Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / NewStats: 3,153,037 members, 7,818,065 topics. Date: Sunday, 05 May 2024 at 06:31 AM |
Nairaland Forum / Spyder880's Profile / Spyder880's Posts
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (of 1122 pages)
Properties / Re: The Property Investment and development Journal by spyder880(m): 2:43pm On Apr 02 |
Cement prices are gradually reducing. I bought cement for about N7,600 yesterday in Enugu. |
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 7:35am On Apr 01 |
We have completed the concrete cast of the floor that joined the basement decking, now we can form the walls of the first floor and take the walls to lintel height as soon as possible.................
|
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 7:32am On Apr 01 |
We made more blocks yesterday, until we ran out of space. We will have to use all the whole blocks on the ground so we can start more blocks production.............. 1 Like
|
Properties / Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(m): 7:29am On Apr 01 |
horlabiyi: Welcome.
|
Properties / Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(m): 10:47am On Mar 31 |
Installing more ceiling lights .............
|
Properties / Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(m): 10:31am On Mar 31 |
The main living room area, and all the works going on there.............
|
Properties / Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(m): 10:29am On Mar 31 |
Balconies, hallways................
|
Properties / Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(m): 10:27am On Mar 31 |
Let's look at the changes that has occurred at this project as we continue to work to complete this house................ Happy easter everyone. 3 Likes
|
Properties / Re: Buy Lands At A New Layout In Akpuoga Nike, Enugu. by spyder880(m): 10:14am On Mar 31 |
More pictures of this ongoing house, roofing will start later............. 1 Like
|
Properties / Re: Buy Lands At A New Layout In Akpuoga Nike, Enugu. by spyder880(m): 10:12am On Mar 31 |
We have been working on building up some rooms here on this land. This house will serve us for a lot of purposes, temporal estate office, site store, workers shelter. My mission is to keep a steady presence of my people on this land, I want people starting to live on this land so we can have the required presence and spark off the development we need. Other estates sharing boundaries with this land are also doing same. 1 Like
|
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 9:48am On Mar 31 |
We have been making a lot of blocks in the past weeks, by this week, we shall be laying a lot of blocks for the first floor walls................ 1 Like
|
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 5:42pm On Mar 28 |
More.........
|
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 5:39pm On Mar 28 |
Buying more materials for the next stages.............. Cement, sand, chippings coming in. 1 Like
|
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 4:04pm On Mar 28 |
horlabiyi: Some still use 12mm as long as it's a bungalow that wont carry a decking slab. 1 Like |
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 4:00pm On Mar 28 |
Completing the decking cast of the basement flat, moving to cast the DPC of the other side now.............
|
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 3:57pm On Mar 28 |
Badgers14: Where it is possible because of the design and the cost, doing the stairs last is better. This is because the stairs will have more time to cure and get ready for use, as against the system of casting stairs first. There may not be enough time left for concrete curing before the stairs will go into heavy use. 1 Like |
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 2:59pm On Mar 28 |
We have started the concrete cast for the decking.............
|
Properties / Re: The Property Investment and development Journal by spyder880(m): 2:57pm On Mar 28 |
Asquare84: Burnt bricks is another building option but it seems it's more costly to obtain and use these days because of energy costs. Plus the fact that due to internal conduit reasons for electrical and water supply convenience, the ordinary blocks are preferred than burnt bricks as a wall option. Sorry for replying late. |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 4:31pm On Mar 27 |
double3: Things are going haywire now, people are getting scared to take on more jobs. |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 8:11am On Mar 27 |
collele: Thank you bro. 1 Like |
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 7:21am On Mar 27 |
Iron reinforcement works for the slab, staircase preparation and other works completed.............
|
Properties / Re: Building Construction Of 8 Flats Of 3 Bedrooms + Basement At Onitsha by spyder880(m): 7:18am On Mar 27 |
Electrical pipes and other fittings for this basement decking already supplied...........
|
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:16am On Mar 27 |
double3: To build a normal soakaway system of about 12ft length, 7 feet width and 10 feet depth will cost about N850,000 in today's costs, materials, workmanship, etc. |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:14am On Mar 27 |
horlabiyi: You should wait for at least 4 days for the concrete to cure properly, however, if there were plans and the concrete was mixed to be used in a shorter period, 2 days will be enough. It's all about the mix. Thanks. |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:12am On Mar 27 |
collele: It's a small world bro, I pass the house regularly and even stand around the side to get better pictures of this house. It's a cool area, the neighbohood is gradually filling up. |
Autos / Re: Nigerian Used Toyota Tacoma 2001 For Sale In Enugu (SOLD) by spyder880(m): 8:34am On Mar 25 |
SOLD SOLD SOLD! 1 Like |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 4:01pm On Mar 24 |
Chidimercy: Use 16mm since cars will be passing on it. Please use a column base with a mat of at least 2 feet wide under each column. Doing the right thing will make your projects last without too much maintenance for the longest period. 1 Like |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 1:14pm On Mar 24 |
vastolord4: Good afternoon bro, there is no flood in the area of the 7 bedroom high ceiling house in Anambra. The house and fence is inside a fenced compound and the fringes of the concrete floor could be covered with carpet grass which is erosion resistant. As for this thread and the filling here, the land is naturally sloped to the back, we did a water drainage channel to wedge this sand fill from pushing against the back fence. Thank you Sir. 1 Like
|
Properties / Re: Buy Lands At A New Layout In Akpuoga Nike, Enugu. by spyder880(m): 4:02pm On Mar 20 |
Work on the rooms we are building here have got to advanced stages, I an also building a dwarf wall to demarcate this land from the next estate we share a bound with. I acquired a new land as road access into this land to prevent a situation where we will run into issues with other people who owns lands in this area. This whole area is getting a lot of interest from land investors. 3 Likes |
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 6:38am On Mar 20 |
More pictures from the compound........
|
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 6:20am On Mar 20 |
More pictures of the compound.............
|
Properties / Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 6:17am On Mar 20 |
The sand filling of this compound had since started..........
|
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (of 1122 pages)
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 31 |