Stay tuned with us here. We are resuming fully by January 10th 2023. With wiring and POP Works to follow immediately. Stay tuned here and follow the thread. |
Update on the boy's Quarter works
|
Parapet works Iron works update. Completed today and concrete works to follow next
|
The BQ Parapet works is ongoing now. The Carpentry works
|
Plastering update on the first Soakaway and Septic Tank
|
conceptbiz:Good morning Ola, By concept, I feel biodigester ought to be better but then I haven't used it on any of my project. Hoping to soon at one of my Lagos project. One of the pending issues about it is the fact that it's a new system of sewage management in Nigeria that it's full potential and options haven't been weighed fully. Cost-wise I feel it's cheaper too. The conventional soakaway we know has its own advantages as well depending on the perimeter you are using to measure the two, though more expensive to do than the bio-digester. |
Work update on the second Soakaway and Septic
|
First Soakaway and Septic Tank work almost completed. Second one is underway too. Block work to commence on it today still.
|
Update on the BQ. Now at lintel level and done.
|
Good morning Viewers Doors installed now.
|
More view of the gate. Work is still ongoing on the gate.
|
Finished result from the works here Day Light View of the room See the quality of curtain we did.
|
Good evening dear followers. More updates to come online tomorrow. Thank you for following up with us. We appreciate it. Kindly drop your comments, questions, ideas where need be and when you want to. |
Soakaway and Septic Tank getting ready for concrete works
|
Electrical Piping ongoing Bedrooms and sitting rooms
|
We are moving at a great pace BQ block works commenced immediately today.
|
Work update today. Alot is happening simultaneously. Soakaway and Septic Tank works ongoing. BQ site concrete slab work ongoing. Fence cap work ongoing. Electrical Piping ongoing AC mechanical works ongoing.
|
We equally have gone to the Market and made procurement for the mechanical AC installations to the tone of about 765K for up to 25 Air Conditioning systems in the building. Find attached the pictures of the materials. Note: This AC piping works is different from that of the electricians. This one is specifically installed by AC technicians only for conduit purposes. Pictures of this would be uploaded as the work commences today.
|
See progress report so far and see what we have been able to do within this few days. BQ already backfilled.
|
See how it's looking now...
|
Bathroom Work update
|
Furniture Works update on the room. We are doing new bed head board, full wall. New TV shelve. New wardrobe New curtains. New Doors
|
Work update on the gate work and BQ Foundation works. And soakaway
|
The BQ has been set out. We are commencing digging immediately as well.
|
Bathroom work update here See current state vs Before state in the last two pictures
|
Soak away works ongoing. (Digging) Reinforcement works for BQ ongoing too. Electrical Piping Works ongoing as well.
|
See the work progress so far on this hotel room transformation. Room space after screeding and then now furniture works to introduce new headboards and TV shelves
|
Additional electrical material we are buying to add for the works we have done on the decking stage and part of ground floor then.
|
As promised. Gate work updates. Gate works - 1.4m (Direct Client Negotiations with vendor). Electrical works too are ongoing. We are also doing two soakaway and septic tanks
|
Good morning Dear Followers. We are back here. Ready to resume. Granite just arrived. 30 Tons
|
Tiles removal and screeding works and Electrical works
|
More views of the from the terraces. Master's and Family Lounge Terrace alike
|