More Plastering updates from here. We are doing the main building concrete facial and Fence Plastering simultaneously...
|
folmus:Thank you sir. |
Update on the roofing Works done here... We used Milano Roofing Pattern Stone Coated. About 350Sqm for both security and Gen House and BQ
|
Find attached the 3D Model of this project.
|
erico2k2:Thank you sir for coming around our thread. |
We have equally done the front fence works with coping just like designed on the 3D. We do as we say... We Design and Build to precision...
|
folmus:Good evening sir. Sorry we, waited for the borehole people to install the pump yesterday that was why we didn't put up any update. However we have that for you now. Pump used here is 1.5Hp and Depth is 70meters...
|
The Plastering labour for this all is 1.35m Which includes the main building. Security and Gen House. 45m fence Carpentry scaffolding Window Hood and art works. |
erico2k2:Check the link below https://www.nairaland.com/5955403/new-4-bedroom-duplex-swimming/15#102830553 |
Plastering with a difference. Follow us up here... https://www.nairaland.com/5955403/new-4-bedroom-duplex-swimming
|
Plastering Stage of our current project. Follow us up here... https://www.nairaland.com/5955403/new-4-bedroom-duplex-swimming |
More site updates. Comparing Design vs Actual Construction.
|
More work updates...
|
It just keeps getting better here...
|
josephsm823:Construction budget is on the earlier part of the thread. Finishing budget is not summed up yet because there is unstable rise in material cost. However we are doing it stage by stage of which when we are done with each stage we can state the amount spent herein. |
For more details on this work. Stage of Work: Plastering Follow this link below. https://www.nairaland.com/5955403/new-4-bedroom-duplex-swimming
|
We start from the concrete facial for Plastering... The security and Gen House...
|
Scaffolding works for external Plastering of the security and Gen House.
|
External scaffold works
|
We commenced borehole drilling today here too... Recommended depth from soil test report is about 65 - 70meters which is approximately over 230fit..
|
More Plastering update. Sitting room on the ground floor.
|
More site updates. Plastering ongoing still from the inside while we monitor the weather outside. Still very much the dinning area of this structure.
|
More photo update From what we have done so far. Staircase area Plastering...
|
Concrete coping on fence done...
|
EgunMogaji2:Thanks a bunch Sir for reading and following through. |
Good evening good people. Kindly follow up with us on the construction of this edifice. We Design and Build to 99% accuracy level. Current stage of work: Plastering https://www.nairaland.com/5955403/new-4-bedroom-duplex-swimming/15#102371755
|
A recap of the 3D Model of this project... Watch closely for all details. We are going to be doing them live in construction.
|
Here we go. My carpenter is representing in Enugu. BQ Roofing Update below...
|
We keep moving. Kindly stay in touch for more updates from us. |
Stay tuned for updates. We have started work on the front fence.
|
We do more than the ordinary way of doing things when carrying out construction. Reason why we have a standard for good and quality job delivery. Why understand the after effect of works and we look beyond now when working. Stay tuned for more updates. |
More updates would be coming from the interior Plastering. We are simultaneously doing some real time finish and cleaning up of the window frames from stains... We work, we clean, we render.
|