Re: Construction Progress Of 2nd Niger Bridge. by adanny01(m): 2:19pm On Aug 01, 2019
bigpicture001:


Yes they can...by placing very many large pipes below the constructed road to allow for water flow

Pls tell me you are joking.

First you have to calculate the amount of water passing that point in a minute the provide the pipes that would allow passage of the same water plus account for friction, turbulence etc

By this time you are not just back to square 1 but you have actually made the problem worst because the pipes will not be able to bear the weight of a congested traffic on the road which is the worst case scenario. The possibilities of this being the worst idea is endless.

Water bodies are not what you will play with anyhow else it will lead to loss of lives and property.
Re: Construction Progress Of 2nd Niger Bridge. by obailala(m): 2:21pm On Aug 01, 2019
Dave0116:
if its true then its fine. But trust any nigerian government at your peril
Well, government policies do change with time. Another government could come in tomorrow and decide to toll the bridge and other new roads/bridges across the country. If the money received from the tolls would actually be used to maintain the roads/bridges to global standards, then tolling shouldn't be a bad idea. But you and I know how Nigerian governments operate, the money realised would certainly be diverted even whilst the roads/bridges degrade without maintenance.

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by OdumegwuOjukwu: 2:21pm On Aug 01, 2019
Afamed:

But GEJ stole your oil money


And Buhari is using the rest to fight Boko Haram, Shia, ISWAP, Cattle rustler, and politicians - basically wasting money and time, without any strategy.

Whatever is left he wants to use to resettle Fulani all over in world in Nigeria - Ruga!

This bridge, like several other infrastructure the dullard is trying to build are mostly from borrowed funds.

Wait until the dullard leaves office to see the full extent of the rot.

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by descartes400: 2:22pm On Aug 01, 2019
theenchanter:
guy, there's a bridge in Sweden, its exactly the way I thought but it has an opening at one end.

Show us the pictures so that nairaland engineers can dissect and analyse it and make recommendations to the appropriate channels tongue

2 Likes

Re: Construction Progress Of 2nd Niger Bridge. by shogsman(m): 2:22pm On Aug 01, 2019
theenchanter:
The question is..... since they can sandfill the construction site for heavy trucks to move materials, why can't they just sandfill that very place and build the road on it without building the bridge?

Won't it save more than building the bridge? undecided

Lol it's too dangerous because the water will fight back,it's better to be safe than sorry that's why the road is above ground.
Re: Construction Progress Of 2nd Niger Bridge. by Bobnotrouble: 2:23pm On Aug 01, 2019
That's fantastic! Even though the psychologically blind wailing wailers wont see this progress and appreciate it.

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by Nobody: 2:24pm On Aug 01, 2019
etrouble:
And they still hate Buhari. What your brother Goatluck could not do for 5.5 wated years, what your party PDP could not do for 16 miserable years, your enemy, the Fulani herdsman called Buhari is doing it. May God not make us beg our enemy for food. The money in imPatience Jonathan accounts can build this bridge.
what is wrong with you, must you bring in tribalism. you have a lot of problem, it is just that you are not aware of it. can you tell me any president in Nigeria that has not done something tangible during his time?
Re: Construction Progress Of 2nd Niger Bridge. by Afamed: 2:24pm On Aug 01, 2019
descartes400:


Show us the pictures so that nairaland engineers can dissect and analyse it and make recommendations to the appropriate channels tongue
Ignore him most of them are born to hate
Re: Construction Progress Of 2nd Niger Bridge. by sunsewa16: 2:24pm On Aug 01, 2019
FOLYKAZE:


Is this how bridges are constructed on expanded rivers and lagoons?

I have always wondered how third mainland bridge was built. Do the engineers have to sand-fill every now and then before they can complete it?

No, not in all cases, light railway bridge in marina Lagos is typical example,it was not Sand filled before or while erecting the bridge.

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by descartes400: 2:26pm On Aug 01, 2019
Dpharisee:


That Bridge is being built with out Oyel money and not from Buharis pocket. Moreover it will be for the benefit of Nigerians from every part who do business in that axis. Enough of the hate and stupid comments angry

Was the same "our oyel money" not available for GEJ and even more but yet did nothing about it?

8 Likes

Re: Construction Progress Of 2nd Niger Bridge. by LZAA: 2:27pm On Aug 01, 2019
yemmight:
Later some IPOB bigots will say there is nothing like 2nd bridge construction in the east.

1 Share

Re: Construction Progress Of 2nd Niger Bridge. by Godwin2am(m): 2:28pm On Aug 01, 2019
theenchanter:
The question is..... since they can sandfill the construction site for heavy trucks to move materials, why can't they just sandfill that very place and build the road on it without building the bridge?

Won't it save more than building the bridge? undecided
HOW ABOUT THE FLOW OF WATER AND BIG SHIP?
Re: Construction Progress Of 2nd Niger Bridge. by Nobody: 2:29pm On Aug 01, 2019
9jatriot:
Every other region celebrates the construction work that goes on there.


If PMB can tackle the Fulani herdsmen and other security wahala, PDP will have nothing else to campaign with so that they can be relegated to the dustbin of history. PDP knows this that is why security is not likely to improve as that is the only ace they have up their sleeves.
What about the economy? undecided
Re: Construction Progress Of 2nd Niger Bridge. by Afamed: 2:30pm On Aug 01, 2019
[quote author=LZAA post=80836621][/quote]
Oya now.No second Niger bridge construction going on?
Re: Construction Progress Of 2nd Niger Bridge. by winterfell007(m): 2:30pm On Aug 01, 2019
Afamed:

But your Otueke GEJ with faster 5G speed and even PhD holder didn't start the bridge now . Or suddenly you have forgotten

Idiots even if GEJ was still there, the bridge construction will have continued regardless. The financing arrangement was already sorted by them. Okonjo Iweala, the current MD of Nigeria Sovereign Wealth Fund (NSIA), Mr. Uche Orji all perfected the financing arrangement with the FG already paying down their 30% counterpart funding and NSIA and JB will source the remaining through ECA and equities. PMB assumed into office and saw a worked out system in place and followed it up as expected of him
So stop blabbing about how PMB is doing us a favour, because it's not a favour, it's our bloody right. Even if he decides to hault the project, successive administrations will complete it. So Bleep off

2 Likes 2 Shares

Re: Construction Progress Of 2nd Niger Bridge. by IkemChris(m): 2:31pm On Aug 01, 2019
theenchanter:
The question is..... since they can sandfill the construction site for heavy trucks to move materials, why can't they just sandfill that very place and build the road on it without building the bridge?

Won't it save more than building the bridge? undecided
Nice question. You get brain. The answer is simple though. The sandfill is just for a temporary basis. Over time they will allow the flow of water if not the water level will rise and you know what it means naa
Re: Construction Progress Of 2nd Niger Bridge. by stankezzy: 2:32pm On Aug 01, 2019
as an engineer d company building it is using local technology, with modern technology bridges are built with fewer but more strong pillars with bigger gaps in between to allow bigger vessels to pass through, strong steel alloys are use for the top since d gaps are more d strength of d materials will be great so that it doesn't cave in but in this case they are using Chinese local technology ,supporting it with a lot of small useless pillars, choking up spaces, vessels d size of trailer or container body can't pass under this bridge , bad technology

2 Likes

Re: Construction Progress Of 2nd Niger Bridge. by Engrduke: 2:33pm On Aug 01, 2019
theenchanter:
The question is..... since they can sandfill the construction site for heavy trucks to move materials, why can't they just sandfill that very place and build the road on it without building the bridge?

Won't it save more than building the bridge? undecided


I want to believe that you asked an innocent question here, so you don't deserve any scolding.
No amount of "sandfilling" and asphaltic laying would make any road constructed around that area be able to withstand the tension and loads Dangote trucks and the likes would be exerting on it.

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by Godoverevery: 2:35pm On Aug 01, 2019
OdumegwuOjukwu:



Whatever.

Fact is Buhari is doing no one a favour but doing his job.

He deserves no accolade for continuing a job and there is no guarantee in any case that he will finish it.

He still stands the worst president ever to have presided over Nigeria!
You are a man.....been bitter about D's make no sense.
Re: Construction Progress Of 2nd Niger Bridge. by femi4: 2:35pm On Aug 01, 2019
theenchanter:
The question is..... since they can sandfill the construction site for heavy trucks to move materials, why can't they just sandfill that very place and build the road on it without building the bridge?

Won't it save more than building the bridge? undecided
Water will always find another route and that might lead to a serious flood. Like the way bar beach is dealing with lagosians
Re: Construction Progress Of 2nd Niger Bridge. by GreenArrow2: 2:36pm On Aug 01, 2019
OdumegwuOjukwu:



Whatever.

Fact is Buhari is doing no one a favour but doing his job.

He deserves no accolade for continuing a job and there is no guarantee in any case that he will finish it.

He still stands the worst president ever to have presided over Nigeria!

Save yourself the hate and anger. Those who sold you guys that rhetoric were paid for the job before and during elections. Even they have lost and since moved on. If to say i follow Buhari and Nairaland hatred...hmmm na stagnation straight!

2 Likes

Re: Construction Progress Of 2nd Niger Bridge. by ridbell01(m): 2:36pm On Aug 01, 2019
VenusTechShop:
Are these not same pictures that have been circulating the cyber space for over 3 years now? Why is this bridge being used for Politics always? When will this bridge ever pass Pillar like level?

Tufia.
product of hate and perdition.. Team ATIKU IS CUMMING. YOU ARE SIGHTED

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by Afamed: 2:36pm On Aug 01, 2019
winterfell007:


Idiots even if GEJ was still there, the bridge construction will have continued regardless. The financing arrangement was already sorted by them. Okonjo Iweala, the current MD of Nigeria Sovereign Wealth Fund (NSIA), Mr. Uche Orji all perfected the financing arrangement with the FG already paying down their 30% counterpart funding and NSIA and JB will source the remaining through ECA and equities. PMB assumed into office and saw a worked out system in place and followed it up as expected of him
So stop blabbing about how PMB is doing us a favour, because it's not a favour, it's our bloody right. Even if he decides to hault the project, successive administrations will complete it. So Bleep off
I hardly exchange banter with nonentity especially the indomie generation

3 Likes

Re: Construction Progress Of 2nd Niger Bridge. by Nobody: 2:37pm On Aug 01, 2019
VenusTechShop:
Are these not same pictures that have been circulating the cyber space for over 3 years now? Why is this bridge being used for Politics always? When will this bridge ever pass Pillar like level?

[b]Tufia.
YOU THINK BY ABRAKADRA IT WILL JUST RISE UP.A WAILER IS SPOTTED[/b].
Re: Construction Progress Of 2nd Niger Bridge. by winterfell007(m): 2:37pm On Aug 01, 2019
obailala:
The tolling was the original idea when the bridge was conceived in 2014. But the current government cancelled the tolling arrangement; the bridge is currently being built by FG alone, no more PPP.

There hasn't been any cancellation. PMB is just following up the process as planned by his predecessor. FG during GEJ's tenure had a already paid up their counterpart funding. The project is under the active management of the NSIA
Re: Construction Progress Of 2nd Niger Bridge. by OdumegwuOjukwu: 2:38pm On Aug 01, 2019
Godoverevery:

You are a man.....been bitter about D's make no sense.

Bitter about what?

How did you read bitter in the text? I wonder how folks read messages these days. Counter argument is now bitterness?

Please speak for and about yourself. I don't need your negative projection.

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by Godoverevery: 2:38pm On Aug 01, 2019
winterfell007:


Idiots even if GEJ was still there, the bridge construction will have continued regardless. The financing arrangement was already sorted by them. Okonjo Iweala, the current MD of Nigeria Sovereign Wealth Fund (NSIA), Mr. Uche Orji all perfected the financing arrangement with the FG already paying down their 30% counterpart funding and NSIA and JB will source the remaining through ECA and equities. PMB assumed into office and saw a worked out system in place and followed it up as expected of him
So stop blabbing about how PMB is doing us a favour, because it's not a favour, it's our bloody right. Even if he decides to hault the project, successive administrations will complete it. So Bleep off
so it was after 5yr Gej remember to make the arrangement......I don't no why all D's hate for......i av lot of igbo friends here in lag and dey aiin't D's bitter.....
Re: Construction Progress Of 2nd Niger Bridge. by GreenArrow2: 2:39pm On Aug 01, 2019
stankezzy:
as an engineer d company building it is using local technology, with modern technology bridges are built with fewer but more strong pillars with bigger gaps in between to allow bigger vessels to pass through, strong steel alloys are use for the top since d gaps are more d strength of d materials will be great so that it doesn't cave in but in this case they are using Chinese local technology ,supporting it with a lot of small useless pillars, choking up spaces, vessels d size of trailer or container body can't pass under this bridge , bad technology

The choice of any particular method of construction lies not just with the contractor but also the client's brief.
Re: Construction Progress Of 2nd Niger Bridge. by gcof(m): 2:40pm On Aug 01, 2019
theenchanter:
nice response, very correct.

I didn't think of such thing.... was basing my thought on financial aspect alone.
you must be an Igbo Man
Re: Construction Progress Of 2nd Niger Bridge. by winterfell007(m): 2:40pm On Aug 01, 2019
Afamed:

I hardly exchange banter with nonentity especially the indomie generation

As expected when faced with a superior argument, they begin to term you 'indomie generation'. Counter it and don't cower

1 Like

Re: Construction Progress Of 2nd Niger Bridge. by ridbell01(m): 2:41pm On Aug 01, 2019
Dave0116:
While you're deceiving them with a bridge pls don't fail to tell them that you're not funding the bridge but a toll will be placed on the bridge for at least 50years to refund the company funding the bridge..... #StayWokeNaija
your hero ought to have done that also
Re: Construction Progress Of 2nd Niger Bridge. by Afamed: 2:41pm On Aug 01, 2019
stankezzy:
as an engineer d company building it is using local technology, with modern technology bridges are built with fewer but more strong pillars with bigger gaps in between to allow bigger vessels to pass through, strong steel alloys are use for the top since d gaps are more d strength of d materials will be great so that it doesn't cave in but in this case they are using Chinese local technology ,supporting it with a lot of small useless pillars, choking up spaces, vessels d size of trailer or container body can't pass under this bridge , bad technology
Engineer, don't die of hatred. There is a space for vessels close to the first Niger bridge already which is not far from the second Niger bridge. Ships and vessels are making use of that and as a result they have no business getting to the second Niger bridge.

(1) (2) (3) (4) (5) (6) (Reply)

Obasanjo’s Aide Disarms Drunken Policeman At Igbinedion’s 85th Birthday / Olusegun Obasanjo During His Traditional Wedding Years Back (Photo) / Court Orders Immediate Release Of Emefiele, Bars DSS From Re-arresting Him

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 51
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.