000

Foundation Block Setting & Sock away Pit
Blocks = 1400 @ 150 = 210,000
Cement - 30 bags @ 2400 = 72,000
Sharp Sand =15 tonnes = 24,000
Labour for Soak away = 62,000
Extra Labour Expenses = 20,000
Total = 388,000

Foundation Filling
Labour = 92,000
Laterite = 326,000
Total = 418000

DPC - Half
DPM Nylon = 11,500
Granite= 10 tonnes = 45,000
Tara = 10 tonnes =13,000
Sharp sand = 10 tonnes = 15,500
Planks - 25 pieces & nails = 25000
Iron
16mm - 4 lengths @4400 = 17600
8mm - 3 lengths @ 1250 = 3750
Binding wire =2500
Transport = 2500
Workmanship
Labourer = 40000
Welder and carpenter = 13000
Cement = 28 bags @ 2500= 70000
Wire Mesh = 10500
Total = 273,000

Above Foundation Block setting + 2 soak away pits
Blocks 4100 @ 150 = 615000
Water = 3000
Sharp sand = 36000
Joining sand = 18000
Cement @2500 =162500
labour = 56000
Total = 891000

Lintel and Pillars Casting
16mm - 8 lengths @ 3630 = 29040
8mm - 31 lengths @ 1030 = 31930
12mm - 34 lengths @ 2050 = 69700
1 binding wire = 4000
Transport & logistics = 4000
Wood and planks ➕ TP = 51000
Granite = Used remains
Sharp sand = 15000
Cement = 30 bags @ 2500 = 75000
Workmanship
Labour 40000
Carpenter 22000
Iron bender 17000
Total =360000

Parapet and soak away Casting
Iron plus
12mm - 30 lengths @ 1970 = 59100
8mm - 51 lengths @ 1420 = 72420
Big Binding wire @ 7000
Extra iron = 9000
Quarter rod - 15 lengths @ 200 = 3000
Transport = 3500
Workmanship = 25000
Wood and cutting = 175000
Nail = 11100
Transport = 4000
Workmanship = 40000
Granite = 20 tonnes = 100000
Sharp sand = 15 tonnes = 21000
Cement 50 bags @ = 130000
Labour = 50000
Total = 710,000

Electrical
20mm pipe = 2 bundles @2100
25mm pipe = 1 bundle @ 3200
Electrical materials = 14000
Workmanship =9000

Plumbing
Internal plumbing
Cost of pipes and accessories = 47,000
Labour = 18,000

Perfecttouchade:
the link to the thread: https://www.nairaland.com/2550211/general-topic-thread-to-discuss-anything/1345

1 Like

Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 6:56pm On Mar 18, 2020
Valentine87:
this what some else spent in finishing all his bock work of a bungalow that is even bigger


This what I have spent to this stage.

Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000

Blinding
Cement - 30 bags @ 2500 = 75,000
Sharp Sand - 20 tonnes = 32,000
Granite - 25 tonnes = 105,000
Total = 212,000

Foundation Block Setting & Sock away Pit
Blocks = 1400 @ 150 = 210,000
Cement - 30 bags @ 2400 = 72,000
Sharp Sand =15 tonnes = 24,000
Labour for Soak away = 62,000
Extra Labour Expenses = 20,000
Total = 388,000

Foundation Filling
Labour = 92,000
Laterite = 326,000
Total = 418000

DPC - Half
DPM Nylon = 11,500
Granite= 10 tonnes = 45,000
Tara = 10 tonnes =13,000
Sharp sand = 10 tonnes = 15,500
Planks - 25 pieces & nails = 25000
Iron
16mm - 4 lengths @4400 = 17600
8mm - 3 lengths @ 1250 = 3750
Binding wire =2500
Transport = 2500
Workmanship
Labourer = 40000
Welder and carpenter = 13000
Cement = 28 bags @ 2500= 70000
Wire Mesh = 10500
Total = 273,000

Above Foundation Block setting + 2 soak away pits
Blocks 4100 @ 150 = 615000
Water = 3000
Sharp sand = 36000
Joining sand = 18000
Cement @2500 =162500
labour = 56000
Total = 891000

Lintel and Pillars Casting
16mm - 8 lengths @ 3630 = 29040
8mm - 31 lengths @ 1030 = 31930
12mm - 34 lengths @ 2050 = 69700
1 binding wire = 4000
Transport & logistics = 4000
Wood and planks ➕ TP = 51000
Granite = Used remains
Sharp sand = 15000
Cement = 30 bags @ 2500 = 75000
Workmanship
Labour 40000
Carpenter 22000
Iron bender 17000
Total =360000

Parapet and soak away Casting
Iron plus
12mm - 30 lengths @ 1970 = 59100
8mm - 51 lengths @ 1420 = 72420
Big Binding wire @ 7000
Extra iron = 9000
Quarter rod - 15 lengths @ 200 = 3000
Transport = 3500
Workmanship = 25000
Wood and cutting = 175000
Nail = 11100
Transport = 4000
Workmanship = 40000
Granite = 20 tonnes = 100000
Sharp sand = 15 tonnes = 21000
Cement 50 bags @ = 130000
Labour = 50000
Total = 710,000

Electrical
20mm pipe = 2 bundles @2100
25mm pipe = 1 bundle @ 3200
Electrical materials = 14000
Workmanship =9000

Plumbing
Internal plumbing
Cost of pipes and accessories = 47,000
Labour = 18,000

shocked
Valentine87:
this what some else spent in finishing all his bock work of a bungalow that is even bigger


This what I have spent to this stage.

Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000

Blinding
Cement - 30 bags @ 2500 = 75,000
Sharp Sand - 20 tonnes = 32,000
Granite - 25 tonnes = 105,000
Total = 212,000

Foundation Block Setting & Sock away Pit
Blocks = 1400 @ 150 = 210,000
Cement - 30 bags @ 2400 = 72,000
Sharp Sand =15 tonnes = 24,000
Labour for Soak away = 62,000
Extra Labour Expenses = 20,000
Total = 388,000

Foundation Filling
Labour = 92,000
Laterite = 326,000
Total = 418000

DPC - Half
DPM Nylon = 11,500
Granite= 10 tonnes = 45,000
Tara = 10 tonnes =13,000
Sharp sand = 10 tonnes = 15,500
Planks - 25 pieces & nails = 25000
Iron
16mm - 4 lengths @4400 = 17600
8mm - 3 lengths @ 1250 = 3750
Binding wire =2500
Transport = 2500
Workmanship
Labourer = 40000
Welder and carpenter = 13000
Cement = 28 bags @ 2500= 70000
Wire Mesh = 10500
Total = 273,000

Above Foundation Block setting + 2 soak away pits
Blocks 4100 @ 150 = 615000
Water = 3000
Sharp sand = 36000
Joining sand = 18000
Cement @2500 =162500
labour = 56000
Total = 891000

Lintel and Pillars Casting
16mm - 8 lengths @ 3630 = 29040
8mm - 31 lengths @ 1030 = 31930
12mm - 34 lengths @ 2050 = 69700
1 binding wire = 4000
Transport & logistics = 4000
Wood and planks ➕ TP = 51000
Granite = Used remains
Sharp sand = 15000
Cement = 30 bags @ 2500 = 75000
Workmanship
Labour 40000
Carpenter 22000
Iron bender 17000
Total =360000

Parapet and soak away Casting
Iron plus
12mm - 30 lengths @ 1970 = 59100
8mm - 51 lengths @ 1420 = 72420
Big Binding wire @ 7000
Extra iron = 9000
Quarter rod - 15 lengths @ 200 = 3000
Transport = 3500
Workmanship = 25000
Wood and cutting = 175000
Nail = 11100
Transport = 4000
Workmanship = 40000
Granite = 20 tonnes = 100000
Sharp sand = 15 tonnes = 21000
Cement 50 bags @ = 130000
Labour = 50000
Total = 710,000

Electrical
20mm pipe = 2 bundles @2100
25mm pipe = 1 bundle @ 3200
Electrical materials = 14000
Workmanship =9000

Plumbing
Internal plumbing
Cost of pipes and accessories = 47,000
Labour = 18,000


Thank you for this

1 Like

Re: Help With Costing Of 4 Bedroom Bungalow by Godisgreatest1: 7:41pm On Mar 18, 2020
Valentine87:
this what some else spent in finishing all his bock work of a bungalow that is even bigger


This what I have spent to this stage.

Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000

Blinding
Cement - 30 bags @ 2500 = 75,000
Sharp Sand - 20 tonnes = 32,000
Granite - 25 tonnes = 105,000
Total = 212,000

Foundation Block Setting & Sock away Pit
Blocks = 1400 @ 150 = 210,000
Cement - 30 bags @ 2400 = 72,000
Sharp Sand =15 tonnes = 24,000
Labour for Soak away = 62,000
Extra Labour Expenses = 20,000
Total = 388,000

Foundation Filling
Labour = 92,000
Laterite = 326,000
Total = 418000

DPC - Half
DPM Nylon = 11,500
Granite= 10 tonnes = 45,000
Tara = 10 tonnes =13,000
Sharp sand = 10 tonnes = 15,500
Planks - 25 pieces & nails = 25000
Iron
16mm - 4 lengths @4400 = 17600
8mm - 3 lengths @ 1250 = 3750
Binding wire =2500
Transport = 2500
Workmanship
Labourer = 40000
Welder and carpenter = 13000
Cement = 28 bags @ 2500= 70000
Wire Mesh = 10500
Total = 273,000

Above Foundation Block setting + 2 soak away pits
Blocks 4100 @ 150 = 615000
Water = 3000
Sharp sand = 36000
Joining sand = 18000
Cement @2500 =162500
labour = 56000
Total = 891000

Lintel and Pillars Casting
16mm - 8 lengths @ 3630 = 29040
8mm - 31 lengths @ 1030 = 31930
12mm - 34 lengths @ 2050 = 69700
1 binding wire = 4000
Transport & logistics = 4000
Wood and planks ➕ TP = 51000
Granite = Used remains
Sharp sand = 15000
Cement = 30 bags @ 2500 = 75000
Workmanship
Labour 40000
Carpenter 22000
Iron bender 17000
Total =360000

Parapet and soak away Casting
Iron plus
12mm - 30 lengths @ 1970 = 59100
8mm - 51 lengths @ 1420 = 72420
Big Binding wire @ 7000
Extra iron = 9000
Quarter rod - 15 lengths @ 200 = 3000
Transport = 3500
Workmanship = 25000
Wood and cutting = 175000
Nail = 11100
Transport = 4000
Workmanship = 40000
Granite = 20 tonnes = 100000
Sharp sand = 15 tonnes = 21000
Cement 50 bags @ = 130000
Labour = 50000
Total = 710,000

Electrical
20mm pipe = 2 bundles @2100
25mm pipe = 1 bundle @ 3200
Electrical materials = 14000
Workmanship =9000

Plumbing
Internal plumbing
Cost of pipes and accessories = 47,000
Labour = 18,000

Well detailed and clear, thank you and best regards.
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 7:53pm On Mar 18, 2020
Re: Help With Costing Of 4 Bedroom Bungalow by Amastermovic(m): 7:55pm On Mar 18, 2020
I will post tomorrow the quantity of the materials needed to the last block excluding roofing..
After that stage I might help u with d quantity of tiles needed also ..mind you u will fix d price to each material urself will just tell u d quantity..


[color=#006600][/color]
Re: Help With Costing Of 4 Bedroom Bungalow by Perfecttouchade: 9:42pm On Mar 18, 2020
grafixdon:


Thank you
welcome sir
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 3:11pm On Mar 19, 2020
Amastermovic:
I will post tomorrow the quantity of the materials needed to the last block excluding roofing..
After that stage I might help u with d quantity of tiles needed also ..mind you u will fix d price to each material urself will just tell u d quantity..


[color=#006600][/color]

Thanks boss
Re: Help With Costing Of 4 Bedroom Bungalow by saydfact(m): 11:25pm On Mar 19, 2020
Perfecttouchade:
cc: saydfact

Plus send a WhatsApp message pls.

I can't promise full estimate but Ian help with major.breakdown.. Been busy and unavailable.

Thanks
Re: Help With Costing Of 4 Bedroom Bungalow by yak(m): 11:40pm On Apr 02, 2020
Valentine87:
this what some else spent in finishing all his bock work of a bungalow that is even bigger


This what I have spent to this stage.

Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000

Blinding
Cement - 30 bags @ 2500 = 75,000
Sharp Sand - 20 tonnes = 32,000
Granite - 25 tonnes = 105,000
Total = 212,000

Foundation Block Setting & Sock away Pit
Blocks = 1400 @ 150 = 210,000
Cement - 30 bags @ 2400 = 72,000
Sharp Sand =15 tonnes = 24,000
Labour for Soak away = 62,000
Extra Labour Expenses = 20,000
Total = 388,000

Foundation Filling
Labour = 92,000
Laterite = 326,000
Total = 418000

DPC - Half
DPM Nylon = 11,500
Granite= 10 tonnes = 45,000
Tara = 10 tonnes =13,000
Sharp sand = 10 tonnes = 15,500
Planks - 25 pieces & nails = 25000
Iron
16mm - 4 lengths @4400 = 17600
8mm - 3 lengths @ 1250 = 3750
Binding wire =2500
Transport = 2500
Workmanship
Labourer = 40000
Welder and carpenter = 13000
Cement = 28 bags @ 2500= 70000
Wire Mesh = 10500
Total = 273,000

Above Foundation Block setting + 2 soak away pits
Blocks 4100 @ 150 = 615000
Water = 3000
Sharp sand = 36000
Joining sand = 18000
Cement @2500 =162500
labour = 56000
Total = 891000

Lintel and Pillars Casting
16mm - 8 lengths @ 3630 = 29040
8mm - 31 lengths @ 1030 = 31930
12mm - 34 lengths @ 2050 = 69700
1 binding wire = 4000
Transport & logistics = 4000
Wood and planks ➕ TP = 51000
Granite = Used remains
Sharp sand = 15000
Cement = 30 bags @ 2500 = 75000
Workmanship
Labour 40000
Carpenter 22000
Iron bender 17000
Total =360000

Parapet and soak away Casting
Iron plus
12mm - 30 lengths @ 1970 = 59100
8mm - 51 lengths @ 1420 = 72420
Big Binding wire @ 7000
Extra iron = 9000
Quarter rod - 15 lengths @ 200 = 3000
Transport = 3500
Workmanship = 25000
Wood and cutting = 175000
Nail = 11100
Transport = 4000
Workmanship = 40000
Granite = 20 tonnes = 100000
Sharp sand = 15 tonnes = 21000
Cement 50 bags @ = 130000
Labour = 50000
Total = 710,000

Electrical
20mm pipe = 2 bundles @2100
25mm pipe = 1 bundle @ 3200
Electrical materials = 14000
Workmanship =9000

Plumbing
Internal plumbing
Cost of pipes and accessories = 47,000
Labour = 18,000



what's the size of this property sir?
because I have a small 3bed bungalow that got to bungalow today. can't continue because of the govt lockdown order

(1) (Reply)

Mini Flat And 2 Bedroom Flat @ Okota For Rent / 6 Units Of Newly Built 3 Bedroom Flats For Rent, Awoyaya, Lagos / Get Nice Architectural Designs From A Fresh Graduate Architect At Low Prices

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 54
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.