Reinforcement works We have 14 pillars in the architectural design of this structure, the pillars have varying dimensions. The iron bender started work on the reinforcement from day one in line with the work schedule. 4 nos of 12mm were used for the main bars while 10mm spaced at 300mm c/c was used for the shear reinforcement (rings).
|
Excavation continued
|
Excavation Excavation of the prepared site began after the completion of the setting out. The soil was excavated to a depth of 600mm and a width of 675mm , this follows best practice for bungalow foundations. The width of 675mm would help to properly spread the load of the building.
|
Call us today @08068396895 for a free quote
|
First floor Slab Construction This stage of work involves constructing the first-floor slab and beams based on the structural design of the structure. For this structure, a combination of 16mm reinforcement bars, 12mm reinforcement bars and 10mm reinforcement bars was used. TMT reinforcement was used as it is closer to the design tensile stress of 410N/mm2 than the other reinforcements in the market ( KAM reinforcement is also a very nice choice of reinforcement ). Formwork Placement This involved the placement of formwork comprising of 1"x 12" planks ( Marine boards are better due to strength and straightness of the boards and should be used if the budget permits), 2'' x 4 '' woods and bamboo for suffix support. A team of 5 carpenters worked for 5 days to complete this task. Reinforcement placement Reinforcement was placed based on the structural drawings. 12mm bars served as both the main and distribution bars for the slab while a combination of 16mm bars and 12mm bars were used as the main bars in the beams for both the tensile and compression zones. 10mm bars were used as links for the beams. Concrete Plcaement This follows the completion of the formwork and reinforcement placement. The concrete was mixed to a mix ratio of 1:2:4 in order to achieve the design concrete strength of 25N/mm2. A concrete mixer and poker vibrator was used to achieve a well compacted and workable concrete mix during the concreting. https://www.youtube.com/watch?v=YsjpXO6Ssvc
|
Build | Design | Realestate
|
Four bedroom pent house + two units of two bedroom flats Sits perfectly on a 50ft x 100ft plot of land Pent house - 4 ensuite bedrooms Visitors toilet Main lounge Kitchen Dining room Two bedroom flats - 2 bedrooms Main lounge Dining room Kitchen
|
Foundation Works -Setting out -Excavation -Leveling -Foundation concrete works -Blockwork -Backfilling -Damp Proof course We start with the setting out Setting out The project commenced with the setting out operation to a transmit the site plan to the site. The equipments used for the setting out are:- - Building square - Building working drawings -Pegs -profile board -line -marker -nails -hammer The setting out operation took several hours but was completed once the last grid on the architural drawing was indicated on the profile board. https://www.youtube.com/watch?v=HBcjUMaY3xU
|
youngestuk:Yes sir |
The Construction team of 1 Coren registered engineer, Building technologist, carpenters, iron benders and other skilled artisans were dispatched to the site to execute the project located at Sabo-Gida, Edo state. The team arrived late in the evening, work to commence the following morning Due to the current cost of construction materials, its imperative for engineers, builders and architects to come together and look for solutions to drive down the cost of construction. The most expensive and prevalent building material is cement, reducing the quality of cement in your structure can drive down the cost by 35%. One of this solutions in reducing amount of cement in our structures is use of interlocking bricks which we would show later on in this thread https://www.youtube.com/watch?v=0kom4pSWm90
|
Project Title: Residential Development Of a four bedroom bungalow Project Location: Sabo-Gida, Edo state Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com) Client : Diasporan Project cost: 23 million naira
|
The tilling works began from the first floor with the levelling operation with the use of water level/Dumpy level to ascertain the level of the floor screed (mixture of cement and sand )and obtain a uniform level all over the floor area. Once that is completed, a mixture of cement and water is poured over the screed floor to receive the tiles. https://www.youtube.com/watch?v=bMICFjESjh8
|
This project involves the tilling works for a 5 bedroom duplex located at Asokoro, Abuja. The materials to be used are - - Ceramic floor and wall tiles - Sharp sand -Cement -Gum -white cement https://www.youtube.com/watch?v=z2VFqnKbV5I
|
Project Title: Ceramic Floor and wall tiling Project Location: Asokoro, Abuja Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com) Client : ********* Tilling Area : 610 sqm Project cost: 4 million naira Project Duration: 17 days
|
Let us build you a home
|
Happy Easter from the Harneyprojects family
|
dammykoga:Contact us via WhatsApp /Call :08068396895 Email :Harneyprojects@gmail.com You can visit our nairaland page showcasing some of our design @ https://www.nairaland.com/6006760/exhibition-3d-building-models We are currently running a 10% discount promo on all of our services. Contact us today and enjoy our discounted price
|
Happy Easter from the Harneyprojects family
|
Ground floor construction This involved masonry works, reinforcement works, carpentry works and concrete works. Reinfrocement works This involved the reinforcement works for the ground floor colunms and lintel . Y16mm reinforcement bars was used for the colunms with 10mm reinforcement bars for the links. The lintel had a combination of 12mm reinforcement bars and 10mm reinforcemnt bars for the links. The structural drawings for the columns indicated 4Y16 and the links are Y10 @ 200mm c/c . The lintel is also 4Y12 with links of Y10 @ 300mm c/c Masonry works This involved laying of 9'' and 6'' blocks bonded with mortar . The blocks are laid to the height specified in the architectural drawings . A combination of plum, line.,square and leveling instrument was used to ensure a well levelled block. Capentry works This involved the use of 1'' x12''x 12' , 1'' x 9'' x 12' , 1'' x 6'' x 12' machine sawed planks to cover the vertical sides and suffix of the lintels and colunms. A combination of 2'' x 4 '' woods and binding wire were used to brace the planks against failure. Concrete works This involved placement of insiitu concrete for the colunms and lintels. The mix ratio used was 1:2:4 and the concrete was well vibrated with a vibrating machine. A concrete mixer was used to ensure a consistent well mixed workable concrete. The Ground floor stage concluded with the laying of the final four courses of blocks on the lintel taking the height to the level specified in the architectural design. The plumber works for the ground floor and first floor was done to the specifications in the mechanical drawings N.B Mortar is a mixture of cement and sand in a mix ratio of 1:6 , Mortar is used to bond the sancrete blocks to achieve the desired bond type. The sharp sand can be partly or fully replaced with stone dust in location where stonedust is ready available. Experiments have shown that the best replacement for sharp sand with stonedust is a 50% partial replacement , this is also the best for partial replacement of sharp sand in concrete. https://www.youtube.com/watch?v=pBbDEFK4TNs
|
|
Damp proof course (DPC )Works This involved filling up the foundation voids with laterite of significant volume, compaction with a mechanical compactor, placement of hardcore, carpentry works and concrete works. A damp proof membrane (DPM) was placed before concrete works to reduce the effect of the capillary action of moisture. https://www.youtube.com/watch?v=uRhMXdQ9Fso
|
Timberwolves:We have a team of artisans with whom we have developed a working relationship over many years. They understand the quality we desire and they deliver accordingly. |
Timberwolves:Thank you. The concrete mixture for this project was done by volume using head pans/ wheel barrows. 1 bag of cement would can be poured into 2 head pans, therefore the mix ratio by headpans was fone by mixing 1 bag of cement : 4 head pans of sand : 8 head pans of gravel. We put as little water as possible while still maintaining a workable mixture because workability of concrete is very important in concrete placement. For larger projects with significant concrete volume, harneyprojects employes the use of a batching plant where concrete is mixed by weight. |
Foundation blockwork Blockwork preceded the foundation concrete works. It involved the placement of sancrete blocks on the strip footing bonded with mortar(a combination of cement and sharp sand (1:6). The blocks are laid to the Damp proof course (DPC) level specified in the architectural design. The specified height above Natural ground level (NGL) is 1.25m. The foundation blockwork was filled with concrete with a mix ration of 1:4:8 Foundation Colunms ,Pinth Beams and Damp proof course (DPC) This involved reinforcement work, concrete works and carpentry works. The plinth beam became necessary due to the height of the foundation columns and was provided to prevent buckling The reinforcement works was done to structural specifications and involved 4Y16 as main bars and Y10-200 c/c as shear reinforcement ( rings) for both the columns and plinth beam. The carpentry works involved covering up the sides and providing bracing against failure. A combination of 1'' X 12' boards, 2'' x 4'' planks of wood and 3'' nails were used for the carpentry works. The concrete was mixed to a mixed ratio of 1:2:4 conforming to the specified mix ratio in the structural design. The concrete was placed and compacted with a vibrating machine to avoid honeycomb and voids in the concrete. N.B - - ' sign denotes feet. An imperial system of measurement - '' sign denotes inches. An imperial system of measurement
|
The main work began with the foundation. FOUNDATION WORKS : The setting out [/i]of the foundation was done using line, square, pegs, profile board, measuring tape and nails. The setting out team involved an engineer, builder and a carpenter. [i]The excavation works [/i]preceded the conclusion of the setting out of which the buildings strip foundation was excavated to a depth of approx 1.2meter and width of 0.675m while the pad foundation was excavated to a depth of 1.4m and width of 1.2m. The excavation team involved a team of locally sourced labourers and the building technologist. The foundation involved a combination of stip foundation and pad foundation . The strip foundation would cater to the sancrete blocks walls while the pad foundation would cater to the columns which serve as part of the structural frame of the building. [i]The Reinforcement work [/i]preceded the excavation. This involved a combination of 16mm,12mm and 10mm high yield TMT bars bent to the structural specification in the approved structural drawings. The reinforcement work for the pad base and columns were done and placed in the excavated foundation pit. [i]The concrete works involved mixing the concrete to a ratio of 1:2:4 using a concrete mixer and placed with wheelbarrows and shovels. A vibrating machine was used to ensure well-vibrated concrete. The strip footing has a thickness of 225mm while the pad footing has a thickness of 350mm https://www.youtube.com/watch?v=85PUGjYVPy4
|
The preliminaries work involved the construction of a store and drilling of a borehole |
The Construction team of 1 Coren registered engineer, Building technologist, carpenters, iron benders and other skilled artisans were dispatched to the site to execute the project.
|
The building approval process was done with Federal Capital Developement Authority (FCDA) . The lead Engineer ( Engr. A.P Saliu ) is a Coren Registered engineer and also a member of the Nigerian society of engineers(NSE) , his registration status lead to a smooth building approval process.
|
Project Title: Residential Development Of a Block of Four units of 2bedroom flats Project Location: Kubwa, Abuja Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com) Client : Nairalander Project cost: 69 million naira Project Duration: 7 months
|
Four blocks of 2 bedroom flats Each block has - 2 ensuite bedrooms 1 Visitors toilet Main lounge Dining Kitchen Sits on a 50ft x 100ft plot of land Check the thread below for the construction update and pictures https://www.nairaland.com/6455070/kubwa-build-construction-diary-block-4
|
Four bedroom duplex + two units of two bedroom flats Sits perfectly on a 50ft x 100ft plot of land Four bedroom duplex - 4 ensuite bedrooms Visitors toilet Main lounge Kitchen Dining room Two bedroom flats - 2 bedrooms Main lounge Dining room Kitchen
|
Four bedroom duplex 4 ensuite bedrooms Main lounge Kitchen Dining Sits on a 25ft x 100ft plot of land
|