See the work progress so far on this hotel room transformation. Room space after screeding and then now furniture works to introduce new headboards and TV shelves
|
Additional electrical material we are buying to add for the works we have done on the decking stage and part of ground floor then.
|
As promised. Gate work updates. Gate works - 1.4m (Direct Client Negotiations with vendor). Electrical works too are ongoing. We are also doing two soakaway and septic tanks
|
Good morning Dear Followers. We are back here. Ready to resume. Granite just arrived. 30 Tons
|
Tiles removal and screeding works and Electrical works
|
More views of the from the terraces. Master's and Family Lounge Terrace alike
|
Site update from here. Plastering completed. Window hood done Fence art works ongoing.
|
Gate works ongoing here now...
|
Procurement of tiles, cements and tiles done. One shocking item on the list of what we budgeted for is POP CEMENT. We bought for 9200. That's really shocking. From a budget of 6,500 per bag.
|
Good afternoon Viewers. We have a new hotel room renovation on our hand. Scope of work. "Give the room a modern face-lift". Area of concentrations - Door: To be changed from MDF to glossy HDF - Wardrobe to be changed. - New Head Board from ground to POP - NEW Toilet Tiles Design. - New Plumbing Fittings Below is the existing picture of the hotel room.
|
Doors painted, keys installed and now being transported to site
|
. Good evening Dear followers We are glad to announce to you that. We are going back to site this November. Scope of Work would be communicated in due course. Stay tuned. .
|
Painting works on the doors Client chose cream color
|
We have now started the doors of this project We are fabricating irons doors...
|
Good afternoon Viewers |
Adedward:Thanks bro |
We are cleaning the windows as we Plastering to make final cleaning easier
|
. . . |
. . . Welcome back to our thread |
. . . . . |
. . . |
. . . Good afternoon Viewers |
. |
. . |
. I |
. . . |
. . . |
. . . Good evening all |
. . . After meeting with client on site today. We are glad to announce to you that we are going to be pushing through with other stages of work like wiring and POP next to finish before December meets us. So stay tuned with us as we update the thread as we get vital information and updates |
Resuming soon... We will be right back as soon as client gives a go ahead. Project is still within our purview
|
Resuming soon
|
Good evening House. Thanks For your follow up thus far on this project. As you all know, the first estimate (BOQ) for this project was done June 2021, that was what was used to start up the project though through client advise. He was subject to inflation and new price lists that we may encounter in the course of the project execution. The Project Costing is as Follows... Main Building = 36.5m Additional Fence Works = 1.85m Security and Gen House = 2.9m Total Expended so far = 41.25m Budget Variation on the main building mainly came from the cost of Granite which was 260K last year while we bought for 470K upon project start up. Sand was 26K now sold for 38K. Planks from 1300 now sold for 1750. Cement from 3500 to 4100 and some other new scope of works added to the project like ground beams and higher foundation level during filling. We are still hoping to start up the BQ of this project upon resumption. Below is the 3D model of what the building would look like upon finishing.
|