Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,152,133 members, 7,814,964 topics. Date: Thursday, 02 May 2024 at 02:35 AM

The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" - Properties (14) - Nairaland

Nairaland Forum / Nairaland / General / Properties / The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" (23470 Views)

The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms / The Making Of The "Emene Enugu Block Of 6 Flats Of 2 Bedrooms" / The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra (2) (3) (4)

(1) (2) (3) ... (11) (12) (13) (14) (15) (16) (Reply) (Go Down)

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by michlins(m): 5:20am On Sep 13, 2022
collele:


Where's your location
my location is Nnewi Anambra State sir.

Good morning sir
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 2:04pm On Sep 14, 2022
Work updates on the roofing wood, so much rains in Asaba.

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:26am On Sep 15, 2022
Measurements for roofing sheets will be done for this shop today.
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:34am On Oct 07, 2022
We have completely roofed the shops at this house...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:39am On Oct 07, 2022
More pictures of the ongoing work at this site.............

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:42am On Oct 07, 2022
Generator base........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:44am On Oct 07, 2022
Working on the remaining doors, burglar proofs and handrails.............

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:39am On Oct 07, 2022
Work goes on.
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 11:35am On Nov 06, 2022
Our plastering works on the inside of the shops..........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 11:39am On Nov 06, 2022
The rooms upstairs...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 11:45am On Nov 06, 2022
The shops as at last week.........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 11:49am On Nov 06, 2022
Inside the compound.................

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:30am On Nov 07, 2022
Getting ready to do the windows, doors, ceul8ng and other remaining works at this site.
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:40pm On Nov 23, 2022
Fence caps being cast in this site, as we complete all other works at this site.

More pictures later.

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:47pm On Nov 23, 2022
Our house, as seen from another neighbouring site..........

1 Like

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by rukyboy(m): 12:42pm On Nov 25, 2022
spyder880:
Working on the remaining doors, burglar proofs and handrails.............
.

Engr. Is that POP im seeing at the staircase area ?
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 1:37pm On Nov 25, 2022
rukyboy:
.

Engr. Is that POP im seeing at the staircase area ?

Yes, cornice and a screeded centre.
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by rukyboy(m): 2:15pm On Nov 25, 2022
spyder880:


Yes, cornice and a screeded centre.

I was told that the difference in cost between fixing POP on decking and Plastering/screeding/cornice isn't much .

Is this true pls
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 6:56pm On Nov 26, 2022
Some random pictures from our work in this site, from bother the main building and the shops........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 6:59pm On Nov 26, 2022
More doors dressing, more shops dressing and more fence plastering and dressing..........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:03pm On Nov 26, 2022
The fence we are working on today...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 12:29pm On Dec 13, 2022
We plan to start work on the laying of pipes on the compound of this building, the work should start as from tomorrow. Waste pipes, water pipes etc. We also plan to do the inspection chambers before casting the compound floor before the end of this year.

More pictures later.
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 12:19pm On Dec 24, 2022
Pipes laid in this compound, chambers done and completed.......

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 12:20pm On Dec 24, 2022
More.......

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 12:21pm On Dec 24, 2022
We are poised to start the works on the compound floor...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 2:51pm On Jan 09, 2023
We're back to this site, we are completing all fence plastering and dressing works prior to the compound floor works.

More pictures later.
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:24am On Jan 22, 2023
We have done a lot of finish works on this building as we move to complete the house...........

1 Like

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:27am On Jan 22, 2023
More pictures as we prepare to cast the concrete of the compound...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:30am On Jan 22, 2023
More pictures...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:33am On Jan 22, 2023
From inside some flats...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:34am On Jan 22, 2023
Outside, the fence has been completed...........

Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:40am On Jan 22, 2023
Still more........

1 Like

(1) (2) (3) ... (11) (12) (13) (14) (15) (16) (Reply)

Emeka Ikwechegh Donates New House To Blind Woman In Abia (Photos) / Photos: Shops In Oshodi Under Demolition / 3 BED LUXURY APARTMENTS AT TREASURE HOMES ILASA MUSHIN

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 20
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.