Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 2:08pm On Jan 05, 2017 |
Pictures of blinding
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 2:10pm On Jan 05, 2017 |
More pictures
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 7:57am On Jan 06, 2017 |
Good morning all. we'll be resuming work this morning with reinforcement of floor slab(german floor). pictures coming shortly. stay tuned |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:38pm On Jan 07, 2017 |
Pictures loading
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:39pm On Jan 07, 2017 |
More pictures of reinforcement
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:43pm On Jan 07, 2017 |
Levelling instrument stationed to take final level 1 Share
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 5:34pm On Jan 07, 2017 |
German floor casting
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:39am On Jan 09, 2017 |
Good morning and happy new week. We'll continue with block wall and reinforcement for columns, but before I start posting the pictures, here is the cost of foundation Setting out Profiles, pegs, lines, nails etc -----#45,000 Labour for blinding --------#15,000 Reinforcement work 2 tonnes of 16mm 4 tonnes of 12mm 2 tonnes of 10mm 3 bundles of binding wire Labour-------#240,000 formwork 50 nos of 1x12 wood(35 nos for base and 15 nos for sides of German floor) 30 nos of 3x4 wood 1 bag of 3" nail 3 packet of 3" concrete nail Labour ----------#30,000 Raft wall Labour for steel panel work----#120,000 Concrete work 200 bags of cement 60 tonnes of 3/4" granite 40 tonnes of sharp sand Labour--------#120,000 Note: the cost has being lump up from setting out to floor slab(german floor). |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:43am On Jan 09, 2017 |
Pictures 1 Like 1 Share
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:46am On Jan 09, 2017 |
Column reinforcement being prepared
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 12:23pm On Jan 09, 2017 |
temmy6996: Well-done. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:51pm On Jan 09, 2017 |
segzy14:Thanks boss |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 9:15pm On Jan 10, 2017 |
Day 1 of block work
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:28am On Jan 12, 2017 |
Block work completed. Taking levels for lintels
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:30am On Jan 12, 2017 |
More pictures
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 11:56am On Jan 12, 2017 |
This is very good work, I'm impressed. 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 7:01pm On Jan 12, 2017 |
EgunMogaji: thanks so much sir, I appreciate |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 7:04pm On Jan 12, 2017 |
temmy6996: You're welcome. You've sold me on the below ground work. Looking forward to the final finishing. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by twinskenny(m): 7:50pm On Jan 12, 2017 |
temmy6996: nice and neatly done... good luck sir |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Flaghouse1: 9:32pm On Jan 12, 2017 |
Inspiring job, I really like the cleanliness of the site and the application of lean management technique in your job All the best |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by mufutau55(m): 10:28pm On Jan 12, 2017 |
EgunMogaji: We are all keenly following this guy... Impressive. Hajji M. 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 11:01pm On Jan 12, 2017 |
mufutau55: And this is a prime example of what I try to tell newcomer builders on here with different schemes. The path to success is simple and straight forward. 1) Introduce yourself with full contacts. 2) Let your work speak for itself. Show a build with detailed pictures. Quality and detailed work that shows pride of workmanship. 3) Then you'll have to beat customers back from too much work. Easy peasy. 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by mufutau55(m): 11:33pm On Jan 12, 2017 |
EgunMogaji: Agreed 1m %. Well said sir. Hajji M. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 8:31am On Jan 13, 2017 |
EgunMogaji: I'm flattered sir. will definitely do justice to the finishings, God willing 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 8:32am On Jan 13, 2017 |
twinskenny:Thanks so much |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 2:39pm On Jan 16, 2017 |
Good afternoon, we'll continue with the lintel works. Pictures coming in
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 8:28am On Jan 17, 2017 |
More pictures 1 Like
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:58am On Jan 17, 2017 |
We continue with 3 courses of block work after lintel. Pictures coming in shortly. Criticism allowed please |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:10pm On Jan 17, 2017 |
Pictures
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 4:25pm On Jan 17, 2017 |
Nice one |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 5:05pm On Jan 17, 2017 |
temmy6996: Your bricklayers are brilliant wizards. Please salute them for me. 4 Likes |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 8:39pm On Jan 17, 2017 |
EgunMogaji: thanks so much sir, will do that, but this is also as a result of close supervision sir. 2 Likes |
Distress Sale Of 900sqm Land At Mayfair Garden Estate Lekki 27m / Are You In The Building Industry? Don't Miss This Event / How Do I Identify Quality Stone Coated Roofing Tile in Nigeria Market?
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 29 |