Column Formwork preparation ongoing at Atlantic View
|
Atlantic View
|
Updates from the Atlantic View Project
|
Atlantic View Project - Just in Preparation work ongoing for the structural framework.
|
LKH Plot 10AB
|
POP Ceiling Work at LKH Plot 10AB Interestingly, we didn't plaster the slab of this house. We just screed over the neatly finished slab, all thanks to our marine board slab formwork.
|
Awoyaya MultiDwell
|
And more...
|
More
|
Desmond Flats by NextHome - Lwvels don change now
|
caseymoney:Respect bro! We give thanks to God. |
LASU Mixed-Use Development The shops we built has been occupied by tenants yielding almost 35% ROI in the first year. The apartment is almost at decking level. Remember, we are building 6 units of executive 2 bed and 2.5 bath flats. Picture updates coming later on this thread. |
Awoyaya MultiDwell - Preparing for the pour of the ground beams/raft. Pic updates later today. |
3strike:The update will come alive tomorrow morning. We are still at construction site pouring the DPC of one of our site. |
Square One by NextHome - Foundation Work Completed
|
Atlantic View Contemporary Living - Just in
|
Akoka MultiDwell by NextHome - Groundworks/Unloading of existing columns https://www.youtube.com/watch?v=Z3M5-INzJgk https://www.youtube.com/watch?v=k9hoKji7GXM
|
New and Upcoming Next Week - 20 Rooms Residential Hostel in UNAAB. Project starts next week. Pre-works underway. |
Atlantic View Contemporary Living Happening Now - Pouring of the DPC. Picture updates later this evening. |
K-024 by NextHome Often times, proper curing of concrete is neglected. The main reasons for these on the part of the contractor is our desire for rapid production. Time is money! We (the contractor) want to finish building the house in record time without considering the health of the concrete. Clients often lack patience, especially when time is money, and curing demands serious patience and attention to detail. This project is an exception to the odd. The timing is right and the physical health of the structure is of paramount importance. Watch us build K-024! https://www.youtube.com/watch?v=878woNELQWI
|
EndiaSami:Let's have a meeting sometimes this week. There are lot of stuffs we can do together in the coming weeks. |
Inside NextHome H52
|
Inspired Spaces By NextHome Concept design of Square One modern shops. Work in progress.
|
NextHome | K-024 Getting the most out of concrete with strict attention to proper curing.
|
The Reserve - See what N40m can get you! https://www.youtube.com/watch?v=xLs7ayPWpEM https://www.youtube.com/watch?v=OrPBFZKrU7k |
Upcoming! - Creating Inspired Spaces Ecolodges and Beach Resort Development by NextHome
|
nextstep:Thanks once again. You inspired us to do more. In answer to question, we do not need any lining. We have a team in charge of cleaning and maintenance of the forms and various tools of trade. Here's a short video of how we preserve and maintain our boards. https://www.youtube.com/watch?v=s51shQJ7FWA |
From K-024
|
K-024 by NextHome - Columns just the way I want it.
|
^^^Thanks for the compliment. |