PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 12:33pm On Nov 11, 2021
#KugboBuild Foundation construction Video

https://www.youtube.com/watch?v=NdAr6_Xct08
PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 12:31pm On Nov 11, 2021
Damp proof course (DPC) formwotn and concrete placement
The DPC formwork was done with combinations of 1''x120 planks and 2'' *4'' Wood for bracing and concrete placement was done to a mixed ratio of 1:2 :4.

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 12:13pm On Nov 11, 2021
Laterite filling / Hardcore and Damp proof membrane (DPM) placement
Laterite filing and compaction of the filling with a mechanical compactor was done after completion of the blockwork.
After which hardcore and DPM were put in place.
The placement of DPM is a regularly neglected phase in the building construction industry in Nigeria, failure to put the DPM before casting of the damp proof floor (DPC) would allow rise of moisture through the foundation block work leading to damage of screeding and painting layers.

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 9:55am On Nov 09, 2021
Foundation Blockwork
The block work commenced 2 days after the concrete works of the pad and Strip
The blocks were laid in accordance with the foundation layout drawings.
Due to the depth of the foundation and carrying levels of the pad base, grade beams with depths of 300mm were introduced
The foundation blockwork was filled with concrete.

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 9:39am On Nov 09, 2021
Pad Base and Strip Base concreting.

The layman term for this phase of work is Blinding.
The Strip foundation that would carry the load of the foundation blockwork, dpc and ground floor blockwork has a depth of 225mm while the pad foundation that would carry the colunms, beams and slab has a depth of 350mm.
The concrete was mixed with a concret mixer and placement done with labourers. The concret had a mixed ratio of 1:2:4 ( One bag of cement : four head pan of sand : eight head pan of gravel) according to BS/NS code specifications.

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 10:23pm On Nov 07, 2021
abuuthmaan:
Make I siddon look
Welcome sir, Enjoy the show
PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 7:46pm On Nov 07, 2021
Reinforcement works
The structural design indicated the use of 20mm diameter rods for the colunms and 12mm diameter rods for the colunm bases.

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op):
Excavation of the foundation trenches and colunm bases commenced after the setting out operation.
The colunm bases had varying dimension from 1200mm x 1200mm, 1500mm x 1500mm and 1800mm x1500mm

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 8:15pm On Nov 05, 2021
Mini Estate comprising 6 units of 4 bedroom duplexes plus pent house
Each unit contains
4 ensuite bedrooms
Visitors toilet
Main lounge
Kitchen
Dining room

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 8:03pm On Nov 05, 2021
zoeA:
Anything building now for naija dey fear me o!
No be to build be the koko, na to get competent hands to supervise your building and buy standard building materials be the main wahala.
Check out the Nairaland Post, the guy been explain the major causes of building collapse
https://www.nairaland.com/4466821/major-causes-building-collapse-nigeria#66946220
PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op):
Work commenced on site, with the setting out operations one of the the units of 4 bedroom duplex plus pent house based on the site plan and foundation layout drawings.

PropertiesRe: #kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op): 7:36pm On Nov 05, 2021
The building approval was done in the office of the Federal Capital Developement Authority (FCDA) . The lead Engineer ( Engr. A.P Saliu ) being a Coren Registered engineer and also a member of the Nigerian society of engineers(NSE) made the whole process smooth
Properties#kugbobuild Construction Diary Of A Mini Estate in Kugbo, Abuja. by Harneyprojects(op):
Project Title: Residential construction of a Mini Estate comprising 6 units of 4 bedroom duplexes with pent house

Project Location: Kugbo, Abuja

Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com)

Client : ********

Project cost: 750 million naira

PropertiesRe: Ikoyi Building Collapse: LASEMA Rescue Another Person by Harneyprojects: 8:21am On Nov 02, 2021
In light of another building collapse, check the link below to get insights into causes of building collapse in Nigeria
https://www.harneyprojects.com/single-post/2018/04/22/major-causes-of-building-collapse-in-nigeria
PoliticsRe: Obiora Okonkwo: Russia Ready To Assist Nigeria Revamp Ajaokuta Steel by Harneyprojects: 7:41am On Sep 28, 2021
lalajnr:
https://www.google.com/url?q=https://www.vanguardngr.com/2021/09/russia-ready-to-assist-nigeria-revamp-ajaokuta-steel-okonkwo/&sa=U&ved=2ahUKEwj-l9bc6J_zAhUP3qQKHav5AOIQlO8DegQIBBAD&usg=AOvVaw2nlL8ArV0SVWjnHSXQlPf7
Harneyprojects wrote an article last year titled the " Ajaokuta steel company debacle". There is currently a glut of steel in the market due to excess production from china. The Nigerian government needs to do away with the Ajaokuta steel company due to foundational errors made while setting it up. You can read the article here https://www.harneyprojects.com/single-post/2018/05/27/ajaokuta-steel-industry-debacle
PropertiesRe: Setting Up A Sancrete Block And Stabilised Earth Brick Industry In Abuja by Harneyprojects(op): 11:24am On Sep 13, 2021
Next step was obtaining a storage space for cement and other working equipment.
The space would also the security and serve as an office.
The choice was between buying a berger container or building store with zince and wood.
We went in the direction if building a store as a cost saving alternative but buying a container would still ve necessary in the future.

PropertiesRe: Setting Up A Sancrete Block And Stabilised Earth Brick Industry In Abuja by Harneyprojects(op): 11:13am On Sep 13, 2021
The first step was obtaining a production location. Every business must be sighted close to a its market or source of raw materials as dictated in Economics 101.
A site was found in Kubwa close to a river that would seeve as a source of water.
A production site was leased for 6 months for a relatively fair amount.
PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 8:02pm On Sep 11, 2021
Four bedroom block of flats

Sits perfectly on a 60ft x 120ft plot of land

4 ensuite bedrooms
Visitors toilet
Main lounge
Kitchen
Dining room

PropertiesSetting Up A Sancrete Block And Stabilised Earth Brick Industry In Abuja by Harneyprojects(op): 10:20pm On Sep 10, 2021
This thread would follow harneyprojects ( www.harneyprojects.com ) as it attempts to set up an industry that would produce sancrete hollow blocks and stabilised earth bricks in Abuja.
PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 5:18pm On Jul 20, 2021
DESIGN | BUILD | REALESTATE

PropertiesRe: Ceramic Floor And Wall Tilling Dairy For A Project In Asokoro, Abuja. by Harneyprojects(op): 5:17pm On Jul 20, 2021
DESIGN | BUILD | REALESTATE

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 5:16pm On Jul 20, 2021
DESIGN | BUILD | REALESTATE

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 10:16am On Jul 01, 2021
Design | Build | Realestate

www.harneyprojects.com

Info@harneyprojects.com

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 10:14am On Jul 01, 2021
Design | Build | Realestate

www.harneyprojects.com

PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 6:14am On May 22, 2021
mufutau55:
This is lovely Sir.

Hajji M.
Thank you sir
PropertiesRe: Exhibition Of 3D Building Models by Harneyprojects(op): 12:26pm On May 21, 2021
A block of 8 units of 2 bedroom flats

Each unit has -

2 ensuite bedrooms
1 Visitors toilet
Main lounge
Dining
Kitchen

Sits on a 100ft x 100ft plot of land

PropertiesRe: Monday Moltivations by Harneyprojects(op): 11:25am On May 17, 2021
Build| Design |Realestate

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 3:30am On May 16, 2021
Roof covering pictures..

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 3:28am On May 16, 2021
More roofing pictures.

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 3:25am On May 16, 2021
Roof truss/ Roof covering

The roof truss was done with treated hardwood timber .The number used is listed below :-
2x6 @ 160pcs
2x4 @ 380pcs
2x3 @ 450pcs
2x2 @ 250pcs
nails 4" inches @ 4 carton
nail 3" inches @ 2 cartoon
sohangram @ 3 gallon

The roof covering used was 0.55mm thick aluminium shingle measuring 450sqm .

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op):
Roof beam/Concrete Facial

The roof beam as a depth of 300mm and reinforcement detail that involved the use of 12mm bars as the main bars and 10mm bars as the links.
Concrete facial with an horizontal/vertical pattern was used.
Concreting was done after the completion of the reinforcement and formwork placement

PropertiesRe: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects(op): 2:01pm On May 14, 2021
Roof Construction

This stage is divided into two units
- Construction of the roof beam/ concrete facial

- Construction of the Roof truss and placement of roof covering