PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI - Properties (10) - Nairaland

Nairaland Forum / Nairaland / General / Properties / PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI (53390 Views)

Construction Process Of A 6 Flats (3 Bedrooms House) / ABUJA:CONSTRUCTION PROCESS OF TERRACE BUILDING BY MOORE / Construction Process Of The 3 Bedroom Block Of Four Flats In Warri (2) (3) (4)

(1) (2) (3) ... (7) (8) (9) (10) (11) (12) (13) ... (43) (Reply) (Go Down)

Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:49pm On Feb 02, 2016
Roofing carcass in progress
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 5:00pm On Feb 02, 2016
Picture shortly
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 1:09pm On Feb 04, 2016
segcymoor:
Roof carcass in progress

Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Dominionng(m): 1:19pm On Feb 04, 2016
Well-done Boss mi.
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 1:35pm On Feb 05, 2016
Dominionng:
Well-done Boss mi.
How is work going.?
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by sgtkole: 2:53pm On Feb 05, 2016
[quote author=segcymoor post=42612314][/quote]

Good work sir!

Where in lekki is this project? because i need a piling job for a project in lekki also.
provide you mail so we can discuss further.
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:26pm On Feb 05, 2016
sgtkole:


Good work sir!

Where in lekki is this project? because i need a piling job for a project in lekki also.
provide you mail so we can discuss further.

https://www.nairaland.com/1854938/pile-foundation-terrace-building-lekki
This particular project is at off Mobil road, just behind Royal Garden Estate
......and the Terrace building is at Green land Estate, just after LBS

MOORE-DESIGNBUILD LTD|...We ve wealthy of experience in Pilling Foundation

Do send ur mail to -mooredesignbuild@gmail.com for futher discussion
Regards!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Dominionng(m): 1:23am On Feb 08, 2016
segcymoor:

How is work going.?

We bless God Boss.
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by sgtkole: 7:54am On Feb 08, 2016
A mail will be sent shortly.

segcymoor:


https://www.nairaland.com/1854938/pile-foundation-terrace-building-lekki
This particular project is at off Mobil road, just behind Royal Garden Estate
......and the Terrace building is at Green land Estate, just after LBS

MOORE-DESIGNBUILD LTD|...We ve wealthy of experience in Pilling Foundation

Do send ur mail to -mooredesignbuild@gmail.com for futher discussion
Regards!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:52pm On Feb 08, 2016
sgtkole:
A mail will be sent shortly.

ok
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by bobo2k3(m): 4:41pm On Feb 18, 2016
Oga Tonny, na only u dey enjoy for Lekki. When are we covering the project. Pls am waiting to see the output of the carcass. Weldone friend.
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 6:01pm On Feb 24, 2016
bobo2k3:
Oga Tonny, na only u dey enjoy for Lekki. When are we covering the project. Pls am waiting to see the output of the carcass. Weldone friend.
Enjoy wetin?...abeg forget all those bobo
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:07pm On Feb 25, 2016
Roof covering in progress

Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:16pm On Feb 26, 2016
Completion of carcass

Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 8:39pm On Mar 02, 2016
Double volume living room

Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:04am On Mar 05, 2016
We really thank God for successfully completion of this carcass despite all odd.





-----------
It really challenging!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:10pm On Mar 09, 2016
segcymoor:
We really thank God for successfully completion of this carcass despite all odd.
-----------
It really challenging!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by google1(m): 6:44pm On Mar 09, 2016
Good work sir, you have great wealth of experience in building construction, Keep up the Good work. From an aspiring builder.
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:22pm On Mar 09, 2016
MOORE-DESIGNBUILD LTD-We do structures right!

mooredesignbuild@gmail.com
08091110234 (calls & WhatsApp)
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:51pm On Mar 10, 2016
Plastering work in progress
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:47pm On Mar 11, 2016
segcymoor:
Plastering work in progress
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:44pm On Mar 12, 2016
MOORE-DESIGNBUILD LTD


--------
We do structures right!
mooredesignbuild@gmail.com
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:38am On Mar 14, 2016
segcymoor:
MOORE-DESIGNBUILD LTD


--------
We do structures right!
mooredesignbuild@gmail.com
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:23pm On Mar 15, 2016
External plastering

Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:26pm On Apr 23, 2016
MOORE-DESIGNBUILD LTD
08091110234
mooredesignbuild@gmail.com
We set to serve but better!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:57am On Jun 03, 2016
segcymoor:
MOORE-DESIGNBUILD LTD
--------
We do structures right!
mooredesignbuild@gmail.com
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:58am On Jun 03, 2016
segcymoor:
MOORE-DESIGNBUILD LTD
--------
We do structures right!
mooredesignbuild@gmail.com


--------
We do!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:52pm On Jun 21, 2016
Integrity!


--------
Our watch words!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:46pm On Jun 22, 2016
segcymoor:
MOORE-DESIGNBUILD LTD
08091110234
mooredesignbuild@gmail.com
We set to serve but better!
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:56am On Jul 13, 2016
Finishing works in progress.....
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:56am On Jul 13, 2016
Finishing works in progress...........
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:57am On Jul 13, 2016
Finishing works in progress.....

(1) (2) (3) ... (7) (8) (9) (10) (11) (12) (13) ... (43) (Reply)

That’s Not Inside The Abuja Mansion Of Africa’s Richest Man, Dangote / See The Tallest Building In Africa / Chelsea Estate In Ajah Lagos: John Mikel Obi Is Building It...

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)