New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. - Properties (18) - Nairaland

Nairaland ForumNairaland GeneralPropertiesNew Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. (43248 Views)

1 2 3 ... 15 16 17 18 19 20 21 Reply (Go Down)

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 6:55pm On Dec 22, 2020
Electrical wiring of this house is almost completed........

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 7:02pm On Dec 22, 2020
Coaxial cable for TV reception........ plus other cables coming out from socket positions.......

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by fabulous85: 7:19pm On Dec 22, 2020
spyder880:
Electrical wiring of this house starts.......
nice, please can you give me a rough estimate of the quantity or rolls of 1.5mm and 2.5mm that wired the whole house. it will really help me thanks
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 9:12pm On Dec 22, 2020
fabulous85:
nice, please can you give me a rough estimate of the quantity or rolls of 1.5mm and 2.5mm that wired the whole house. it will really help me thanks
We are still working. But this is the quotation he sent to me before we started the work.

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by omanzo02: 9:46pm On Dec 22, 2020
spyder880:
Rounding off all carpentry and iron works in preparation for the parapet concrete cast......
Spyder, is the parapet baskets iron works made with 12mm and 8mm iron rods?
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by fabulous85: 11:07pm On Dec 22, 2020
spyder880:
We are still working. But this is the quotation he sent to me before we started the work.
thanks alot
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 7:32am On Dec 23, 2020
fabulous85:
thanks alot
Yes they are.
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 12:52pm On Dec 29, 2020
We're starting the excavation of a toilet soakaway/septic tank system in this house as from today. More pictures later.
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 7:23pm On Dec 30, 2020
Marking out the soakaway space and starting the excavation works........

13 feet length
7 feet width
10 feet depth to the existing ground level

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 7:42am On Dec 31, 2020
Works on this soakaway system continues today.........
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 6:51pm On Jan 01, 2021
Still digging, but the workers are on a short holiday.

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by Badgers14: 1:20am On Jan 02, 2021
spyder880:
Still digging, but the workers are on a short holiday.
Just curious, why was the soak away system being done this late in the game?

I thought usually this things are done earlier before now?
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 7:35am On Jan 02, 2021
Badgers14:
Just curious, why was the soak away system being done this late in the game?

I thought usually this things are done earlier before now?
The season. We were waiting for the dry season when ground water will be at its lowest before we started to work on this, we had fears of hitting some water inside the ground if we had done this during the rainy season. This soakaway system was paid for about 6 months ago, but I had to delay it, of course with the consequence of paying more for cement and rods cheesy
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 8:55pm On Jan 03, 2021
We are going to continue with the soakaway system this week, plus arrangements for

Plumbing and sanitary wares
Cabinets
Painting
Electrical fittings
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 1:54pm On Jan 06, 2021
Digging deeper today, and buying more materialsfor the soakawaysystem.........

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 2:06pm On Jan 06, 2021
Starting to fit the wash room equipment........

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 7:55pm On Jan 08, 2021
We still dig deeper.......

Preparation of iron rods for columns.........

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 3:27pm On Jan 11, 2021
The soakaway system, today........
We are filling up all the block holes with lean concrete.

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op):
Fixing more washroom facilities .......

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by whirlwind7(m): 4:44pm On Jan 11, 2021
spyder880:
The soakaway system, today........
We are filling up all the block holes with lean concrete.
Why do you fill the block holes with concrete?
This is the first time I'm seeing something like this in a septic tank.
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 5:19pm On Jan 11, 2021
whirlwind7:
Why do you fill the block holes with concrete?
This is the first time I'm seeing something like this in a septic tank.
We do this in areas where there is a high water table. We add lean concrete into the block holes to strengthen the blocks since most of the blocks will be enmeshed in water most of the years.

We did this in another site this year.

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by whirlwind7(m): 5:57pm On Jan 11, 2021
spyder880:
We do this in areas where there is a high water table. We add lean concrete into the block holes to strengthen the blocks since most of the blocks will be enmeshed in water most of the years.

We did this in another site this year.
Oh, I get it now.
Thanks
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 11:05am On Jan 17, 2021
More pictures from this site later.
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 6:54am On Jan 19, 2021
Still working on the soakaway system........

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 8:05pm On Jan 21, 2021
Plastering works on the septic tank today.

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 8:44am On Jan 25, 2021
Apart from works on the soakaway system of this house. We have been working to complete the ceiling of this house. Painting and electrical fittings to follow immediately after.

More pictures later.
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 2:07pm On Jan 25, 2021
Completed stairway ceiling

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 2:10pm On Jan 25, 2021
Getting ready with paints.......

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by michlins(m): 2:24pm On Jan 25, 2021
spyder880:
Getting ready with paints.......
you go buy Sharon paints, you're sparing nothing oh on this house
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 2:40pm On Jan 25, 2021
michlins:
you go buy Sharon paints, you're sparing nothing oh on this house
My brother, they have served me well in some past projects. Although they just increased prices, I will patronize them because of their consistent quality.
Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 2:51pm On Jan 25, 2021
Plastered septic tank, ready for the decking..........

Re: New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. by spyder880(op): 11:05pm On Feb 01, 2021
We have completed the iron matting of this soakaway system, we even completed the concrete cast today...........

1 2 3 ... 15 16 17 18 19 20 21 Reply

New Construction Of A Block Of 4 Flats Of 3 Bedrooms At Awka, Anambra stateThe Awka Block Of 6 Flats Of 2 Bedrooms ProjectNumber Of Bedrooms In 50 By 100234

Tenant Sues Landlady For Refusing To Sell Her House To HimWhat Is The Difference Between Power Of Attorney And Deed Of Assignment???Prince Ebeano Supermarket In Lekki On Fire