The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 4:51am On Jun 19, 2015
This thread is being opened to document the building process for a new residential duplex with penthouse on top. Details of the project;

Project: The construction of a duplex with a penthouse
Location: Port Harcourt City, Rivers state.
Client: A Nigerian
Contractor: Tigerkenn Homes Ltd.
Project Duration: 120 days
Budget: To be released later

Contractor's contact info Tigerkenn Homes Ltd, Phone number 08033350750, 07081821271 or send a mail to ckenneths@yahoo.co.uk

2 Likes 1 Share

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 4:52am On Jun 19, 2015
These are the first pictures from this site on the first day of visit.

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 4:52am On Jun 19, 2015
When you come for a site inspection, it is advised you keep your eyes very open. As an experienced person, you are to watch out and document all observations. First, this vegetation, this lush green grass is indicative of what might be found underground. This is what we call the walk-over survey.

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 4:53am On Jun 19, 2015
I had to return to this site to do a site test to assure me of the type of soil characteristics we are going to be working on. To help me, a site test has been carried out for this land, but I am not taking any chances, I want my own independent testing. So I ordered a dig.

I got ground water at about 1.2 mts, we closed for the day, more observation to be carried out later.

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 4:54am On Jun 19, 2015
Of course we came back and cleared this site of all grass, in preparation for the start of the foundation.....

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 4:54am On Jun 19, 2015
ssssfg
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by podosci(m): 5:00am On Jun 19, 2015
How much did you budget for the site clearance and excavation of top vegetative soil?
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:02am On Jun 19, 2015
podosci:
How much did you budget for the site clearance and excavation of top vegetative soil?

N25k
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by podosci(m): 5:23am On Jun 19, 2015
Keep us uptodate with photos and written updates....Whats the size of the plot
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by podosci(m): 5:25am On Jun 19, 2015
What was the bearing capacity you used in your design? and now seeing the nature of the soil on ground, how would you effect it on your already designed foundation
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:35am On Jun 19, 2015
podosci:
What was the bearing capacity you used in your design? and now seeing the nature of the soil on ground, how would you effect it on your already designed foundation

The objective is to carry out an independent survey irrespective of earlier reports. This will help to design the foundation. Tests are still in progress.
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:37am On Jun 19, 2015
There are little things we should not ignore while inspecting a site or documenting your findings, this black line got me thinking.......

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by podosci(m): 5:38am On Jun 19, 2015
okay sir....Nice work, hoping to learn a lot from your post
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:42am On Jun 19, 2015
podosci:
Keep us uptodate with photos and written updates....Whats the size of the plot

This land measures about 462 sq.mts.

1 Like

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:42am On Jun 19, 2015
podosci:
okay sir....Nice work, hoping to learn a lot from your post

Welcome bro.

1 Like

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:45am On Jun 19, 2015
Still observing the test excavation for water levels as we prepare to start.

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 5:49am On Jun 19, 2015
There is also a visible flow of water around the land, not too strong a flow but equally important to note. We plan to start the construction from next week.

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by podosci(m): 2:41pm On Jun 19, 2015
The site looks water logged but it would be interesting to see the type of foundation you choose to proceed with
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by tranxo(m): 6:51pm On Jun 21, 2015
spyder880:
There is also a visible flow of water around the land, not too strong a flow but equally important to note. We plan to start the construction from next week.
Looks like a case of previous land filling.
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 7:27pm On Jun 23, 2015
We are still planning to start work on this site. I dropped a trip of filling sand here to fill the portion where I am going to build a site store/workers room. This is to prevent a situation where the water level rises as the rains increase and start to mess up my supplies, especially cement.

2 Likes

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by twinskenny(m): 9:46pm On Jun 23, 2015
Boss... we are still here. weldone sir

1 Like

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by plasgidy: 10:22pm On Jun 23, 2015
Spydoo congrats, Jehovah has done it again more oil to your engine.

1 Like

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 12:06am On Jun 24, 2015
twinskenny:
Boss... we are still here. weldone sir

plasgidy:
Spydoo congrats, Jehovah has done it again more oil to your engine.

Thank you my people.
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by francizy(m): 12:21am On Jun 24, 2015
Following wholeheartedly.. cheesy
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by EndiaSami: 10:20am On Jun 24, 2015
Well done sir sypder. More blessings coming our way...#classinsession
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 11:21am On Jun 24, 2015
francizy:
Following wholeheartedly.. cheesy
EndiaSami:
Well done sir sypder. More blessings coming our way...#classinsession

My People, I thank you all.
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 11:24am On Jun 24, 2015
Now, we start to fill the portion. .......

1 Like

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by podosci(m): 10:13pm On Jun 24, 2015
whats your long term solution for the water logged site?
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by francizy(m): 11:32pm On Jun 24, 2015
spyder880:



My People, I thank you all.

Dear Spyder880,

I've been following you here and on your blog, I wish to get make some enquiries from you, therefore, can you help me with some important information as regards to welding?
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by spyder880(m): 7:18am On Jun 25, 2015
podosci:
whats your long term solution for the water logged site?

I plan to build a foundation that will be suitable for the environment and the building. This will mean that some sections of the foundation will be done with raft. Its either we

1. Do a normal 150mm concrete blinding, let the column starter bars stand on 300mm pads as column bases (very tall starter bars to allow for a high foundation)
2. Use wood to form another 225mm high reinforced concrete beam, cast it right on top of the blinding and column bases.
3. Do a high block wall foundation to keep the building floor as far away from water and dampness as possible
4. Damp proofing with thick nylon sheets
5. Build another 225mm concrete beam on top of the blocks before casting the over site concrete floor. (German Floor)
6. Fill the compound with enough soil to prevent water flows coming near the foundation footing.

This plan is subject to change as I am delaying a bit to monitor the environment more.

2 Likes

Re: The Making Of "The Port Harcourt Duplex + Penthouse" by youngterry: 12:40am On Jun 27, 2015
Hello Oga Spyder and other Oga's in the house. I am about to start up my other project which is a twin four flat storey building (8flats). The two buildings are going to be built in a 100 by 100 land at Amagba in Benin City. Please kindly help me check out the quotations the engineer gave me. for each of the building. I think the measurement of each building is 25200 by 9750 and 26225 by 10500.


ESTIMATE FOR FOUNDATION WORKS
Setting out 30000
Land clearing 10000
Pegs and profile 15000
Total 55000

FOUNDATION WORKS
Labour for Digging 40000
Labour for Foundation base casting 40000
50 bags of Cement @2000- 100000
3-Sharp sand @15000- 45000
Water 6000
15 tons granite - 65000
Total 296000

DPC BLOCKWORK
6"Blocks 2000
Block laying Labour@50per block -100000
20 bags of cement@2000 -40000
2 trips of sharp sand @15000- 30000
1 tank of Water 6000
Total -176000

IRON WORKS
12mm for column Baskets 16 lengths@1250-20000
12mm for Starter bars 20 lengths@1250-25000
12mm for Extension columns 30 lengths@1250-37500
8mm for Stirrups 30 lengths@800-24000
1 roll of Binding wire 6000
Iron bender 30000
Total 142500

WOOD
15 1*12 planks @1250-18750
5 2*2 wood for bracing @450-2250
3"Nail 6000
Carpenter labour 10000
Total 37000

5" THICK DPC SLAB
15 tons of granite @65000
4 trips of sharp sand @15000-60000
20 trips of filling sand @8000-160000
Sand filling labour 40000
Ramming 8000
2 tanks of Water for wetting after sand filling 12000
70 bags of cement @2000-136500
Machine Floor casting 80000
Total 565000

SUPERVISION 200,000

SUPERSTRUCTURE WORK TO LINTEL
SUPERSTRUCTURE WORK TO LINTEL
BLOCKWORK
Blocks 3000
Cement 30bags@2000 -60000
Block Labour@50per block 150000
Water 1 tank 6000
2 trips of Sand 30000
TOTAL - 246000

IRON FOR LINTELS
25y12mm @1250-31250
10 y8mm@800 -8000
1/2 Binding wire 3000
Iron bender 20000
TOTAL - 62250

LINTEL/COLUMN CASTING
Casting labour 15000
Sand 1/2 trip @7500-7500
Granite 15tons @65000
Cement 15 bags@2000 30000
Water 1/2 tank 3000
TOTAL - 120500

Wood
20 planks @1250--25000
5 2*2 wood @ 450- 4750
1 bag of nail 5000
Carpenter 10000
Supervision 100000
Miscellaneous - 100000

Total cost - 2145000

This estimate is for one of the building.
Re: The Making Of "The Port Harcourt Duplex + Penthouse" by wunmite90: 7:24am On Jun 27, 2015
youngterry:
Hello Oga Spyder and other Oga's in the house. I am about to start up my other project which is a twin four flat storey building (8flats). The two buildings are going to be built in a 100 by 100 land at Amagba in Benin City. Please kindly help me check out the quotations the engineer gave me. for each of the building. I think the measurement of each building is 25200 by 9750 and 26225 by 10500.


ESTIMATE FOR FOUNDATION WORKS
Setting out 30000
Land clearing 10000
Pegs and profile 15000
Total 55000

FOUNDATION WORKS
Labour for Digging 40000
Labour for Foundation base casting 40000
50 bags of Cement @2000- 100000
3-Sharp sand @15000- 45000
Water 6000
15 tons granite - 65000
Total 296000

DPC BLOCKWORK
6"Blocks 2000
Block laying Labour@50per block -100000
20 bags of cement@2000 -40000
2 trips of sharp sand @15000- 30000
1 tank of Water 6000
Total -176000

IRON WORKS
12mm for column Baskets 16 lengths@1250-20000
12mm for Starter bars 20 lengths@1250-25000
12mm for Extension columns 30 lengths@1250-37500
8mm for Stirrups 30 lengths@800-24000
1 roll of Binding wire 6000
Iron bender 30000
Total 142500

WOOD
15 1*12 planks @1250-18750
5 2*2 wood for bracing @450-2250
3"Nail 6000
Carpenter labour 10000
Total 37000

5" THICK DPC SLAB
15 tons of granite @65000
4 trips of sharp sand @15000-60000
20 trips of filling sand @8000-160000
Sand filling labour 40000
Ramming 8000
2 tanks of Water for wetting after sand filling 12000
70 bags of cement @2000-136500
Machine Floor casting 80000
Total 565000

SUPERVISION 200,000

SUPERSTRUCTURE WORK TO LINTEL
SUPERSTRUCTURE WORK TO LINTEL
BLOCKWORK
Blocks 3000
Cement 30bags@2000 -60000
Block Labour@50per block 150000
Water 1 tank 6000
2 trips of Sand 30000
TOTAL - 246000

IRON FOR LINTELS
25y12mm @1250-31250
10 y8mm@800 -8000
1/2 Binding wire 3000
Iron bender 20000
TOTAL - 62250

LINTEL/COLUMN CASTING
Casting labour 15000
Sand 1/2 trip @7500-7500
Granite 15tons @65000
Cement 15 bags@2000 30000
Water 1/2 tank 3000
TOTAL - 120500

Wood
20 planks @1250--25000
5 2*2 wood @ 450- 4750
1 bag of nail 5000
Carpenter 10000
Supervision 100000
Miscellaneous - 100000

Total cost - 2145000

This estimate is for one of the building.

Actually d prices he gave you for each material are fair to me. But not sorry to say this. Your building will be of low quality

First of all d guy is planning to use just 2000 blocks for the foundation of 2flats ( since its 2 down 2 up) if my calculations are right it means he will only be digging into the ground by just one or one and half feet. Dats bad. People do it. But its bad construction and also u should try to be atleast 2feet off ur natural ground level ( cos of other works). Dat numbers of block can't get u dat level.

2. He has plans to set 100 blocks with a bag of cement. Pls don't allow him to do dat. Don't be penny wise and pounds foolish.


3. I recomend a minimum of 16mm bars for column (pillar) reinforcements. Thr is a way to arrange 12mm bars dat it will be equal to d strength that 4 16mm bars will give u but seeing the guy is already planing to use 100 blocks to a bag of cement I am guessing he will also use just 4 12mm bars in the columns (pillars)

He is nice to you on d prices. Except 4 cement you can get dat 4 less

But you will be building a serious low quality and unsafe house

I dint even see d 6inch block b4. Ar u sure u called an Engineer?

5 Likes 2 Shares

(1) (2) (3) (Reply)

Become a Land owner With Just #630,000 @ Havilah Park & Garden Mowe / Tiwa Commercial Hub Strategically Located Few Mins To The New Airport / Land Without Document

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 42
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.