PropertiesRe: Edo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op): 5:27pm On Apr 29, 2021
Reinforcement works

We have 14 pillars in the architectural design of this structure, the pillars have varying dimensions. The iron bender started work on the reinforcement from day one in line with the work schedule. 4 nos of 12mm were used for the main bars while 10mm spaced at 300mm c/c was used for the shear reinforcement (rings).

PropertiesRe: Edo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op): 5:16pm On Apr 29, 2021
Excavation continued

PropertiesRe: Edo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op): 5:13pm On Apr 29, 2021
Excavation

Excavation of the prepared site began after the completion of the setting out. The soil was excavated to a depth of 600mm and a width of 675mm , this follows best practice for bungalow foundations. The width of 675mm would help to properly spread the load of the building.

PropertiesRe: Monday Moltivations by Harneyprojects(op): 7:02pm On Apr 26, 2021
Call us today @08068396895 for a free quote

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
First floor Slab Construction

This stage of work involves constructing the first-floor slab and beams based on the structural design of the structure. For this structure, a combination of 16mm reinforcement bars, 12mm reinforcement bars and 10mm reinforcement bars was used. TMT reinforcement was used as it is closer to the design tensile stress of 410N/mm2 than the other reinforcements in the market ( KAM reinforcement is also a very nice choice of reinforcement ).

Formwork Placement
This involved the placement of formwork comprising of 1"x 12" planks ( Marine boards are better due to strength and straightness of the boards and should be used if the budget permits), 2'' x 4 '' woods and bamboo for suffix support. A team of 5 carpenters worked for 5 days to complete this task.

Reinforcement placement
Reinforcement was placed based on the structural drawings. 12mm bars served as both the main and distribution bars for the slab while a combination of 16mm bars and 12mm bars were used as the main bars in the beams for both the tensile and compression zones. 10mm bars were used as links for the beams.

Concrete Plcaement

This follows the completion of the formwork and reinforcement placement. The concrete was mixed to a mix ratio of 1:2:4 in order to achieve the design concrete strength of 25N/mm2. A concrete mixer and poker vibrator was used to achieve a well compacted and workable concrete mix during the concreting.

https://www.youtube.com/watch?v=YsjpXO6Ssvc

PropertiesRe: Monday Moltivations by Harneyprojects(op): 8:34am On Apr 19, 2021
Build | Design | Realestate

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 11:04am On Apr 16, 2021
Four bedroom pent house + two units of two bedroom flats

Sits perfectly on a 50ft x 100ft plot of land


Pent house -

4 ensuite bedrooms
Visitors toilet
Main lounge
Kitchen
Dining room


Two bedroom flats -
2 bedrooms
Main lounge
Dining room
Kitchen

PropertiesRe: Edo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op):
Foundation Works

-Setting out

-Excavation

-Leveling

-Foundation concrete works

-Blockwork

-Backfilling

-Damp Proof course


We start with the setting out


Setting out

The project commenced with the setting out operation to a transmit the site plan to the site.
The equipments used for the setting out are:-
- Building square
- Building working drawings
-Pegs
-profile board
-line
-marker
-nails
-hammer

The setting out operation took several hours but was completed once the last grid on the architural drawing was indicated on the profile board.

https://www.youtube.com/watch?v=HBcjUMaY3xU

PropertiesRe: Edo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op): 11:50am On Apr 15, 2021
youngestuk:
Starting to finish??
Yes sir
PropertiesRe: Edo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op):
The Construction team of 1 Coren registered engineer, Building technologist, carpenters, iron benders and other skilled artisans were dispatched to the site to execute the project located at Sabo-Gida, Edo state.
The team arrived late in the evening, work to commence the following morning

Due to the current cost of construction materials, its imperative for engineers, builders and architects to come together and look for solutions to drive down the cost of construction.
The most expensive and prevalent building material is cement, reducing the quality of cement in your structure can drive down the cost by 35%.
One of this solutions in reducing amount of cement in our structures is use of interlocking bricks which we would show later on in this thread

https://www.youtube.com/watch?v=0kom4pSWm90

PropertiesEdo-build Construction Diary Of A 4 Bedroom Bungalow In Sabo, Edo State by Harneyprojects(op):
Project Title: Residential Development Of a four bedroom bungalow

Project Location: Sabo-Gida, Edo state

Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com)

Client : Diasporan

Project cost: 23 million naira

PropertiesRe: Ceramic Floor And Wall Tilling Dairy For A Project In Asokoro, Abuja. by Harneyprojects(op):
The tilling works began from the first floor with the levelling operation with the use of water level/Dumpy level to ascertain the level of the floor screed (mixture of cement and sand )and obtain a uniform level all over the floor area. Once that is completed, a mixture of cement and water is poured over the screed floor to receive the tiles.

https://www.youtube.com/watch?v=bMICFjESjh8

PropertiesRe: Ceramic Floor And Wall Tilling Dairy For A Project In Asokoro, Abuja. by Harneyprojects(op):
This project involves the tilling works for a 5 bedroom duplex located at Asokoro, Abuja. The materials to be used are -

- Ceramic floor and wall tiles

- Sharp sand

-Cement

-Gum

-white cement

https://www.youtube.com/watch?v=z2VFqnKbV5I

PropertiesCeramic Floor And Wall Tilling Dairy For A Project In Asokoro, Abuja. by Harneyprojects(op): 4:18pm On Apr 14, 2021
Project Title: Ceramic Floor and wall tiling

Project Location: Asokoro, Abuja

Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com)

Client : *********

Tilling Area : 610 sqm

Project cost: 4 million naira

Project Duration: 17 days

PropertiesRe: Monday Moltivations by Harneyprojects(op): 11:06am On Apr 12, 2021
Let us build you a home

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 8:33am On Apr 05, 2021
Happy Easter from the Harneyprojects family

PropertiesRe: Complete Building Plan/design Needed by Harneyprojects: 3:48pm On Apr 04, 2021
dammykoga:
Hello,

Who can make an affordable building plan/design please? A contact needs you in Abuja,

Architectural, Structural, Electrical etc.

4 bedroom duplex. and 4 units of 2 bedroom flats Land size: 800sqm
Contact us via
WhatsApp /Call :08068396895
Email :Harneyprojects@gmail.com

You can visit our nairaland page showcasing some of our design @ https://www.nairaland.com/6006760/exhibition-3d-building-models

We are currently running a 10% discount promo on all of our services. Contact us today and enjoy our discounted price

PropertiesRe: Monday Moltivations by Harneyprojects(op): 1:35pm On Apr 04, 2021
Happy Easter from the Harneyprojects family

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
Ground floor construction
This involved masonry works, reinforcement works, carpentry works and concrete works.

Reinfrocement works
This involved the reinforcement works for the ground floor colunms and lintel . Y16mm reinforcement bars was used for the colunms with 10mm reinforcement bars for the links. The lintel had a combination of 12mm reinforcement bars and 10mm reinforcemnt bars for the links. The structural drawings for the columns indicated 4Y16 and the links are Y10 @ 200mm c/c . The lintel is also 4Y12 with links of Y10 @ 300mm c/c

Masonry works
This involved laying of 9'' and 6'' blocks bonded with mortar . The blocks are laid to the height specified in the architectural drawings . A combination of plum, line.,square and leveling instrument was used to ensure a well levelled block.

Capentry works

This involved the use of 1'' x12''x 12' , 1'' x 9'' x 12' , 1'' x 6'' x 12' machine sawed planks to cover the vertical sides and suffix of the lintels and colunms. A combination of 2'' x 4 '' woods and binding wire were used to brace the planks against failure.

Concrete works

This involved placement of insiitu concrete for the colunms and lintels. The mix ratio used was 1:2:4 and the concrete was well vibrated with a vibrating machine. A concrete mixer was used to ensure a consistent well mixed workable concrete.

The Ground floor stage concluded with the laying of the final four courses of blocks on the lintel taking the height to the level specified in the architectural design. The plumber works for the ground floor and first floor was done to the specifications in the mechanical drawings

N.B

Mortar is a mixture of cement and sand in a mix ratio of 1:6 , Mortar is used to bond the sancrete blocks to achieve the desired bond type. The sharp sand can be partly or fully replaced with stone dust in location where stonedust is ready available. Experiments have shown that the best replacement for sharp sand with stonedust is a 50% partial replacement , this is also the best for partial replacement of sharp sand in concrete.

https://www.youtube.com/watch?v=pBbDEFK4TNs

PropertiesMonday Moltivations by Harneyprojects(op): 9:46pm On Mar 22, 2021
www.harneyprojects.com

WhatsApp/call : 08068396895

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
Damp proof course (DPC )Works
This involved filling up the foundation voids with laterite of significant volume, compaction with a mechanical compactor, placement of hardcore, carpentry works and concrete works.
A damp proof membrane (DPM) was placed before concrete works to reduce the effect of the capillary action of moisture.

https://www.youtube.com/watch?v=uRhMXdQ9Fso

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 1:48am On Mar 17, 2021
Timberwolves:
that would be a rich concrete mix, keep it up

one more thing, how do you cope with workmanship? I have one site at pyakasa, opposite lugbe, the labourers n artisans in that axis aren't much professionals as per construction industry is concerned
We have a team of artisans with whom we have developed a working relationship over many years. They understand the quality we desire and they deliver accordingly.
PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
Timberwolves:
Job weldone

For the concrete, you used 1:2:4, is the ratio by weight or by volume? can you share more light on this ?
Thank you.

The concrete mixture for this project was done by volume using head pans/ wheel barrows.
1 bag of cement would can be poured into 2 head pans, therefore the mix ratio by headpans was fone by mixing 1 bag of cement : 4 head pans of sand : 8 head pans of gravel. We put as little water as possible while still maintaining a workable mixture because workability of concrete is very important in concrete placement.
For larger projects with significant concrete volume, harneyprojects employes the use of a batching plant where concrete is mixed by weight.
PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
Foundation blockwork
Blockwork preceded the foundation concrete works. It involved the placement of sancrete blocks on the strip footing bonded with mortar(a combination of cement and sharp sand (1:6). The blocks are laid to the Damp proof course (DPC) level specified in the architectural design. The specified height above Natural ground level (NGL) is 1.25m. The foundation blockwork was filled with concrete with a mix ration of 1:4:8

Foundation Colunms ,Pinth Beams and Damp proof course (DPC)

This involved reinforcement work, concrete works and carpentry works. The plinth beam became necessary due to the height of the foundation columns and was provided to prevent buckling

The reinforcement works was done to structural specifications and involved 4Y16 as main bars and Y10-200 c/c as shear reinforcement ( rings) for both the columns and plinth beam.

The carpentry works involved covering up the sides and providing bracing against failure. A combination of 1'' X 12' boards, 2'' x 4'' planks of wood and 3'' nails were used for the carpentry works.

The concrete was mixed to a mixed ratio of 1:2:4 conforming to the specified mix ratio in the structural design. The concrete was placed and compacted with a vibrating machine to avoid honeycomb and voids in the concrete.


N.B -
- ' sign denotes feet. An imperial system of measurement
- '' sign denotes inches. An imperial system of measurement

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
The main work began with the foundation.
FOUNDATION WORKS :

The setting out [/i]of the foundation was done using line, square, pegs, profile board, measuring tape and nails. The setting out team involved an engineer, builder and a carpenter.

[i]The excavation works [/i]preceded the conclusion of the setting out of which the buildings strip foundation was excavated to a depth of approx 1.2meter and width of 0.675m while the pad foundation was excavated to a depth of 1.4m and width of 1.2m. The excavation team involved a team of locally sourced labourers and the building technologist. The foundation involved a combination of stip foundation and pad foundation . The strip foundation would cater to the sancrete blocks walls while the pad foundation would cater to the columns which serve as part of the structural frame of the building.

[i]The Reinforcement work [/i]preceded the excavation. This involved a combination of 16mm,12mm and 10mm high yield TMT bars bent to the structural specification in the approved structural drawings. The reinforcement work for the pad base and columns were done and placed in the excavated foundation pit.

[i]The concrete works
involved mixing the concrete to a ratio of 1:2:4 using a concrete mixer and placed with wheelbarrows and shovels. A vibrating machine was used to ensure well-vibrated concrete. The strip footing has a thickness of 225mm while the pad footing has a thickness of 350mm


https://www.youtube.com/watch?v=85PUGjYVPy4

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 9:50am On Mar 14, 2021
The preliminaries work involved the construction of a store and drilling of a borehole
PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
The Construction team of 1 Coren registered engineer, Building technologist, carpenters, iron benders and other skilled artisans were dispatched to the site to execute the project.

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
The building approval process was done with Federal Capital Developement Authority (FCDA) . The lead Engineer ( Engr. A.P Saliu ) is a Coren Registered engineer and also a member of the Nigerian society of engineers(NSE) , his registration status lead to a smooth building approval process.

PropertiesKubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
Project Title: Residential Development Of a Block of Four units of 2bedroom flats

Project Location: Kubwa, Abuja

Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com)

Client : Nairalander

Project cost: 69 million naira

Project Duration: 7 months

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op):
Four blocks of 2 bedroom flats

Each block has -

2 ensuite bedrooms
1 Visitors toilet
Main lounge
Dining
Kitchen

Sits on a 50ft x 100ft plot of land

Check the thread below for the construction update and pictures
https://www.nairaland.com/6455070/kubwa-build-construction-diary-block-4

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 8:16pm On Sep 28, 2020
Four bedroom duplex + two units of two bedroom flats

Sits perfectly on a 50ft x 100ft plot of land


Four bedroom duplex -


4 ensuite bedrooms
Visitors toilet
Main lounge
Kitchen
Dining room


Two bedroom flats -

2 bedrooms
Main lounge
Dining room
Kitchen

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op):
Four bedroom duplex

4 ensuite bedrooms
Main lounge
Kitchen
Dining

Sits on a 25ft x 100ft plot of land

1 2 3 4 5 6 7 8 (of 8 pages)